第一篇:扬尘治理专项方案(1-2#、1-3#楼)
目 录
一、工程概况······························································································1
二、扬尘来源······························································································1
三、扬尘管理目标·····················································································2
四、组织建立·····························································································3
五、责任制考核·························································································4
六、控制要点·····························································································5
七、管理控制·····························································································5
(一)日常管理··················································································5
(二)阶段性管理··············································································7 施工现场扬尘专项防治方案
一、工程概况
工程名称: 盛苑·新街一期1-2#、1-3#楼及1-2#、1-3#楼地下室工程 建设单位:来宾广投晓都置业有限公司 设计单位:中国华西工程设计建设有限公司 监理单位:广西中信恒泰工程顾问有限公司 施工单位:南宁市同恩建筑安装工程有限责任公司
工程地点:来宾市兴宾南路与文化路交叉口东南角(电厂生活区内)工程概况:本工程盛苑·新街(电厂生活区棚户区改造工程)一期1-2#、1-3#楼及1-2#、1-3#楼地下室工程,1-2#、1-3#楼总建筑面积为39776.06㎡,地下室1层,地上32层;1-2#楼建筑面积18628.99㎡,建筑高度为99.3m;1-3#楼建筑面积18357.98㎡,建筑高度为99.6m;1-2#、1-3#地下室建筑面积2789.09㎡;施工场地原地面建筑为电厂生活住宅小区。
场地特点:施工场地平整,对面为中小学校及居民小区,对做好防尘工作要求较高。
二、扬尘来源
1、施工期的扬尘主要来自:拆除施工,机械清渣,渣车运输、粉末材料堆码、土方堆放及运输车辆道路扬尘。
2、拆除期间,人工机械作业时构筑物掉落及坍塌造成对周边居民的影响极大,渣车装载运输期间的扬尘影响。
3、施工期间,从建筑上层将具有粉尘逸散形的物料、渣土或废弃物输送至地面或下一楼层时产生的扬尘。
4、堆放的原材料(如水泥、白灰、沙子等)底泥流淌在路面风干产生。
5、后续混凝土浇筑车辆大量进出施工场地导致道路扬尘。
三、扬尘管理目标
1、施工扬尘污染控制达标;
2、无市民重大投诉;
3、无因施工扬尘控制不善造成的上级处罚和通报批评;
4、上及部门检查验收达标;
5、创建施工扬尘污染控制示范工地;
四、组织建立
项目部扬尘控制领导小组,负责施工现场扬尘污染控制的策划、组织、落实,并从财力、物力、人力上实施战略布置,将本工程的施工扬尘控制溶入到整个管理中。扬尘控制领导小组:
组 长:邓锐帆 副组长:莫品安
组 员:何凯、郑世坤、林涛
组 长:负责全面管理,与有关部门的协调,定期组织检查。
副组长 :具体负责做好扬尘治理的落实、安排、指挥等各项管理工作。负责日常检查,定期检查的组织,全员扬尘治理工作的教育,配合做好现场宣传工作。具体负责现场扬尘治理各项工作的协调。负责项目扬尘治理工作的宣传、培训工作。组员:
1、具体负责扬尘治理的日常监督检查工作,检查通报的起草,扬尘预防治理培训宣讲;
2、负责对现场扬尘治理情况进行监督,扬尘治理措施的制定,扬尘预防治理培训参加人员的组织;
3、负责项目扬尘污染防治物资准备,确保现场材料存放规范,租赁周转材料及时退租。
4、负责扬尘治理的相关资料的收集、整理;扬尘治理的宣传;培训工作会场安排、资料收集整理。
5、车辆进出大门负责人林海,联系方式:***
五、责任制考核
实施施工现场扬尘控制,责任在领导,管理在岗位,关键是班组。因此项目部必须在建立和健全各项扬尘控制规章制度的基础上,落实各级管理责任,将施工扬尘控制与安全生产和文明施工管理紧紧联系在一起,使之终贯穿于整个施工管理过程中,实施全过程、全方位控制。
1、项目经理是施工扬尘污染控制的责任人,须对施工现场的扬尘污染控制负全面责任;
2、各级管理岗位人员须对施工扬尘控制列入施工全过程管理的范畴,对照自己的指责,加强管理;
3、班组长是施工扬尘污染控制的第一责任人,须对施工现场的扬尘污染控制负全面责任;
4、项目部与各施工班组操作人员落实施工扬尘控制责任,制定奖罚制度,以推动施工扬尘污染控制的进程。
六、控制要点
①工地围墙及大门封闭控制;②现场硬地坪施工;③现场材料进出扬尘控制;④混凝土使用;⑤拆除施工扬尘控制;⑥砂浆的使用;⑦建筑垃圾处理; ⑧生活垃圾处理;⑨工地脚手架施工现场扬尘控制;⑩结构楼层施工扬尘控制;⑾木工棚管理;⑿装饰施工阶段扬尘控制。
七、管理控制
(一)日常管理
1、施工现场保洁
(1)施工现场四周采用封闭的实体墙围档,墙高1.8米。
(2)施工区内派清扫班每日进行定时清扫,及时洒水,确保路面清洁;日常车辆进料必须对车辆进行冲洗,保证灰土不带出工地。生活区、办公区由保洁员每天进行日常清扫工作;
①每日进行1至2次清扫,清扫的灰尘和垃圾必须及时处理至垃圾存放点,不得滞留;
②在清扫前,必须对路面、地面进行洒水,防止清扫时产生扬尘而污染周边环境;
③车辆进料必须进行登记,车辆出门必须进行清洗,入料车辆拒不执行洗车,一律不予放行,并及时报告项目部;
④做好保卫工作,与本工程无关的扬尘污染源禁止带进工地; ⑤生活区垃圾箱必须及时更换垃圾袋,及时清运,及时上盖; ⑥联系附近小区物业管理部门,对附近居民进行告知及出示通告; ⑦渣车装载后货箱部分必须全面遮蔽。
2、专用建筑临时储存间管理
(1)建筑垃圾必须分类堆放,不得混堆;(2)禁止超量堆放;(3)保持周边清洁,不得散落;(4)及时做好记录;
3、木工棚管理
木工棚由木工机械操作员日常负责管理,必须确保木工棚产生的粉尘、废料不污染环境。
(1)木工棚由木工机械操作员管理;
(2)保持木工棚整齐、整洁、及时清理锯木及废料,锯木及刨花等必须装袋后清运至指定地点,必要时可进行喷水湿润后再清理;(3)专棚专用,禁止将木工棚作他用。
4、垃圾及材料运输管理
垃圾及砂石等材料的运输,能导致在运输途中的撒、漏、扬等不良现象,造成扬尘污染和其它环境影响,必须实施控制。
(1)垃圾的清运和砂石材料的进场必须由车厢自动翻盖的车辆实施封闭运输,无此设备的车辆禁止进场运输;
(2)禁止超载,必须保证车厢封闭完整,不留漏缝;(3)车辆出门必须用水冲洗;
(4)自动反倒时必须缓慢进行,禁止猛加油门而造成排气管冲灰产生扬尘。
5、露天材料堆放管理 钢筋、砂、石子等均为工地露天堆放材料,如管理不好,将产生钢筋粉飞扬、砂石尘飞扬等粉尘污染,因此必须加以控制。
(1)严格控制成型钢筋进场,钢筋进场后产即整理归堆上架,做好标识;(2)石子、砂堆放在专用堆场,控制进料量,做到随到随用,不得大量囤积;(3)石子、砂必须堆积方正,底脚整齐、干净,并将周边及上方拍平压实,用密目网进行覆盖,如过分干燥,必须及时洒水;
(4)使用砂石时禁止将所有遮盖的密目网全部打开,稍打开一角,用后拍平盖好。
(二)阶段性管理
在加强基础设施日常管理同时,必须按以下五个阶段进行动态管理,由负责人定期或不定期做好扬尘污染的监控工作。
1、临时设施阶段
(1)施工范围进行封闭施工,保持施工场地整洁、整齐、平顺、美观;(2)将工地进出口用砼进行硬化,并设置冲洗设备及排水沟等,施工运输车辆、设备出工地前必须作除尘、除泥处理,防止出场车辆将泥土、尘土带入城市道路;
(3)风速四级以上易产生扬尘时,要采取有效措施,防止尘土飞散;(4)对可能产生粉尘的施工,采取先洒水或在施工中喷水的办法减少粉尘的产生,尽可能选用环保的低排放施工机械,并在排气口下方的地面浇水冲洗干净,防止排气将尘土扬起飞散;
(5)认真落实“门前三包”责任制;
2、房屋拆除阶段
(1)房屋拆迁施工现场应当设立垃圾渣土存放场地,并及时清运。垃圾渣土运出房屋拆迁施工现场时,应当按照批准的路线和时间到指定的消纳处理场所倾倒;
(2)机械拆除应采用洒水或喷淋式措施。人工拆除法,应采用脚手架围挡、密目网、立笆或布式围档等措施,以控制粉尘外泄;严禁采用整体拉、推墙体的拆除方法;(3)清理楼面、整理破碎构件、翻渣和清运建筑垃圾时,应采取洒水或喷淋设施;
(4)建筑垃圾在48小时内不能完成清运的,应采取覆盖或洒水等防尘措施。
(5)拆除工程完工后,应及时将渣土清运出场。清运渣土的车辆必须采用封闭式运输车辆,施工现场出口处应设置车辆冲洗设施,并应对驶出的车辆进行高压清洗。出入现场时应有专人指挥。清运渣土的作业时间应遵守工程所在地的有关规定。
(6)拆除工程施工时,应有降低噪声的措施。选用低噪声、低振动的设备。
(7)及时联系附近小区物管部门,协助对附近居民的协调和对周边居民发出通告。
3、结构施工阶段
(1)所搭设的脚手架必须全部密目网进行外围封闭,无损坏和漏洞,旧网在使用前必须清洗干净;
(2)结构周边的临边防护必须用密目网设臵,底部设置防空隙的踢脚板,防止垃圾从楼层外围散落而产生扬尘;
(3)现场一律使用商品混凝土和砂浆;
(4)楼层清理垃圾时,预先洒水湿润。待湿透后再进行清扫,各楼层垃圾集中堆放,用劳动车从施工升降机清运至地面,为防止垃圾在清理时因风吹、抖动而产生扬尘,在使用劳动车清运时,每部车上都必须遮盖密目网。禁止从预留筒、内天井或电梯井向下抛扔垃圾,更不准从结构外围抛扔垃圾;
(5)清理脚手架垃圾时,禁止抛翻和拍打竹底笆,必须预先进行洒水,然后用扫把清扫,集中堆放在楼层内,用劳动车运下;(6)清扫电梯井垃圾时,禁止使用抖动安全网的方法,必须用特殊工具伸入网内进行舀清;
4、装饰施工阶段
(1)由于装饰期间的建筑垃圾品种较多,故在现场设施的垃圾堆放点必须进行分隔,以便分类堆放装饰建筑垃圾;
(2)拆除脚手架,禁止焚烧直接掀翻竹架板,必须先行洒水并清理垃圾;
(3)施工现场禁止焚烧垃圾废料等;
(4)装饰用的石膏粉、腻子粉等必须袋装,并装入库集中管理;(5)装饰阶段应相应组织木制半成品进入施工现场,实施装配式施工,减少因切割木制品所产生的扬尘污染。
(6)工程结束前不得拆除工地围墙,如因正式围墙施工妨碍必须拆除临时围墙时,必须设臵临时围墙档措施;
八、检查及奖罚
1、项目部每周由项目经理带队,组织扬尘小组人员、各劳务队及班组负责人必须参加,对现场进行一次扬尘治理情况大检查,具体情况在检查后向各责任人及劳务队伍通报,并发整改通知单,明确整改人、整改时间及整改要求。
2、对环境污染严重的问题,项目部必须局部或全面停工进行整改。
第二篇:扬尘治理专项方案
单县名城国际二期B区扬尘治理专项施工方案
单县铸建工程监理有限公司
单县名城国际二期B区
扬 尘 治 理 专 项 方 案
编制人:________
日期:
年
月
日单县名城国际二期B区扬尘治理专项施工方案
单县铸建工程监理有限公司
扬尘治理专项方案
1、编制目的
由于该工程的场地位置紧邻单县主城区,位于32号路东临方向,为了有效防治城市及住宅区扬尘污染,改善城市环境空气质量及人居环境,为城市创建田园城市做出贡献,为认真贯彻落实《菏泽市建设工程文明施工管理规定》和《单县建设工程施工扬尘污染防治管理办法》以及菏泽市工程建设的有关文明施工管理规定,实现文明施工现场达到菏泽市相关标准,特编制本施工扬尘控制专项方案,并成立联合检查领导小组,开展项目施工扬尘整治工作的日常检查工作。
2、编制依据
1、《菏泽市建设工程文明施工管理规定》;
2、《单县建设工程施工扬尘污染防治管理办法》;
3、《菏泽市城市扬尘污染防治管理暂行规定》;
4、《菏泽市建筑施工现场监督管理规定》;
3、组织保证措施
项目部建立施工现场扬尘控制责任体系并始终保持运转。
1、项目经理负责对施工全过程监督,从源头做好施工扬尘整治单县名城国际二期B区扬尘治理专项施工方案
单县铸建工程监理有限公司
工作。
2、项目副经理负责对本方案的检查、监督及评价。对违法违规、不符合要求的扬尘行为必须坚决制止,不听劝阻的要及时向建设行政主管部门报告。
3、技术负责人负责对扬尘治理专项方案的编制、实施和检查,对投入到扬尘专项治理的人、机、材、设备等作统一安排和部署,对扬尘污染负主责。必须按照《单县建设工程施工扬尘污染防治管理办法》的规定,落实好在建工地“七个百分之百”(施工现场100%封闭围挡,砂石100%覆盖,工地路面100%硬化,拆除工程100%洒水,出工地运输车辆100%冲净车轮车身且密闭无洒漏,暂不开发场地100%绿化,外脚手架密目式安全立网100%张挂)要求,施工现场组织结构必须有专门机构,指派专人负责,每天对施工现场扬尘整治工作进行检查并记录,使工地扬尘整治工作步入常规化和规范化管理。
4、专职安全员:负责每天检查扬尘治理落实及实施情况并作好记录。
5、综治员:负责对路面、加工棚、水沟、机械挖土进行覆盖。
6、施工员:负责对路面保洁人员的监督。
7、材料员:负责对项目针对扬尘整治的材料采购。
4、施工扬尘控制措施
(一)施工现场扬尘污染的来源
建设工程施工的扬尘污染,是指在房屋建设施工、道路与管线施工、物料运输、物料堆放、道路保洁、泥地裸露等活动中产生粉尘颗单县名城国际二期B区扬尘治理专项施工方案
单县铸建工程监理有限公司
粒物,对大气造成的污染。
施工现场易产生扬尘污染的物料主要有:水泥、砂石、灰土、灰浆、灰膏、建筑垃圾、工程渣土等。
施工现场扬尘治理措施:建设工地施工过程中,要做到“六必须、六不准”,即必须打围作业、必须硬化道路、必须设置冲洗设施、必须湿法作业、必须配齐保洁人员、必须定时清扫施工现场;不准车辆带泥出门、不准高空抛撒建渣、不准现场搅拌混凝土、不准场地积水、不准现场焚烧废弃物、不准现场堆放未覆盖的裸土。确保施工现场扬尘污染总体受控。
积极开展社会舆论监督,发动群众参与监管,设立施工扬尘举报投诉电话,接受公众对建设工程施工现场扬尘污染的举报和投诉;邀请社会热心人士担任施工扬尘整治义务监管员,对施工工地进行监督和举报。对违规制尘的工地项目名称、相关责任单位、处罚情况,各监督管理单位可以通过网站、报纸、媒体等向社会曝光公示。
对涉及扬尘问题的作业班组进行专项防止扬尘交底,将扬尘防止工作具体落实到操作层,并建立奖罚制度以推动施工扬尘污染控制过程。项目部与作业班组签定扬尘治理目标责任书,对扬尘治理工作进行目标化管理。
(二)设置围档
根据规划红线范围,沿白云路工地南北向长约1公里区域内,设置高度不低于2.5m的砖砌围墙,施工现场外围次干道设置不低于1.8米的彩钢板墙,确保整个施工区域与外界充分隔离。在二标段东侧设单县名城国际二期B区扬尘治理专项施工方案
单县铸建工程监理有限公司
置项目部,同时在施工大门口设置高压冲洗设备、沉淀池及排水沟。施工运输车辆、挖掘机械等驶出工地前必须清除泥土作防尘处理,严禁将泥土、尘土带出工地。
(三)作业场地、施工便道硬化处理
1、施工现场应平面布置要求做好主要道路、材料堆场、生活办公区域铺设混凝土路面工作,实行场地的硬化或绿化处理,确保无一处露土现象,以达到防尘控制要求。
2、工程每个区的进出口、场内施工便道和建筑材料堆放地进行硬化处理,浇筑混凝土。安排专人经常清洁、洒水降尘。
3、在施工场地内,设置车辆清洗设施以及配套的排水、泥浆沉淀设施;工地出入口配置冲洗用水和设备,其门内侧铺设宽度不少于3米的麻袋并加湿。运输车辆带泥轮胎进行冲洗干净后,方可驶出工地。
(四)道路清扫扬尘污染的控制
安排保洁人员2名(佩戴标识)每日对施工现场的道路进行1~2次的清扫,清扫前对路面进行洒水。天气干燥或风力较大时,增加洒水频次,以保持路面的湿润。
(五)土方施工、堆放扬尘污染的控制
在架空层基础土方开挖、回填施工中,主要采取淋水、降尘和防止车辆泥土外泄等措施。当雨天开挖、基坑回填时,应在施工临时通道上铺设麻袋。严格按挖土施工方案中所规定的挖土流程,堆土位置及车辆出入口线路进行指挥。加强对渣土运输车辆的车况检查,指派单县名城国际二期B区扬尘治理专项施工方案
单县铸建工程监理有限公司
专人随机跟车监督,保证按规定线路行运,严禁偷倒、乱倒。
在场地内堆放作回填使用土方应集中堆放。同时,在土方未干化之前,经表面整平压实后,用密目网进行覆盖。定时洒水维持湿润,以有效地控制扬尘。
(六)建筑材料扬尘污染的控制
1、砂石设置专用池槽进行堆放,控制进料数量,做到随到随用,不大量囤积。堆放时做到堆积方正、底脚整齐干净,并将周边及上方拍平压实,然后用密目网罩进行覆盖。砂石料如过于干燥,应及时进行洒水。
2、施工用的页岩空心砖及配砖砌块必须在指定场地进行堆放。进场后及时进行洒水湿润,定时由专人对堆放场地进行清扫。
3、其他易飞扬物、细颗散体材料(如塑料泡沫、膨胀珍珠岩粉末等),必须进行严密的遮盖或存放在不透风的仓库内,运输车辆要有防止泄漏、飞扬装置,卸料时采取集中码放措施,以减少污染。(七)砂浆拌制扬尘污染的控制
在砂浆搅拌操作间四周进行封闭围挡,以控制和减少水泥扬尘对大气造成的污染。袋装水泥设置封闭的库房进行堆放,安排专人进行管理,定时进行清扫,保持库内整洁,地面无积灰现象。如需露天存放应采取严密遮盖措施。装卸以及拌制作业时严格要求工人佩带口罩,做到轻搬轻放。砂浆拌制时严格按顺序进料,以控制和减少水泥扬尘。搅拌机储料池前应设置三面挡水,并做好排水沟、沉淀池,定期对沉淀池进行清理。单县名城国际二期B区扬尘治理专项施工方案
单县铸建工程监理有限公司
为减少施工现场扬尘污染源,施工现场全全部使用商品混凝土。(八)木工机械作业扬尘污染的控制
木工加工棚按施工组织总设计的布置要求,在每个区段内落实责任制,指定作业场所环境保护责任人,负责木工棚的日常管理。保持木工棚的整洁,及时清理木屑、刨花和边角料,必要时进行洒水湿润后再清理,并装袋运至指定地点堆放,定期处置。
(九)道路清扫扬尘污染的控制在施工现场主要道路边、生活区域内场地适当位置安装一些水龙头,使洒水皮管、洒水车能就近使用,便于操作。道路安排专人每日对施工现场的道路进行1~2次的清扫,清扫前需进行洒水湿润,天气干燥或风力较大时,增加洒水频次,以保持路面的湿润。所产生的生活垃圾和粉尘经分类袋装后及时地投放到指定的地点。
(十)运输车辆扬尘污染的控制
运输建筑材料、垃圾和泥土等的车辆,在驶出建设施工现场之前,要加强防尘冲洗、遮蔽、清洁等工作,防止建筑垃圾、泥土的散落,污染道路和周边环境。
冲洗车辆产生的泥浆水应通过二级沉淀达到排放标准后,方可排人城市公共管网。沉淀池派专人定期进行清理,一般为2~3天清理一次。
施工现场设置规范化大门,并安装视频监控系统,录像存储1个月以上。
(十一)建筑垃圾扬尘污染的控制 单县名城国际二期B区扬尘治理专项施工方案
单县铸建工程监理有限公司
1、建筑结构楼层内的施工垃圾(暴露垃圾)清扫前先洒水湿润,运输可采用搭设封闭式专用垃圾通道运输或采用密封容器、装袋清运,并派专人进行检查、监督。严禁随意在预留洞、阳台、窗口处凌空抛洒。所清扫集中的垃圾,在现场规划场地内堆放,并适量洒水或覆盖密目网,定时清运搬离现场,以减少粉尘污染。
2、建筑垃圾、工程渣土在48小时内不能完成清运的,在施工工地内设置临时堆放场,临时堆放场采取围挡、遮盖等防尘措施。
3、在施工现场处置工程渣土时进行洒水或者喷淋降尘。
4、施工现场堆放的渣土,堆放高度不得高于围档高度,并采取遮盖措施。
5、在建筑物、构筑物上运送散装物料、建筑垃圾和渣土时,采用密闭方式清运,禁止高空抛掷、扬撒。
(十二)生活垃圾扬尘污染的控制
生活垃圾安排专人进行收集、清理,按指定地点与建筑垃圾分开堆放,并进行密闭遮挡。生活垃圾应由环卫部门及时清运出场。
禁止在现场焚烧建筑垃圾、废弃木料、塑料品和热熔沥青,以防止对大气的污染。
(十三)对涉及扬尘问题的作业班组进行专项防止扬尘交底,将扬尘防止工作具体落实到操作层,并建立奖罚措施。
(十四)项目部与作业班组逐级签定扬尘治理目标责任书,对扬尘治理工作进行目标化管理。
(十五)其他扬尘控制措施 单县名城国际二期B区扬尘治理专项施工方案
单县铸建工程监理有限公司
1、土方作业过程中,安排专人及时清除路面遗洒的泥土,并使路面始终保持较湿润的状态,做到不泥泞,不扬尘。土方施工期间,当气象预报风速达到5级以上时,停止施工作业。
2、禁止使用空气压缩机来清理车辆、设备和物料的尘埃。
3、清扫路面、脚手架时,采取先洒水后清扫的方法。
4、合理安排土石方等容易产生扬尘的工序。
5、野外施工现场主要运输道路,应进行地面硬化,及时洒水。
6、对于施工场地平整作业造成的粉尘排放,要及时洒水。
7、土石方施工现场,经常洒水,保持无风天目测无扬尘。
8、施工过程中,所需水泥库应设防护棚,四周封闭,地面进行硬化处理,水泥袋及时回收扎捆入库。
9、在建工程房屋外立面采用符合规定的密目式安全网全封闭维护。
5、扬尘治理联合检查制度
1、检查内容按建设局发放的《单县建设工程施工扬尘污染防治管理办法》中检查内容进行检查。
2、安全文明施工、扬尘治理联合检查小组每月对施工现场进行检查、考核,项目部各人员随时检查。
3、在安全文明施工、扬尘治理检查小组各人员进行检查后,由专职安全员对检查中所发现的问题,开出“隐患问题通知单”,各班组在收到“隐患问题通知单”后,应根据具体情况,定时间、定人、定措施予以解决, 联合检查小组监督落实问题的解决情况。单县名城国际二期B区扬尘治理专项施工方案
单县铸建工程监理有限公司
4、项目部每周定期对施工现场进行检查,并作好记录。每一个月为一个考核周期,每月月底进行考核。
6、扬尘领导小组组织机构 扬尘领导小组名单:
1、组长:李卫国-负责扬尘治理工作的总体安排。
2、副组长:杨睦艳-负责扬尘治理工作的落实。
3、组员:耿辉-负责扬尘治理方案的编制。
4、组员:耿辉、王发涛、杨睦艳-负责扬尘工作人员安排、检查。
5、组员:胡林责扬尘治理资料收集整理。
6、组员:董超负责进出车辆的清洗、检查。
7、组员:门卫负责工地内、外道路清扫。
第三篇:扬尘治理专项方案
目 录
一、工程概况.............................................................................................2
二、编制依据.............................................................................................2
三、扬尘污染防范措施............................................................................3
四、扬尘治理联合检查制度....................................................................9
扬尘污染控制预案
为认真贯彻落实政府关于严格控制城区扬尘污染的有关要求,保证本工程施工期间,有效防治工地扬尘污染,进一步加强建筑工地文明施工管理,特编制本扬尘污染控制方案。
一、工程概况
(一)工程简介
1、工程名称:青神县监管中心建设项目
2、建设地点:青神县西龙镇马槽寺村6组
3、建设单位:青神县公安局
4、设计单位:青神县吉元建筑设计有限公司
5、施工单位:四川际丰建筑工程有限公司
6、结构类型:砖混、框架结构
7、建筑面积:4300㎡
(二)工程概况:
1、建筑功能:公共建筑
2、建设面积: 4300m2
3、建筑层数:武警综合楼三层,拘留所及办公用房一层,监室一层。
4、建筑高度:。
二、编制依据
1、根据国家有关部门和建设部有关规定及《中华人民共和国大气污染防治法》。
2、当地政府相关法律法规。
三、扬尘污染防范措施
(一)组织保证措施
项目部建立施工现场扬尘控制责任体系并始终保持运转。
1、项目经理负责对施工全过程监督,从源头做好施工扬尘整治工作。
2、项目执行经理负责对本方案进行检查监督及评价。对违法违规不符合要求的扬尘行为必须坚决制止,不听劝阻的要及时向上级反应。
3、项目技术负责人负责对扬尘治理专项方案的编制和实施及检查。对投入到扬尘专项治理的人、机、材、设备等作统一安排和部署,对扬尘污染负责。
4、根据政府和上级行政主管部门要求落实好裸土覆盖,道路硬化、车辆冲洗、洒水降尘,工地绿化5个指标100%必须达标要求,设专职安全员负责每天对施工现场扬尘整治工作进行检查并记录,使工地扬尘整治工作进入常规化和规范化管理。
4、专职安全员:负责每天检查扬尘治理落实及实施情况检查并做好记录。
5、工长:负责对路面、加工棚、水沟、机械挖土进行冲洗或覆盖。
6、施工员:负责对路面保洁人员的监督。、7、材料员:负责项目针对扬尘整治的材料采购。
(二)设置围挡
1、根据规划红线范围,设置高度不低于2.5m的围墙确保整个施工区域与外界充分隔离。
2、在施工大门口洗车槽,洗车槽设沉淀池及排水沟,洗车槽旁边安装一台高压水枪用来冲洗进出工地的汽车轮胎,洗车的污水经二级沉淀排至工地外的市政污水管网内。
3、施工运输车辆,挖掘机械等驶出工地前必须清除轮胎及车身泥土,冲洗干净,严禁将泥土尘土带出工地。
(三)作业场地施工道路硬化处理
1、施工现场应按平面布置图要求做好主道路、材料堆放场、生活区、办公区或铺设混凝土路面工作。实行场地的硬化或绿化处理。确保无一处露土现象,以达到防尘控制要求。
2、工地的进出口,场内施工便道和建筑材料堆放地进行硬化处理,安排专人经常清洁、洒水降尘。
3、在施工场地内设置车辆清洗设施以及配套的排水、泥浆沉淀池设施,工地出入口处设置冲洗用水和设备,其门内侧铺设进门长度、宽度不少于3m的棕垫并加湿。工地大门出入口设置洗车台,对驶出工地的车辆进行清洗,洗车后的污水经过沉淀后集中排放,使其有组织的汇入市政排水设施。并在施工现场设置畅通排水沟渠系统,保持施工道路干燥坚实,场场内无积水、泥浆,施工现场地面硬化,防止粉尘污染环境,施工现场设明排水沟及暗沟经沉淀后接通市政污水道排出。
4、现场进出入车辆,主要为土方运输车辆、砼搅拌车,货车轮胎出工地进行清扫,防止轮胎污物带出工地,现场设垃圾箱,禁止乱丢乱放。
(四)道路清扫扬尘污染的控制
安排保洁人员2名(佩戴标识)每日对施工现场的道路进行来回巡查清扫,清扫前对路面进行洒水,天气干燥或风力较大时增加洒水次数,以保证路面的湿润。
(五)土方施工、堆放扬尘污染的控制
在土方开挖、回填施工中,主要采取淋水降尘和防止车辆泥工外泄等措施。当雨天开挖、基坑回填时,应在施工临时通道上铺设麻袋,严格按挖土施工方案中所规定的挖土流程,堆土位置及车辆 出入口线路进行指挥。加强对渣土运输车辆的车况检查,指派专人随机跟车监督,保证按规定线路运行,严禁在运输途中偷倒乱倒。
在场地内堆放作回填使用土方应集中堆放,同时在土方未干化之前将表面平整压实后用密目网进行覆盖,定时洒水维持湿润,以有效的控制扬尘。
(六)建筑材料扬尘污染的控制
1、砂石设置专用池槽进行堆放,控制进料数量,做到随到随用,不大量囤积。堆放时做到堆积方正,底脚整齐干净,并将周边及上方拍平压实,然后用密目网进行覆盖。砂石料如过于干燥应及时进行洒水。
2、施工用黏土砖、加气块必须指定场地进行堆放。进场后及时进行洒水湿润,定时由专人对堆放场地进行清扫。
3、其他易飞扬物细颗散体材料(如塑料泡沫、膨胀珍珠岩粉末等)必须进行严密的遮盖或存放在不透风的仓库内,运输车辆要有防止漏泄、飞扬装置。卸料时采取集中码放措施,以减少污染。
(七)混凝土、砂浆拌制扬尘污染的控制
1、在混凝土、砂浆搅拌操作间四周做封闭围挡以控制和减少水泥扬尘对大气造成的污染,袋装水泥设置封闭的库房进行堆放,安排专人进行管理,定时进行清扫,保持库房整洁,地面无积水现象。如需露天存放应采取严密遮盖措施。装卸以及拌制作业时严格要求工人佩戴口罩,做到轻搬轻放。混凝土、砂浆拌制时严格按石子(砂)——水泥——砂顺序进料以控制和减少水泥扬尘。搅拌棚四周做20cm高挡水,并做好排水沟、沉淀池,定期对沉淀池进行清理。
2、施工现场全部使用商品混凝土,以减少因现场搅拌砼而产生的粉尘、噪音和废水污染。
(八)木工机械作业扬尘污染的控制
木工加工棚实行责任制,指定木工组长为作业场所环境保护责任人,负责木工棚的日常管理,保持木工棚的整洁,及时清理木屑、刨花和边角料,必要时进行洒水湿润后再清理并袋装运至指定地点定期处置。
(九)砖槽切割加工作业扬尘污染的控制
管线安装施工的砖墙沟槽切割,应采用湿作业法进行施工。装饰工程所用石材应优先组织半成品进入施工现场,实施装配式施工,减少因石材切割、加工所造成的扬尘污染。现场石材切割加工应设置专用封闭作业间,操作人员必须戴好防尘口罩,以降低或减少扬尘对环境的污染和人体的危害。
(十)建筑垃圾扬尘污染的控制
1、建筑结构楼层内的施工垃圾,清扫前先洒水湿润,运输可采用封密容器,袋装清运,由泥工工长进行检查、监督。严禁随意在预留洞阳台、窗口处凌空抛洒。所清扫的垃圾在现场规划场地内堆放,并适量洒水或覆盖密目网,定时清运搬离现场以减少扬尘污染。
2、建筑垃圾、工程渣土不能及时完成清运的,在临时堆放场地采取围挡遮盖等防尘措施。
(十一)运输车辆管理
1、在工地从事运载建筑材料、建筑垃圾、渣土的车辆,必须符合市政环卫部门的有关要求并经市政环卫部门门批准,方可使用。
2、对进出建筑工地运输车辆实行登记制度,所有运输车辆每次进出建筑工地,必须由项目部做好记录,记录存档由项目部保留,记录内容包括进出建筑工地时间、车俩牌号、车辆所属单位、运输货物以及是否符合文明运输的要求等。
3、驶出建筑工地的运输车辆,必须冲洗干净,严禁带泥土上路,严禁超载;运送各种建筑材料、建筑垃圾、渣土的车辆必须应有遮盖和防护措施,防止建筑材料、建筑垃圾尘土飞扬、洒落和流溢,否则不允许其驶出建筑工地。
(十二)烟尘控制
施工现场禁止堆放有毒烟尘和气体,禁止燃烧有毒的物品,不得在施工现场洗石灰、煎熬沥青、工地生活燃料应符合环保有关要求。建筑垃圾、渣土应在指定地点清理;高空施工的建筑垃圾和废弃物应采用密闭式串筒或其他措施清理搬运;建筑垃圾必须通过楼梯或垂直运输机械进行转运,不得从建筑物高处向下流放污水,倾倒建筑垃圾;禁止在道路和人行道上堆放或转运易扬尘的建筑材料;建筑工程完工后,必须及时清理和平整场地,清除各种尘源。(十 三)专人负责车辆冲洗及公路清扫
项目部指派专人负责大门处车辆进出记录,登记冲洗车辆记录,严禁带泥土上路,若有污染立即进行清扫和冲洗。
(十四)主体及装饰施工扬尘污染的控制
在主体及装饰施工期间,外墙操作架外立面全部用绿色的安全密目网作为安全防护及防尘屏障。
(十五)对涉及扬尘问题的作业班组进行专项防止扬尘交底,将扬尘防止工作具体落实到操作层,并建立奖罚措施。
四、土方运输路线及堆放地点
施工现场土方开挖时,根据施工现场实际情况需求,除预留回填的土方以外,剩余土方外运至指定的弃土场内堆放。
主要路线为:施工现场装车覆盖后经外北街右转至青衣大道,经锦绣大道至钟家山村弃土场堆放。
五、扬尘治理联合检查制度
扬尘治理管理小组成员及主要负责人联系电话 组长:邱瑜(***)副组长:吴志春(***)
组员: 廖厚英 喻中慧 唐浩 杨刚 廖冰
1、检查内容按《建筑工程扬尘治理考核表》中检查内容进行检查。
2、安全文明施工扬尘治理联合检查小组每月对施工现场进行检查,考核。
3、在安全文明施工扬尘治理检查小组各人员检查后由专职安全员对检查中发现的问题,开出“隐患问题通知单”各班组在收到“隐患问题通知单”后应根据具体情况,定时间、定人、定措施予以解决,联合检查小组监督落实问题的解决情况。
4、项目部每周定期对施工现场进行检查,并做好记录,每一月为一个考核周每月月底进行考核。
第四篇:扬尘专项治理方案
目录
第一章、编制目的 第二章、编制依据 第三章、第四章、第五章、第六章、第七章、第八章、扬尘治理的目标 组织保证措施 施工扬尘控制措施 扬尘治理联合检查制度 雾霾天气响应预警机制 扬尘领导小组组织结构
第一章、编制目的
为了有效防治城市扬尘污染,改善城市环境空气质量,保障人民群众正常生产、生活秩序和身体健康,预防本工程施工中对环境污染事故的发生,认真贯彻落实《天津市建设工程文明施工管理规定》和《天津市扬尘污染防治管理办法》以及天津市重大工程建设的有关文明施工管理规定,实现文明施工现场达到天津市相关标准,特编制本施工扬尘治理专项方案,并成立联合检查领导小组,开展项目施工扬尘整治工作的日常检查工作。
第二章、编制依据
1、《中华人民共和国大气污染防治法》
2、《天津市建设工程文明施工管理规定》
3、《天津市主城尘污染防治办法(草案)》
4、《天津市环境保护条例》
5、《天津市城市扬尘污染防治管理暂行规定》
6、《天津市建筑施工现场监督管理规定》
7、《天津市房屋建筑和市政基础设施工程施工现场管理暂行标准(环境和卫生)》
8.天津市雾霾天气预警响应预案等有关规定
第三章、扬尘治理的目标
建立有效的管理制度,并通过实施确保工地施工现场达到天津市扬尘治理检查要求,使扬尘治理工作制度化、规范化。
第四章、组织保证措施
项目部建立施工现场扬尘控制责任体系并始终保持运转。
1、项目经理负责对施工全过程监督,从源头做好施工扬尘整治工作。
2、项目副经理负责对本方案的检查、监督及评价。对违法违规、不符合要求的扬尘行为必须坚决制止。
3、技术负责人负责对扬尘治理专项方案的编制、实施和检查,对投入到扬尘专项治理的人、机、材、设备等作统一安排和部署,对扬尘污染负主责。必须按照《天津市城市扬尘污染防治管理暂行规定》、《天津市建筑施工现场监督管理规定》、《天津市房屋建筑和市政基础设施工程施工现场管理暂行标准(环境和卫生)》的规定,特别是在天津市发布雾霾天气预警预报,立即根据雾霾和扬尘天气等级启动预警预案。落实好裸土覆盖、硬化道路、冲洗车辆、洒水降尘、工地绿化5个100%必须达标的要求;必须有专门机构,指派专人负责,每天对施工现场扬尘整治工作进行检查,使工地扬尘整治工作步入制度化和规范化管理。如果预警进入红色等级,施工立即停止,全面采取洒水降尘。
4、专职安全员:负责每天检查扬尘治理落实及实施情况并作好记录。
5、综治员:负责对路面、加工棚、水沟、机械挖土进行覆盖。
6、施工员:负责对路面保洁人员的监督。
第五章、施工扬尘控制措施
(一)施工现场扬尘污染的来源
建设工程施工的扬尘污染,是指在房屋建设施工、道路与管线施工、物料运输、物料堆放、道路保洁、泥地裸露等活动中产生粉尘颗粒物,对大气造成的污染。施工现场易产生扬尘污染的物料主要有:水泥、砂石、灰土、灰浆、灰膏、建筑垃圾、工程渣土等。
施工现场扬尘治理措施:建设工地施工过程中,要做到“六必须、六不准”,即必须打围作业、必须硬化道路、必须设置冲洗设施、必须湿法作业、必须配齐保洁人员、必须定时清扫施工现场;不准车辆带泥出门、不准高空抛撒建渣、不准现场搅拌混凝土、不准场地积水、不准现场焚烧废弃物、不准现场堆放未覆盖的裸土。确保施工现场扬尘污染总体受控。
对涉及扬尘问题的作业班组进行专项防止扬尘交底,将扬尘防止工作具体落实到操作层,并建立奖罚制度以推动施工扬尘污染控制过程。
(二)设置围档
根据规划红线范围,施工区域内,设置高度不低于2.2m的彩钢瓦围墙,确保整个施工区域与外界充分隔离。在施工大门口设置冲洗设备、沉淀池及排水沟。施工运输车辆、挖掘机械等驶出工地前必须清除泥土作防尘处理,严禁将泥土、尘土带出工地。
(三)作业场地、施工便道硬化处理
1、施工现场应平面布置要求做好主要道路、材料堆场、生活办公区域铺设混凝土路面工作,实行场地的硬化或绿化处理,确保无一处露土现象,以达到防尘控制要求。
2、工程每个区的进出口、场内施工便道和建筑材料堆放地进行硬化处理,浇筑混凝土。安排专人经常清洁、洒水降尘。
3、在施工场地内,设置车辆清洗设施以及配套的排水、泥浆沉淀设施;工地出入口配置冲洗用水和设备。运输车辆带泥轮胎进行冲洗干净后,方可驶出工地。
(四)道路清扫扬尘污染的控制
安排保洁人员2名(佩戴标识)每日对施工现场的道路进行1~2次的清扫,清扫前对路面进行洒水。天气干燥或风力较大时,增加洒水频次,以保持路面的湿润。
(五)土方施工、堆放扬尘污染的控制
在基础土方开挖、回填施工中,主要采取淋水、降尘和防止车辆泥土外泄等措施。当雨天开挖、基坑回填时,应在施工临时通道上铺设麻袋。严格按挖土施工方案中所规定的挖土流程,堆土位置及车辆出入口线路进行指挥。
在场地内堆放作回填使用土方应集中堆放。同时,在土方未干化之前,经表面整平压实后,用密目网进行覆盖。定时洒水维持湿润,以有效地控制扬尘。
(六)建筑材料扬尘污染的控制
1、砂石设置专用池槽进行堆放,控制进料数量,做到随到随用,不大量囤积。堆放时做到堆积方正、底脚整齐干净,并将周边及上方拍平压实,然后用密目网罩进行覆盖。砂石料如过于干燥,应及时进行洒水。
2、施工用的页岩空心砖及配砖砌块必须在指定场地进行堆放。进场后及时进行洒水湿润,定时由专人对堆放场地进行清扫。
3、其他易飞扬物、细颗散体材料(如塑料泡沫、膨胀珍珠岩粉末等),必须进行严密的遮盖或存放在不透风的仓库内,运输车辆要有防止泄漏、飞扬装置,卸料时采取集中码放措施,以减少污染。
(七)混凝土、砂浆拌制扬尘污染的控制
在混凝土、砂浆搅拌操作间四周进行封闭围挡,以控制和减少水泥扬尘对大气造成的污染。袋装水泥设置封闭的库房进行堆放,安排专人进行管理,定时进行清扫,保持库内整洁,地面无积灰现象。如需露天存放应采取严密遮盖措施。装卸以及拌制作业时严格要求工人佩带口罩,做到轻搬轻放。砂浆拌制时严格按石子(砂)→水泥→砂顺序进料,以控制和减少水泥扬尘。搅拌机储料池前应设置三面挡水,并做好排水沟、沉淀池,定期对沉淀池进行清理。
(八)木工机械作业扬尘污染的控制 木工加工棚按施工组织总设计的布置要求,在每个区段内落实责任制,指定作业场所环境保护责任人,负责木工棚的日常管理。保持木工棚的整洁,及时清理木屑、刨花和边角料,必要时进行洒水湿润后再清理,并装袋运至指定地点堆放,定期处置。
(九)道路清扫扬尘污染的控制在施工现场主要道路边、生活区域内场地适当位置安装一些水龙头,使洒水皮管、洒水车能就近使用,便于操作。道路安排专人每日对施工现场的道路进行1~2次的清扫,清扫前需进行洒水湿润,天气干燥或风力较大时,增加洒水频次,以保持路面的湿润。所产生的生活垃圾和粉尘经分类袋装后及时地投放到指定的地点。
(十)运输车辆扬尘污染的控制
运输建筑材料、垃圾和泥土等的车辆,在驶出建设施工现场之前,要加强防尘冲洗、遮蔽、清洁等工作,防止建筑垃圾、泥土的散落,污染道路和周边环境。
冲洗车辆产生的泥浆水应通过二级沉淀达到排放标准后,方可排人城市公共管网。沉淀池派专人定期进行清理,一般为2~3天清理一次。
(十一)砖槽切割加工作业扬尘污染的控制
管线安装施工的砖墙沟槽切割,应采用湿作业法进行施工。装饰工程所用石材应优先组织半成品进入施工现场,实施装配式施工,减少因石材切割、加工所造成的扬尘污染。现场石材切割加工应设置专用封闭式作业间,操作人员必须佩带防尘口罩,以降低或减少扬尘对环境的污染和人体的危害。
(十二)建筑垃圾扬尘污染的控制
1、建筑结构楼层内的施工垃圾(暴露垃圾)清扫前先洒水湿润,运输可采用搭设封闭式专用垃圾通道运输或采用密封容器、装袋清运,并派专人进行检查、监督。严禁随意在预留洞、阳台、窗口处凌空抛洒。所清扫集中的垃圾,在现场规划场地内堆放,并适量洒水或覆盖密目网,定时清运搬离现场,以减少粉尘污染。
2、建筑垃圾、工程渣土在48小时内不能完成清运的,在施工工地内设置临时堆放场,临时堆放场采取围挡、遮盖等防尘措施。
3、在施工现场处置工程渣土时进行洒水或者喷淋降尘。
4、施工现场堆放的渣土,堆放高度不得高于围档高度,并采取遮盖措施。
5、在建筑物、构筑物上运送散装物料、建筑垃圾和渣土时,采用密闭方式清运,禁止高空抛掷、扬撒。
(十三)生活垃圾扬尘污染的控制
生活垃圾安排专人进行收集、清理,按指定地点与建筑垃圾分开堆放,并进行密闭遮挡。
禁止在现场焚烧建筑垃圾、废弃木料、塑料品和热熔沥青,以防止对大气的污染。
(十四)对涉及扬尘问题的作业班组进行专项防止扬尘交底,将扬尘防止工作具体落实到操作层,并建立奖罚措施。(十五)项目部与作业班组逐级签定扬尘治理目标责任书,对扬尘治理工作进行目标化管理。
(十六)其他扬尘控制措施
1、土方作业过程中,安排专人及时清除路面遗洒的泥土,并使路面始终保持较湿润的状态,做到不泥泞,不扬尘。土方施工期间,当气象预报风速达到5级以上时,停止施工作业。
2、禁止使用空气压缩机来清理车辆、设备和物料的尘埃。
3、清扫路面、脚手架时,采取先洒水后清扫的方法。
4、合理安排土石方等容易产生扬尘的工序。
5、野外施工现场主要运输道路,应进行地面硬化,及时洒水。
6、对于施工场地平整作业造成的粉尘排放,要及时洒水。
7、土石方施工现场,经常洒水,保持无风天目测无扬尘。
8、施工过程中,所需水泥库应设防护棚,四周封闭,地面进行硬化处理,水泥袋及时回收扎捆入库。
第六章、扬尘治理联合检查制度
1、检查内容按《天津市建设工程扬尘治理检查表》中检查内容进行检查。
2、安全文明施工、扬尘治理联合检查小组每月对施工现场进行检查、考核,项目部各人员随时检查。
3、在安全文明施工、扬尘治理检查小组各人员进行检查后,由专职安全员对检查中所发现的问题,开出“隐患问题通知单”,各班组在收到“隐患问题通知单”后,应根据具体情况,定时间、定人、定措施予以解决, 联合检查小组监督落实问题的解决情况。
4、项目部每周定期对施工现场进行检查,并作好记录。每一个月为一个考核周期,每月月底进行考核。
第七章、雾霾天气预警机制响应
1、根据天津市气象预报发布的关于雾霾和扬尘等级项目部立即采取对应防治措施。
2、达到蓝色,黄色预警时工地立即启动预警响应预案,采取定时洒水和清扫道路,由项目部指派专人负责督办。
3、达到橙色预警时立即停止部分产生扬尘的施工作业,采取对工地全面裸露地面的覆盖措施压尘。
4、达到红色预警时立即全面停工,立即采取全面洒水降尘措施,确保pm2.5达标,保证本工地不发生扬尘现象。
第八章、扬尘领导小组组织机构
扬尘领导小组名单:
1、组 长: 电话: 负责全面指挥、统一组织、协调。
2、副组长: 电话: 负责实施施工现场扬尘治理。
3、组 员: 电话: 负责扬尘治理方案的编制。
4、组 员: 电话: 负责扬尘工作人员安排、检查。
5、组 员: 电话: 负责进出车辆的清洗、检查。
6、组 员: 电话: 负责工地内、外道路清扫、检查。
第五篇:扬尘治理专项方案
…………
三期
扬尘治理专项方案
合肥建工集团有限公司
二零一八年六月
目录
1、工程概况........................................1
2、编制依据........................................1
3、扬尘治理专项措施.................................1
4、扬尘治理实施办法.................................2
5、扬尘治理检查制度.................................4
6、施工现场防噪声污染的各项措施
...................4
7、文明施工措施.....................................5
8、施工现场场容布置及形象管理.......................6
9、文明施工、环境保护的检查措施.....................8
1、工程概况
工程名称:………………(6#-9#住宅楼、商业、幼儿园及地库)主体及配套建设工程
建设单位:………………地产开发有限公司 设计单位:山西省建筑设计研究院 监理单位:广州市恒合工程监理有限公司 施工单位:合肥建工集团有限公司
本工程为运………………,建设地点:山西省运城市圣惠路与涑水街交口;设计地下车库总建筑面积:57277.84㎡,其中地下一层建筑面积:19089.04㎡,地下二层建筑面积:19085.93㎡,一层地面出入口面积:300㎡。6#~9#楼无设备层,地下为整个小区的地下车库。6#楼地上部分总建筑面积:29491.45m2。地上一层为商业网点(配套),二层~三十层为高层住宅,两个单元,每层八户。7#楼地上部分总建筑面积:17512.19m2。地上一、二层为商业网点和商业,三层~三十二层为高层住宅,一个单元,每层四户。8#楼地上部分总建筑面积:26746.59m2。本工程无设备层,地下为整个小区的地下车库。地上一、二层为商业网点(配套),三层~三十三层为高层住宅,两个单元,每层六户。9#楼地上部分总建筑面积:17376.95m2。地上一、二层为商业网点(配套),三层~三十二层为高层住宅,一个单元,每层四户。
2、编制依据
2.1 本工程施工组织设计
2.2山西省建筑施工扬尘污染防治文件汇编 2.3本工程现场总平面布置图
3、扬尘治理专项措施
为有效防治城市扬尘污染,改善城市环境空气质量,保障人体健康,结合本项目的实际情况特制定扬尘治理实施措施。
3.1扬尘治理工作总目标
建立有效的管理制度,并通过实施确保工地施工现场达到市扬尘治理检查要求,使扬尘治理工作制度化,规范化。
3.2扬尘治理工作职责分工
(1)项目部成立扬尘治理管理领导小组: 组长:……强
副组长:…………………………
组 员:……………………………………(2)由专职安全员负责每天检查扬尘治理实施及落实情况并作好记录。
4、扬尘治理实施办法
4.1 进出口地坪和场地内主要道路结合规划总平面图道路和车辆荷载设置工地进出口道路采用C20砼进行硬化处理。设置冲洗车辆设备,在施工现场西侧大门出入口一套冲洗台,安排专人对出入车辆进行冲洗排水沟、沉淀池,防止泥土随车辆,行人带出工地。
4.2施工运输车辆、挖掘机械、混凝土罐车等驶出工地前必须清除泥土作防尘处理,严禁将泥土、尘土带出工地。
4.3运输砂、石、水泥、土方、垃圾等易产生扬尘污染的车辆,进出施工现场必须封闭,严禁撒漏。
4.4楼层建筑垃圾装袋密封,由垂直运输设备向下转运,严禁由楼层自由倾倒。
4.5清扫地面必须洒水,运输建筑垃圾加盖,松散材料堆放盖彩条布,以免粉尘弥漫,污染环境。
4.6在工地上设置临时密闭性垃圾堆放场地或垃圾箱进行存放。4.7设置四名保洁员负责现场的经常性整洁卫生
4.8现场使用的混凝土全部使用商品混凝土禁止现场搅拌、砌筑及抹灰砂浆使用预拌干粉砂浆。
4.9施工现场内裸露土方采用绿网进行全覆盖,堆放的渣土、建筑垃圾、必须采取围挡、遮盖等防尘措施,以防尘土飞扬。
4.10散水泥和其它易飞扬的细颗粒散体材料存放在库房内,如需露天存放采取严密遮盖措施。
4.11对涉及扬尘问题的作业班组进行专项防止扬尘交底,将扬尘防止工作具体落实到操作层,并建立奖罚措施。
4.12项目部与作业班组逐级签定扬尘治理目标责任书,对扬尘治理工作进行目标化管理。
4.13施工现场污水必须有组织排放,设置沉淀池,泥浆、污水未经沉淀严禁直接排入下水道内,泥浆不得外漏。
4.14生活区污水必须设置沉淀池,污水未经沉淀严禁直接排入下水道内。垃圾手机存放后必须及时处理。
4.15房屋建筑脚手架外侧必须设置密目式安全网,维护高度应超出操作层1.5米。
4.16施工现场安装4台固定式雾炮装置、一台洒水车配备雾炮机装置定时对施工现场进行洒水降尘。本工程沿施工现场设置塔吊旋
转喷淋系统,减少施工现场扬尘。
5、扬尘治理检查制度
5.1作业小组严格按照检查保证制度做到每日检查,项目部每周将定期对施工现场进行全面检查评比,并作好保存记录。
5.2按规定向公司书面汇报扬尘治理工作执行情况。
6、施工现场防噪声污染的各项措施
6.1人为噪声的控制
施工现场提倡文明施工,建立健全控制人为噪声的管理制度。尽量减少人为的大声喧哗,增强全体施工人员防噪声扰民的自觉意识。
6.2强噪声作业时间的控制
本公司项目部严格控制作业时间,晚间作业不超过22点,早晨作业不早于6点,特殊情况需连续作业(或夜间作业)的及时申办夜间施工许可证,应尽量采取降噪措施,并事先做好周围群众通告工作。
6.3强噪声机械的降噪措施
(1)牵扯到产生强噪声的成品、半成品加工、制作作业(如预制构件,门窗制作等),应尽量放在工厂、车间完成,减少因施工现场加工制作产生的噪声。
(2)尽量选用低噪声或备有消声降噪声设备的施工机械,施工现场的强噪声机械(如:振动棒、电锯、电刨、砂轮机等)按规范要求设置封闭的机械棚,以减少强噪声的扩散。
6.4加强施工现场管理
加强施工现场环境管理,采取专人负责的原则,达到施工噪声不扰民的目的。
7、文明施工措施 7.1 文明施工目标
依据《建设工程安全管理条例》、建设部JGJ59-2011《建筑施工安全检查评分标准》、市建筑行业管理部门的有关规定和本公司要求。特制定本项目部安全文明管理目标:确保达到市安全质量标准化工地,争创省级安全文明标准化工地; 7.2 管理方针
为美化城市环境,本公司将认真贯彻执行建设部、山西省及运城市关于施工现场文明施工管理的各项规定,同时依据国家行业标准《建筑施工安全检查评分标准》的规定制定方针、目标,选择功能型、环保型、节能型的工程材料设备,配备相应的资源,本着遵守法规、预防污染、节能减废的原则,实现施工与环境的和谐,在施工过程中做到建设工地“整洁、规范、安全、文明”,使施工场地管理符合“场内标准化、场外景观化”的标准。
7.3 工作制度
7.3.1每周召开一次“施工现场文明施工和环境保护”工作例会,总结前一阶段的施工现场文明施工和环境保护管理情况,布置下一阶段的施工文明和环境保护管理工作。
7.3.2建立并执行施工现场环境保护管理检查制度。每周组织一次文明施工检查,参加人员包括项目部全体管理人员及劳务组现场负责人,对检查中所发现的问题,开出“隐患问题通知单”,各专业施工单位在收到“隐患问题通知单”后,根据具体情况,定时间、定人、定措施予以解决,项
目经理部相关部门监督落实问题的解决情况。
7.4文明施工及环境管理体系
(1)在项目经理部建立文明施工及环境保护体系,明确体系中各岗位的职责和权限,建立并保持一套工作程序,对所有参与体系工作的人员进行相应的培训。
(2)本工程施工现场严格按照现场管理规定进行管理,项目经理部下设2人左右的场容清洁组,每天负责施工场内外的清理、保洁、洒水降尘等工作。
8、施工现场场容布置及形象管理
办公区坐落在西侧临近圣惠路,场区内办公室前做绿化带。现场围挡封闭管理,西侧大门出入口采用门禁系统,办公区、生活区、生产区三区分离设置,我单位在施工现场场内沿路边设置彩钢镀锌铁皮围挡,围挡高度2米,围挡支撑采用40*40镀锌方管焊接,每隔4米设置一道斜撑,总长度约合440m左右。因施工场地内土方施工单位、基坑支护施工单位等多家单位同时施工,在北面我部设置1处入口,土方施工单位则设置一进一出两扇大门,出口处设置冲车装置,所有车辆出门必须清洗,防止污染场外道路。各出入口设门卫。围墙外表面图案定期清理保持整洁,并按照业主和行政管理部门意见及相关规定进行涂刷。
8.1 现场围墙、大门
施工现场实行封闭式管理,设置大门和不低于2m的景观围墙,围墙及大门设置位置详总平面布置图。大门采用防锈铁花门,大门及门柱牢固美观,高度不低于2m,围墙上设置企业标识。
8.2现场标牌
(1)施工现场入口处设置工程概况及管理人员名单和监督电话标牌,标牌写明工程名称、建筑面积、层数、业主、设计单位、施工单位、监理单位、项目经理及联系电话、开竣工日期等内容,标牌面积不小于0.9×1.4m,字体为仿宋体,标牌底边距离地面不低于1.1~1.5m。标牌字迹书写规范、美观、并保持整洁完好。
(2)现场入口的显著位置设“十一牌一图”标牌,包括现场施工总平面图、总平面管理、安全生产、文明施工、环境保护、质量控制、材料管理的规章制度和主要参建单位名称。
(3)为确保工程安全施工,现场设立足够的标志、宣传画、标语、指示牌、警告牌、火警、匪警和急救电话提示牌等等。
8.3施工总平面布置
(1)施工现场总平面布置按照布局紧凑、规范周密、管理方便和安全可靠的原则布置,同时符合劳动保护、安全生产、消防、卫生和文明施工等有关规定。
(2)施工现场应明确划分施工区、办公区和生活区,各区设标志牌,明确各区负责人。施工现场根据实际条件进行绿化,摆放盆花,保持清洁有序,绿色环保。
(3)为美化环境,工地周边及进出口无垃圾、无污水,做到安全、整洁、畅通,主要出入口和围墙边进行绿化和摆放盆花。工地内无乱搭乱接,保持干净整洁。
8.4材料堆码
施工现场建筑材料、构件、料具均按照总平面布局统一布置,分类码放整齐,堆码时材料分品种、规格等挂牌标志清楚,重要设备材料利用专门的围栏和库房储存,易燃易爆类物品分类存放。材料的存放场地平整夯实,排水畅通。
8.5现场卫生、医疗站和急救设施
(1)现场设立专门的临时医疗站,配备足够的设施、药物和称职的医务人员。现场准备足够数量的担架,以便发生突发事件时用于急救。
(2)现场请专业的卫生防疫部门定期对现场进行防疫,防止任何传染病的传播,定期进行卫生专业检查、处理,包括消灭白蚁、鼠害、蚊蝇和其它害虫,以防对施工人员、现场和永久工程造成任何伤害。
8.6机械设备管理
对施工机械进行全面的检查和维修保养,保证设备始终处于良好状态,避免噪音、废油和废弃物泄漏造成污染,杜绝重大安全隐患的存在。
9、文明施工、环境保护的检查措施
9.1项目部环境保护小组每周对施工现场的文明施工及环境保护进行一次全面检查,公司每月对项目部进行一次大检查,检查环境保护的组织措施、技术措施以及措施的落实情况。
9.2检查重点围绕场容布置、现场防火、治安综合治理、保健急救、社区服务、污染控制、废弃物管理、环保型材料设备的使用、维护场内正常秩序、垃圾清运、周边建筑物的保护等内容进行。
9.3每次检查均认真作好记录,指出不足之处并限期整改。对每次检查成绩突出者进行奖励,对出现较多不足者督促其整改并进行处罚。
9.4施工期间不应影响邻近建筑物、构造物的安全与正常使用,也不干扰群众的通行方便(难以避免的一定程度的干扰除外)。