Han xiong company introduction
Han xiong heating technology LTD, Was established in 2004.It is a professional company of heating system engineering Company devotes to the boiler's sales, installation and service system and Heating technology development and application.With sales department, technology department, engineering department, after-sale service, contract, etc, with 38 employees, including bachelor degree personnel, senior technical accounted for 70% of the staff have five titles, gathers the design, installation and debugging of professional talents.Especially is Technology and construction site personnel, all have years of experience, a number of projects in the operation.At present, the company is in Shanghai and its neighboring region has successfully run multiple projects.Such as Shanghai(ruijin)hospital, American LuBoRun Shanghai chemical plant, American national starch Shanghai factory, Shanghai Kowloon hotel,(LianYang)ibis hotel,(yuyuan)hotel,(jiangshan)building projects.Each year, company growth more than 30% of the growing business, is a vigorous
professional heating company.Long-term since, adhering to the “integrity, service first” principle, Exploration and the pursuit of excellence, solid technical strength, excellent performance products manifest, Establish credit market image, for clients to create the perfect project, obtain approval and praise of customers.3、Boiler manufacture and acceptance criteria.4、Construction scheme.The first chapter
formulation explanations
Project profile
This project is add steam boiler and accessory equipment procurement projects, heat by Italian law Laurie wholly owned company production of steam boiler unit
Power: 4200kw.The second Chapter
project goals
Quality target:good
★ Project goals:Total duration of 30 days.★
Safe civilized construction goal:Shanghai site.Jiaxing
comprehensive site.The Third Chapter:
The construction period
1.Total duration
This commencement notice shall prevail, according to owner according to the actual date for 30 days total duration.In combination with the engineering characteristics, and similar project construction experience, after carefully calculated out.2.Labor investment plan Companies provide labor in this project.According to the safety and guarantee the construction progress Arrange labor.This project construction for six people , the labor into exits according to different parts of the project.The fourth chapter
construction organization and project management First, the project period is expected to 30 days, the condition of construction etc.Including:
1、Before installation: 2 the open-package inspection and acceptance of the equipment, the inspection and calibration equipment
foundation, 3 The main equipment and auxiliary equipment 4.Boiler flue system of manufacture and installation.1.Engineering construction qualifications.Construction in the boiler room must end, namely basic civil work within the plant has been completed, and paint floor level.Used in construction of electricity(mechanical construction electricity)has been connected to the site or will be able to connect to the site is more convenient.And lighting electricity, lamps and lanterns is complete.To ensure the normal operation of the construction of party A, please provide constructors or placed tools and equipment parts storage room unpacking after a set of boiler(or lock).2.The construction organization and personnel Project management personnel: 3.The boiler installation process To ensure the engineering quality, provide excellent service, Our company strictly according to my except the fuel gas boiler installation process, also must, in accordance with the construction of factory of boiler installation of boiler design drawings and technical documents, product quality documents, installation and operation manuals and design institute of design Draw judge, formulate the best installation process(installation process).The boiler installation scheme(basically with arrangement for sequence)
The fifth chapter : Construction quality control measures and quality detection First, quality assurance measures The engineering practice merit goal management, the construction personnel firmly established “quality first” consciousness, To ensure the project reach Shanghai qualified projects.Second, the flue engineering quality guarantee measures Ⅰ accurate location, bury should level off.Ⅱ
Tubes shall be closely contact, Fixed firmly Ⅲ No hot elongated pipe-hangers, should be installed vertically rods Ⅳ A heat pipe suspenders elongation, the reverse direction to thermal expansion ⅤFixed in the building structure pipe, hanger, shall not affect the safety of the structure Ⅵ scaffolds shall conform to the provisions of the distance.The Sixth chapter: Safety Caution Before installation should be tried in crane, leave the ground in the
boiler should be suspended after checking whether the rigging safe, reliable, Welding and geo-drilling must be strictly implemented operation system, due to special guard over homework, Entering the site must wear a helmet.Banned hidden construction, fatigue, Prohibit thrown tools, pipe, prevent scarred, Accidents control target as zero accidents.5、delivery Delivery:
period: Boiler equipment 45 days after the signing of the contract, the installation period 35 days
汉雄公司介绍
Han xiong company introduction
汉雄热力技术有限公司成立于2004年,是一个从事供暖系统工程的专业公司。
Han xiong heating technology LTD, Was established in 2004.It is a
professional company of heating system engineering 公司致力于锅炉的销售、系统安装、售后服务以及暖通技术的开发与运用。
Company devotes to the boiler's sales, installation and service system and Heating technology development and application.设有销售部、技术部、工程部、售后服务部、合约部等,拥有38名员工,其中本科或本科以上学历人员占70%,具有高级技术职称的员工有5名,汇集了锅炉设计、安装、系统调试的专业人才。With sales department, technology department, engineering department, after-sale service, contract, etc, with 38 employees, including bachelor degree personnel, senior technical accounted for 70% of the staff have five titles, gathers the design, installation and debugging of professional talents.特别是技术和现场施工人员,均有多年丰富的工作经验,参与过多个项目的操作。
Especially is Technology and construction site personnel, all have years of experience, a number of projects in the operation.目前,公司在上海及周边地区已成功运作多个项目,At present, the company is in Shanghai and its neighboring region has successfully run multiple projects 例如上海瑞金医院,美国路博润上海化工厂,美国国民淀粉上海工厂,上海九龙宾馆,联洋宜必思酒店,豫园大酒店,江山大厦等项
目。
Such as Shanghai(ruijin)hospital, American LuBoRun Shanghai chemical plant, American national starch Shanghai factory, Shanghai Kowloon hotel,(LianYang)ibis hotel,(yuyuan)hotel,(jiangshan)building projects.公司成长性良好,每年业务量增长30%以上,是一个充满朝气的专业供暖公司。
Each year, company growth more than 30% of the growing business, is a vigorous professional heating company.长期以来,公司本着“诚信第一,细致服务”的原则,不断探索,追求卓越;凭着扎实的技术实力,彰显产品的卓越性能,树立诚信的市场形象,为客户创造完美的工程,获得广大客户的认可和赞赏。
Long-term since, adhering to the “integrity, service first” principle, Exploration and the pursuit of excellence, solid technical strength, excellent performance products manifest, Establish credit market image, for clients to create the perfect project, obtain approval and praise of customers.3、锅炉制造、验收标准
Boiler manufacture and acceptance criteria
4、施工组织方案 Construction scheme
第一章 编制说明
The first chapter formulation explanations 工程概况
Project profile 本工程为加蒸汽锅炉及其附属设备采购项目,热源由意大利法罗力独资公司生产的蒸汽锅炉机组,功率为: 4200kw。
This project is add steam boiler and accessory equipment procurement projects, heat by Italian law Laurie wholly owned company production of steam boiler unit
Power: 4200kw.第二章 工程目标
The second Chapter
project goals
质量目标:优良。
Quality target:good ★工期目标:总工期30工作日。
Project goals:Total duration of 30 days.★安全文明施工目标:上海市标准化工地。嘉兴市综合治理达标工地。Safe civilized construction goal:Shanghai site.Jiaxing comprehensive site.第三章 工程工期
The Third Chapter: The construction period
1.总工期设定
1.Total duration
本工程开工按业主通知为准,按实际日期计算总工期为30工作日。结合工程特点,以及类似工程的施工经验,经过认真计算而编制的。
This commencement notice shall prevail, according to owner according to the actual date for 30 days total duration.In combination with the engineering characteristics, and similar project construction experience, after carefully calculated out.2.劳动力投入计划
2.Labor investment plan 本工程所需劳动力均由公司提供。根据安全和保证施工进度安排劳动力投入。
Companies provide labor in this project.According to the safety and guarantee the construction progress Arrange labor.本工程计划施工人数为6人,劳动力的进退场根据工程的不同部位作调整。
This project construction for six people , the labor into exits according to different parts of the project.第四章 施工组织、工程管理
The fourth chapter
construction organization and project management 第一、工程期预期30个工作日,根据施工所具备的条件以次类推。
First, the project period is expected to 30 days, the condition of construction etc.包括:
1、安装前的准备;
2、设备的开箱检查和验收,各设备基础的检查和校正;
3、各主要设备和辅助设备的就位;
4、锅炉烟道系统的制作及安装。
Including:
1、Before installation: 2 the open-package inspection and
acceptance of the equipment, the inspection and calibration equipment foundation, 3 The main equipment and auxiliary equipment 4.Boiler flue system of manufacture and installation.1.工程施工所具备的条件。
1.Engineering construction qualifications.工程施工必须在锅炉房土建工作基本结束,即厂房内粉刷已经完成,且地坪平整。各设备的土建基础已达设计强度的75%。
Construction in the boiler room must end, namely basic civil work within the plant has been completed, and paint floor level.施工中所用的电(机械施工用电)已接至现场或将能够较方便地接至现场。并且照明用电、灯具齐全。
Used in construction of electricity(mechanical construction electricity)has been connected to the site or will be able to connect to the site is more convenient.And lighting electricity, lamps and lanterns is complete.为保证施工的正常进行,请建设方或甲方提供放置工具和设备开箱后的零部件存放室一间(或锅炉房设门锁)。
To ensure the normal operation of the construction of party A, please provide constructors or placed tools and equipment parts storage room unpacking after a set of boiler(or lock).2.施工的组织与人员
2.The construction organization and personnel 工程的管理人员:
Project management personnel: 3.锅炉的安装工艺
3.The boiler installation process
为保证工程的质量,为用户提供优秀的服务,我们除了严格按照我公司的燃油、燃气锅炉安装工艺进行施工外,还必须按照锅炉厂出厂的锅炉安装的技术文件、设计图纸、产品质量文件、安装和使用说明书、以及设计院所设计的图纸进行认真的会审,从中制定出最佳安装工艺。(安装工艺略)锅炉的安装方案。(基本上以排列为序)
To ensure the engineering quality, provide excellent service, Our company strictly according to my except the fuel gas boiler installation process, also must, in accordance with the construction of factory of boiler installation of boiler design drawings and technical documents, product quality documents, installation and operation manuals and design institute of design Draw judge, formulate the best installation process(installation process).The boiler installation scheme(basically with arrangement for sequence)第五章 施工质量保证措施、质量检测
The fifth chapter : Construction quality control measures and quality detection 第一、质量保证措施
First, quality assurance measures 本工程实行创优目标管理,全体施工人员牢固地树立起“质量第一”的意识,确保本工程达到上海市合格工程。
The engineering practice merit goal management, the construction personnel firmly established “quality first” consciousness, To ensure the project reach Shanghai qualified projects.第二、烟道工程质量保证技术措施
Second, the flue engineering quality guarantee measures Ⅰ位置正确,埋设应平整牢固。
Ⅰ accurate location, bury should level off.Ⅱ与管接触应紧密,固定应牢固。
Ⅱ Tubes shall be closely contact, Fixed firmly Ⅲ无热伸长的管道吊架,吊杆应垂直安装。
ⅢNo hot elongated pipe-hangers, should be installed vertically rods Ⅳ有热伸长的管道吊杆,应向热膨胀的反方向偏移。
A heat pipe suspenders elongation, the reverse direction to thermal expansion Ⅴ固定在建筑结构上的管道支、吊架,不得影响结构的安全。ⅤFixed in the building structure pipe, hanger, shall not affect the safety of the structure Ⅵ支架的距离应符合规定。
Ⅵ scaffolds shall conform to the provisions of the distance.第六章 安全注意事项
The Sixth chapter: Safety Caution 在吊装前应进行试吊,在锅炉离开地面后应暂停检查索具是否安全可靠;
Before installation should be tried in crane, leave the ground in the boiler should be suspended after checking whether the rigging safe, reliable,电焊、气焊要严格执行操作制度,明火作业应有专人看守;
Welding and geo-drilling must be strictly implemented operation system, due to special guard over homework, 进入工地现场,必须佩带安全帽。
Entering the site must wear a helmet.禁止带隐患施工,疲劳施工;
Banned hidden construction, fatigue, 严禁抛扔工具、管件,防止砸伤;
Prohibit thrown tools, pipe, prevent scarred, 事故率控制目标为零事故。
Accidents control target as zero accidents.5、供货期
5、delivery 交货期:锅炉设备合同签订后45天,安装工期35天
Delivery:
period: Boiler equipment 45 days after the signing of the contract, the installation period 35 days