脚手架搭设施工方案

时间:2019-05-14 03:47:29下载本文作者:会员上传
简介:写写帮文库小编为你整理了多篇相关的《脚手架搭设施工方案》,但愿对你工作学习有帮助,当然你在写写帮文库还可以找到更多《脚手架搭设施工方案》。

第一篇:脚手架搭设施工方案

Xxxx工程

外墙脚手架施工方案

一、工程概况.......................................................................1

二、脚手架的搭设方案.......................................................1

三、脚手架搭设要点...........................................................4

四、杆件搭设顺序...............................................................5 五、一般规定.......................................................................5

六、脚手架拆除...................................................................6

七、脚手架的使用规定.......................................................7

八、安全要求.......................................................................8

九、文明施工及成品保护.................................................10

十、计算书.........................................................................10

十一、脚手架搭设示意图.................................................16

0 Xxxx工程

外墙脚手架施工方案

一、工程概况 工程名称:

兴建单位:

监理单位:

施工单位:

XXXX工程位于XXXXXXXX,D、E座18层(含首、二层裙楼),建筑高度69.05m。外墙脚手架由(±0.00)开始搭设,属落地式脚手架,当施工完裙楼,外脚手架即搭设在裙楼的顶板上。

每6层楼设一次脚手架卸荷和按实际需要每4层设一道安全斜档板。每栋楼设一道施工梯及搭设落地式卸料平台1个。

二、脚手架的搭设方案

1、脚手架基础(见附图一)

脚手架地基应平整夯实,上铺150厚C20砼,靠建筑物边设200³300排水沟一道。脚手架立杆不能直接立于砼面上,应加设木垫板,垫板尺寸不得小于200³200³20。

2、立杆(见附图二)

立杆钢管采用φ48³3.5(外径³壁厚),钢管立杆纵距1.8m,步距1.9m,内排立杆离墙(20)㎝,小横杆内距0.7m,垂直偏差不大于架高的1/300,并同时控制其绝对偏差值,所有立杆采用单根钢管搭设。相邻立杆的接头位置应错开布置在不同的步距内,与相近大横杆的距离不宜大于步距的三分之一。立杆与大横杆必须用直角扣件扣紧,不得隔步设置或遗漏。立杆顶端应高出建筑物檐口上皮高度1.5米。立杆四角应垂直,保证脚手架外观 Xxxx工程

外墙脚手架施工方案

整齐。

3、桥架的搭设

桥架每层步距约1.9m,中间用钢管设水平杆一道,桥架排距宽度为70cm,内立竿距墙面20cm,桥架两边大横杆用钢管,中间铺设竹排。桥架每平方米荷载≤300Kg,不得在同一位置、上下层同时堆放过多材料。桥架两侧的大横杆用十字扣件装设在立杆上,内外大横杆要求平行,同一排横杆的水平偏差不大于该片脚手架总长度的1/250,且不大于50mm。上下横杆的接长位置应错开布置在不同的立杆纵距中,与相近立杆的距离不大于纵距的三分之一。每二步距设红白挡脚板一道。

4、小横杆

小横杆贴近立杆并布置在大横杆之下,用直角扣紧,在相邻立杆之间根据需要加设1根或2根,在任何情况下均不得拆除作为基本结构杆件的小横杆,同时要求小横杆悬挂端离墙面不能小于15cm。

5、剪刀撑

脚手架应根据确保整体稳定和抵抗侧力作用的要求,按照以下规定要求设置剪刀撑。

⑴、每隔4~6根立柱(约8~10米)沿长度和高度布置双向连续剪刀撑。剪刀撑应沿架高连续布置。剪刀撑的斜杆两端用旋转扣件与脚手架的立杆或大横杆扣紧外,剪刀撑接头搭接不小于1.0米,用2个旋转扣件。

⑵、剪刀撑应联系5~7根立杆,剪刀撑的斜杆与水平面的交角(或地面)在45°~60°夹角之间。

6、连墙杆

连墙杆采用刚性锚固,应尽量设置在立杆和大横杆的交叉位置,且每 Xxxx工程

外墙脚手架施工方案

层错开布置,每层楼面平面每隔6m以内设置一锚固点,竖向每层设一道,布置点设置在混凝土梁等刚性较大部位,用Φ12螺丝举行预埋,Φ48短钢管进行连接,防止棚架摆动,起到稳定作用,同时设置拉结点,用Φ8钢筋预埋在混凝土梁等刚性部位,每层错开,控制脚手架向外倾斜。脚手架上部未设置连墙杆的自由高度不得大于6m。连墙杆及拉结筋在外墙装修时不得随意拆除,如需拆除需得到上级主管部门的批准,并进行相应加固。

7、安全挡板

安全挡板设置在脚手架外侧,用钢管由内立柱到外立柱向外飘出2米,呈250角,面上铺扎密篙竹加铺安全网,第一层搭设高度约15米,以上每15米搭设一层。

8、安全围蔽

在脚手架平桥内四周用已送检合格的阻燃式密目安全网全封闭,上、中、下共设三点绑扎,顺桥架走向每50cm绑扎一点,四角要垂直,每搭设完一层桥架,安全网必须满挂,桥架严禁堆放模板、木枋、钢筋等。

9、施工梯设置

在脚手架外侧搭设,跟平桥高度搭设成单边梯上落,即上完一层施工梯转向内桥面,到梯台时再往上一层行走,上落梯台规格为1.5m³1m,梯级用钢管加木板用铁钉铺设,施工梯必须设置兜底安全网、侧网,施工梯两边高度约1.2米用钢管各设1条栏杆扶手,每级步高不得超过30cm,坡度宜采用1:3,每栋搭设一樘。

10、脚手架卸荷

用φ16钢筋做成双曲钩吊环,在楼层边梁预埋,预埋入砼边梁内48cm与梁钢筋连接,外露15cm,用φ14钢丝绳连接吊环向下斜拉吊置脚手架应 Xxxx工程

外墙脚手架施工方案

吊置位置(用钢丝绳穿过大小横杆底部,即兜底),每一条立竿吊拉1条(间距约1.8m),必须拉紧吊实,每条钢丝绳端部应不小于2个扎头,由裙楼面开始每隔6层设1道卸荷。

11、吊料平台设置

采用落地式搭设,每层楼面设1个开口,平台规格按现场实际要求搭设,面层铺设竹排,平台外侧设1.5米高护拦加安全网,吊料平台上方必须预埋吊环用钢丝绳斜吊,下方1.8m处设安全网,并悬挂限荷1.5吨标志牌。

12、脚手架的防雷

采用避雷针与大横杆连通,接地线与整幢建筑物楼层内避雷系统通过立杆连成一体的措施。避雷针采用φ12镀锌圆钢制作,高度不小于1米,设置在脚手架四角立柱上,并将所有最上层的大横杆全部连通,形成避雷网格。

13、栏杆、脚手板

栏杆和挡脚板应搭设在外排立柱的内侧,栏杆上皮高度0.9m,居中设置,挡脚板高度不应小于180mm。

三、脚手架搭设要点

1、杆件连接构造一般规定

钢管脚手架左右相邻立杆和上下相邻平杆的接头应相互错开并置于不同的构架框格内。

钢管脚手架搭接杆件接头长度应≥0.8m。

2、架杆配件的一般规定

钢管件采用Ф48³3.5焊缝钢管,钢管的端部切口应平整。禁止使用有明显变形、裂纹和严重锈蚀的钢管。Xxxx工程

外墙脚手架施工方案

应使用与钢管管径相配合的、符合我国现行标准的可锻铸铁构件。

四、杆件搭设顺序

其搭设顺序为:底座制砼→立杆→水平扫脚杆→大横杆→小横杆→加设临时剪刀撑→连墙杆→护拦杆→剪刀撑→绑扎架桥→张挂安全网→循环搭设。五、一般规定

1、在搭设之前,必须对进场的脚手架杆配件进行严格的检查,禁止使用规格和质量不合格的杆配件。

2、脚手架的搭设作业必须在统一指挥下,严格按照规定程序进行。

3、按施工设计方案设置立杆位置。

4、周边脚手架应从一个角部开始并向两边延伸交圈搭设。

5、应按定位依次竖起立杆,将立杆与纵杆、横杆与扫地杆连接固定,然后安装纵向和横向平杆,随校正立杆垂直之后予以固定,并按此要求继续向上搭设。在设置第一排连墙件前,应设置必要的固定措施,以确保构件稳定和架上作业人员的安全。

6、剪刀撑、斜杆等整体拉结杆件和连墙件应随搭升的架子一起及时设置。

7、扣件要扣紧,并注意拧紧程度要均匀适当,杜绝使用变形的杆和不合格扣件。

8、随时校正杆件的水平偏差和垂直偏差,保证脚手架质量和整齐。

9、下班和临时停工应采取临时措施,保证脚手架整体的安全和稳定。

10、扣件安装:开口朝向应合理,避免雨水流入。立杆大横杆和小横 Xxxx工程

外墙脚手架施工方案

杆的相接点到扣件中心距离不大于150mm,杆件的对伸长度不小于100 mm,底部斜杆与立杆的连接扣件离地不大于500 mm。

11、连墙杆:是关系脚手架安全和稳定的保证,应尽量设置在立杆和大横杆的交叉位置。

12、所有钢管接驳位应错开布置,并用直驳扣拧紧。

13、在所有外脚手架及安全挡板上满挂(铺)密目式防火安全网,接缝严密,不允许出现孔洞。首层外脚手架平桥与建筑物之间的空隙用安全网密封。安全网需经检验合格后方能用于本工程。

六、脚手架拆除

1、拆除说明

脚手架的拆除作业应按正确的拆除程序进行。连墙件应在位于其上的全部可拆杆件都拆除之后才能拆除。在拆除过程中,凡已松开连接的杆配件应及时拆除运走,避免误扶和误靠已松脱连接的杆件。拆下的杆配件应以安全的方式运出和吊下,严禁向下抛掷。在拆除过程中,应作好配合、协调动作,禁止单人进行拆除较重杆件等危险性作业。

2、拆除顺序

拆除扣件式钢管脚手架的原则是先搭设的后拆除,后搭设的先拆除,具体拆除程序为:安全网→护身栏→小横杆→大横杆→立杆→连墙杆→剪力撑。

3、一般要求

⑴、先拆除两层安全网,然后按顺序逐层由上而下进行,严禁上下同时作业。

⑵、所有连墙杆件应随脚手架逐层拆除,严禁先将连墙杆件整层或数 Xxxx工程

外墙脚手架施工方案

层拆除后再拆除脚手架,分段拆除高差不应大于2步,如高差大于2步,应增设连墙件加固。

⑶、当脚手架拆至下部最后一根长管的高度时,应先在适当位置搭临时抛撑加固后,再拆连墙杆。

⑷、在拆棚过程中严禁单人操作,拆立杆时必须要有人配合,密切注意马路面来往车辆和行人动向,拿稳杆件、扣件和螺丝等零件,拆下的零件应用袋装好放置在室内安全的地方,集中运至地面,以免散坠下伤人。

⑸、参加搭、拆作业人员,一律不准酒后操作,操作时必须思想集中,不准说笑,打闹或擅自离开工作岗位。

⑹、钢管上的扣件要全部拆除,拆下的各种材料应分类堆放。参加拆除脚手架的工作人员必须按安全要求,带好安全帽系好安全带,穿好防滑鞋,不穿带好防护用具的人不得从事脚手架的搭、拆工作。

七、脚手架的使用规定

1、作业层每1m2架面上实用的施工荷载(人员、材料和机具重量)不得超过以下的规定值或施工设计值。

2、施工荷载(作业层上人员、器具、材料的重量)的标准,结构脚手架采取2KN/m2。

3、不准在架板上堆放标准砖、砂浆和容器、施工设备等。

4、严禁上架人员在架面上奔跑、退行。

5、作业人员在架上的最大作业高度应以可进行正常操作为度,禁止在架板上加垫器物或单块脚手板以增加操作高度。

6、在作业中,禁止随意拆除脚手架的基本构架杆件、整体性杆件、连接紧固件和连墙件。确因操作要求需要临时拆除时,必须经主管人员同 Xxxx工程

外墙脚手架施工方案

意,采取相应弥补措施,并在作业完毕后,及时予以恢复。

7、工人在架上作业中,应注意自我安全保护和他人的安全,避免发生碰撞、闪失和落物。严禁在架上戏闹和坐在栏杆上等不安全处休息。

8、人员上下脚手架必须走安全防护的出入通(梯)道,严禁攀援脚手架上下。

9、每班工人上架作业时,应先行检查有无影响安全作业的问题存在,在排除和解决后方可开始作业。在作业中发现有不安全的情况和迹象时,应立即停止作业进行检查,解决以后才能恢复正常作业;发现有异常和危险情况时,应立即通知所有架上人员撤离。

10、在每步架的作业完成之后,必须将架上剩余材料物品移至上(下)步架或室内;每日收工前应清理架面,将架面上的材料物品堆放整齐,垃圾清运出去;在作业期间,应及时清理落入安全网内的材料和物品。在任何情况下,严禁自架上向下抛掷材料物品和倾倒垃圾。

八、安全要求

为确保脚手架的构架和防护设施达到使用安全的要求,应做好以下几个方面:

1、杆件Φ48钢管的质量和允许缺陷进行全面检查,确保杆件符合搭设要求。

2、严格按照脚手架搭设设计方案要求施工,使搭设尺寸以及对误差的控制须满足方案要求。

3、附墙杆的设置方式、布点间距以及对连墙点的结构加强均要严格按照方案施工,确保附墙杆起到有效作用。

4、对作业层进行铺板,做好防护措施。Xxxx工程

外墙脚手架施工方案

5、对脚手架实际使用荷载进行控制,包括脚手架上施工人数、材料堆放数量和位置以及多层同时作业时的控制。

6、对施工过程中需要临时拆除杆部件和拉结件的限制以及在恢复前的安全弥补措施要落实,同时要落实检查工作,消除施工安全隐患。

7、脚手架地基要严格按照方案处理。

8、安全网以及其它防护措施均要严格按照要求设置。

9、搭拆过程中注意问题:

⑴、不能随意改变构架结构及其尺寸,特别是立杆间距、附墙点数、卸荷数量等。杜绝使用不合格的杆配件和材料。

⑵、不能随意减少铺板数量、防护杆件和设施。在不符合要求的地基和支持物上不采取措施搭设脚手架,不得在六级以上大风、雷雨天继续作业。⑶、不按质量要求搭设,立杆偏斜,拉结点松弛,起不到有效拉结作用。不按规定的程序和要求进行搭设和拆除作业,包括在搭设时未及时设置拉撑杆件,在拆除过程中过早地拆除拉结杆件。

⑷、在搭设和拆除架体过程中,未采取或未有效采取安全防护措施,包括不设置防护和使用安全防护用品。⑸、不按规定设置安全网。

⑹、随意增加上架的人员和材料,引起超载。⑺、任意拆除构件的杆配件和拉结措施。⑻、任意抽掉、减少作业层脚手板。

⑼、站在不具备操作条件的横杆上或单块板上操作。

⑽、加强管理人员和施工人员的教育,提高自我保护意识和素质。

Xxxx工程

外墙脚手架施工方案

九、文明施工及成品保护

(1)、作业人员必须持证上岗,进入施工现场要戴好安全帽,着装整齐。

(2)、对施工场地的物料进行及时堆放,做到工完料清。

(3)、在脚手架搭设及拆过程中,严格按操作程序施工,对重点部位进行严格保护,确保成品安全。

十、计算书

1、计算说明:

⑴计算参考书为《建筑施工脚手架实用手册》,计算中的公式与查表数据均由手册中查得。

⑵搭设尺寸:根据本章表4—7推荐的脚手架常用尺寸,试选搭设尺寸如下:步距=1.9m,柱距=1.8m,连墙件竖向间距H1 =3m,水平间距L1=6m,安全网尺寸为3.5cm×3.5cm,绳径3.2mm,并取整个脚手架的步距,柱距及连墙件间距相等或相近,先按以上尺寸对立柱进行稳定验算。脚手架搭设高度Hd=51.5m,采用φ48×3.5钢管,材料为Q235(3号)钢,脚手架排距Lb=0.7m,脚手架用于外墙装修,按照两层同时作业计算。

3.立柱稳定验算

本脚手架以相等的步距、柱距、排距、连墙件间距搭设,底层的立柱段所受压力最大,为脚手架的验算部位。(1)w计算

验算部位应根据风荷载产生弯曲压应力大小分析确定,故先计算风荷载产生压应力w Xxxx工程

外墙脚手架施工方案

立网封闭的挡风系数及风荷体型系数参照《建筑结构荷载规范》近似按以下方法计算:3.53.50.321.050.19

23.53.其中 1.05为考虑筋绳的影响。

s1.21.20.1920.23

立网传给立柱的风荷载标准值按式(4—4)计算,风压高度系数z按表4—19中B类取

值,当H=51.5m时,z=1.67,计算风荷载:

k0.7zs0 =0.7 ×1.67×0.23×0.50=0.14kN/m 2

作用于立柱的风线荷载标准值;

qwk =k×l=0.14×1.8=0.252KN/m

风荷载产生的弯矩按式4—33计算

MW1.4qwkh2=1.4*0.252*1.92/10=0.127 KN.m 10

在51.5m高度处立柱段风荷载产生弯曲压应力:

w=MW=0.127*106/(5.08*103)=25 N/mm 2 W

以上计算结果说明,风荷产生的压应力虽在50m高度处稍大,但此处的脚手架结构自重产生的轴压应力很小,且w的绝对值也不大,根据以上分析,仍应验算底层立柱段的稳定性。

(2)底层主柱段的轴心压力

1)脚手架结构自重产生的轴心压力NGK:

由表4—38查得一个柱距范围内每米高脚手架结构自重产生的轴心压力标准值:

gK=0.125KN/m2 Xxxx工程

外墙脚手架施工方案

则51.5高的脚手架结构自重产生轴心压力标准值:

NGK=H·gK =51.5×0.125=6.44KN

2)脚手架活荷载产生的轴心压力:

根据脚手架高度51.5m,按本章4.4.2之四要求,脚手板共15层,查表4—39得脚手板产生轴心压力:

NQ1K=0.5lb0.3lQP=0.5(0.70+0.3)×1.2×0.3×15=2.7KN 脚手架的防护材料产生轴心压力,查表4-40得: NQ2K`=0.228KN,安全网自重:0.01×1.5×50=0.75KN 则NQ2K=0.228KN+0.75KN=0.978 KN 根据装修用途脚手架,两层同时操作,施工均布荷载Qk=2×2.0=4.0kN/m2,查表4—41得施工荷载产生轴心压力: NQ3k=4.06KN

根据公式(4—32),荷载产生轴心压力标准值为

Ni1nQiK = NQ1k + NQ2k + NQ3k=2.7+0.978+4.06=7.738 KN

3)根据公式(4—31)立柱轴心压力设计值,n1.2N=NGK1.4NQiK=1.2*6.44/0.75+1.4*7.738=21.13KN k1i1(分母k1根据H=51.5m,查表4-35得k1=0.75)

(3)立柱稳定性验算

立网封闭时,根据公式(4—32),立柱稳定应满足下式:N≤Afcw

查手册,φ48×3.5钢管,对=0.336,A=4.890cm2,fc=180N/mm2,W=5.08 cm3,代入上式:

Afcw=O.336×4.89×102(180-8.96)×10-3 Xxxx工程

外墙脚手架施工方案

=28.10KN>N=21.13kN 立柱满足要求。

(4)连墙杆采用φ48×3.5钢管,连墙杆的计算长度可取脚手架的离墙距离,lh=500 mm,因此长细比=

lh=51.5/1.58=32.6,查表4-37A,=0.912,i风荷载产生的水平力设计值:Hw =kAW=1.4×3.6×4.5=3.1752KN NH =Hw+3.0=3.1752 +3.0=6.1752 KN

≤Afc=0.912×4.89×102×210=93.653 KN 连墙杆稳定荷载能力够。

φ8钢筋的受拉力:N=Afc=50.27×210=10556 N =10.556 KN

≥Hw+3.0=3.1752 +3.0=6.1752 KN

4.钢丝绳验算

钢丝绳拉吊按实际卸荷最大高度为2~7层共六层楼高,即3.0³6=18米,n1=18/1.9=10步架高,平桥也共12步,按两层同时施工计算。1)脚手架结构自重产生的轴心压力NGK:

由表4—38查得一个柱距范围内每米高脚手架结构自重产生的轴心压力标准值:

gK=0.125KN/m2

则18米高的脚手架结构自重产生轴心压力标准值:

NGK=H·gK =18×0.125=2.25KN 2)脚手架活荷载产生的轴心压力:

脚手板共6层,查表4—39得脚手板产生轴心压力:

NQ1K=0.5(0.70+0.3)×1.2×0.3×6=1.08KN Xxxx工程

外墙脚手架施工方案

脚手架的防护材料产生轴心压力,查表4-40得: NQ2K`=0.228KN,安全网自重:0.01×1.5×18=0.27KN 则NQ2K=0.228KN+0.27KN=0.498KN 根据装修用途脚手架,两层同时操作,施工均布荷载Qk=2×2.0=4.0kN/m2,查表4—41得施工荷载产生轴心压力:NQ3k=4.06KN

根据公式(4—32),荷载产生轴心压力标准值为

Ni1nQiK = NQ1k + NQ2k + NQ3k=1.08+0.498+4.06=5.638 KN

3)根据公式(4—31)立柱轴心压力设计值,n1.21.22.251.45.638=11.493KN N=NGK1.4NQiK=0.75k1i1则取P1=P2=5.75KN,T2=P15.755.75 ===5.98 KN coscos90740.96查建筑施工手册2,本工程选用规格为6³19,绳芯Ⅰ型钢丝绳,查手册表14-2选φ14,Fg ——钢丝绳钢丝破断拉力总和, φ14钢丝绳公称抗拉强度1400 N/mm2为125 KN。

K—— 钢丝绳使用安全系数,按规范取

K=6

——考虑钢丝绳钢丝受力不均匀的钢丝破断拉力换算系数,查手册选a=0.85 Fg0.85125

则:Fg≥= =13.28 KN

8K大于钢丝绳的最大拉力5.98 KN,安全。5.吊环验算 Xxxx工程

外墙脚手架施工方案

工程结构上预埋吊环的计算: 根据《混凝土结构设计规范》(GBJ10—89)第7、8、9条规定,吊环应用Ⅰ级钢筋制作,严禁使用冷加工钢筋,吊环焊接在钢板上的封闭环,每个吊环可按两个截面计算,吊环拉应力不应大于50N/㎜2。

一个吊环承受内、外立柱上两条钢丝绳的拉力,安全系数取3.5倍,本工程选用φ16钢筋吊环,吊环钢筋截面积201㎜2, 210N/m2³201㎜2=42210N=42.210 KN

≥3.5³11.493㎜2 =40.223 KN

所以,安全。

PPP2T2P2700200²

Xxxx工程

外墙脚手架施工方案

吊环拉结筋钢丝绳

十一、脚手架搭设示意图

脚手架垫板厚砼垫层排水沟夯实地基附图一 脚手架基础

Xxxx工程

外墙脚手架施工方案

剪刀撑满挂阻燃密目式安全网拉结筋短钢管排栅立杆20045°外脚手架搭设立面外排栅拉结大样满挂阻燃密目式安全网外脚手架搭设平面示意附图二

吊料平台立面图 Xxxx工程

外墙脚手架施工方案

第二篇:脚手架搭设施工方案

脚手架搭设施工方案

一、编制说明

为了确保武汉佳源花都三期27#楼工程的施工安全,给操作人员创造一个良好的操作环境,避免事故发生,保证外脚手架搭设使用安全管理,同时在本工程的脚手架搭拆过程中,更好地利用规范规定的要求,达到稳固、美观。

本方案作为武汉佳源花都三期27#楼工程脚手架工程搭拆施工的指导和安排。

二、编制依据

1、《建筑施工扣件式钢管脚手架安全技术规范》(JG130-2002);

2、《建筑施工安全检查标准》(JGJ59-99);

3、《建筑安装工人安全技术操作规程》(JGJ22-85);

4、《钢管脚手架扣件》(JGJ22-85);

5、本工程的《施工组织设计》;

三、概要说明

本工程五层向下为落地架,五层以上采用14#工字钢挑架,落地架与挑架搭设参数一致,落地架搭设双排架,内立杆距离结构外墙皮400mm,与主体结构连接点的距离,按二步三跨布置,每根连墙杆控制脚手架的面积不超过40平方米,脚手架钢管采用直径为48mm,壁厚3.5mm。

四、管理目标

1、安全目标:本脚手架在搭设过程中,安全事故为“零”。

2、质量目标:按照《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2002)的要求,搭设规范、稳固、连接牢固、拉结到位、外型美观,验收一次合格。

3、文明施工目标:做到工完料尽场地清,达到“省级文明工地”的验收标准。

五、搭设措施

1、组织措施:

项目部成立悬挑架搭设安全领导小组,设组长一人,成员二人,具体分工如下:组长:项目经理李艳明,负责脚手架搭设所需资源的配备,协调和技术交底参加验收。副组长:项目部技术负责人李英强,负责脚手架工程的施工方案技术交底,进行过程监督,按规范标准组织验收。

成员:项目部安全员孔庆雄,负责脚架搭设的指导,安全教育,过程控制,参加验收,

第三篇:脚手架搭设施工方案(中英文)

录 Directory

一、施工地点:Job location....................................................................................1

二、参照标准: Basis of compiling...................................................................2

三、材料标准:Material streamlined specification.......................2

(一)钢管:Steel pipe..............................................................................................2

(二)扣件:Fastener.................................................................................................3

(三)脚手板:Scaffold board..............................................................................3

(四)安全网:Protecting net................................................................................3

四、施工工艺:Construction technique...................................................3

(一)施工准备:Preparations for construction..........................................3

(二)脚手架搭设的要求:Requirement of scaffold...............................4

A、立杆构造要求:Vertical.......................................................................5 B、纵向水平杆的构造要求:Longitudinal horizontal bracing....5 C、横向水平杆的构造要求:Transverse horizontal bracing........6 D、脚手板的设置:Scaffold board laying..............................................6 E、剪刀撑:X-bracing.......................................................................................7 F、扣件:Fastener................................................................................................7

(三)脚手架的使用:Requirement of use the scaffold..........................8

(四)脚手架的拆除:Demolition the scaffold...........................................8

五、注意事项:Notice proceeding.................................................................8

一、施工地点:Job location ****化工区工业气体二期管道设备保温工程

**** caojing HYCO1 STEP-2 insulation project

二、参照标准: Basis of compiling JGJ130-2001

建筑施工扣件式钢管脚手架安全技术规范

《Steel pipe scaffold safety code of building construction with the fastener》

三、材料标准:Material streamlined specification

(一)钢管:Steel pipe

1、脚手架钢管采用外径48mm,壁厚3.5mm,横向水平杆≤2200mm,其他杆≤6500mm,每根钢管不应大于25kg。

2、钢管表面应平直光滑,不应有裂缝、结疤、分层、错位、硬弯、毛刺、压痕和深的划道。

3、钢管的外径、壁厚、端面等的偏差,应分别符合《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2001)的有关规定。

1.The external diameter of the steel pipe is 48mm, and thickness of pipe wall is 3.5mm.Transverse horizontal bracing shall be less than 2200mm,others less than 6500mm,and every steel pipe shall be less than 25kg.2.The surface of the steel pipe shall be smoothness, and has not the crack, dogs ear, delaminating, burr and deep nick etc.3.The deviation of the steel pipe, as the external diameter, thickness of pipe wall, port etc, shall be accord the code 《Steel pipe scaffold safety code of building construction with the fastener》

(二)扣件:Fastener

1、扣件采用48型。扣件的类型包括:直角扣件、旋转扣件、对接扣件、防滑扣件。

2、脚手架采用的扣件,其材质应符合国家现行标准。

1.Fastener adopt the type of 48,and the types include the right-angle, circumgyrate, butt joint, and slip-resistance.2.The fastener of the scaffold shall be accord the GB code.(三)脚手板:Scaffold board

1、脚手板采用木质,每块质量不宜大于30kg。

2、木脚手板应采用杉木或松木制作,其材质应符合国家现行标准。

3、脚手板的宽度不宜小于200mm,厚度不应小于50mm,两端应各设直径4mm的镀锌铁丝绑扎两道。

1.Every scaffold’s quality shall be less than 30kg.2.Scaffold board shall be make of the fir or deal, and accord the GB code.3.The width of the scaffold board shall be over 200mm and thickness over 50mm.On the ends with the 4mm galvanized wire fixing the board.(四)安全网:Protecting net 在脚手架施工操作面和护栏四周围上防护网。

It shall be laying safety netting on the operating platform and protecting fence.四、施工工艺:Construction technique

(一)施工准备:Preparations for construction

1、工程负责人应按施工组织设计中有关脚手架的要求,向架设和使用人员进行技术交底。

2、应对所有进场材料按规范进行验收,不合格产品不得使用。

3、经检验合格的构配件应按品种、规格分类、堆放整齐、平稳,堆放场地不得有积水。

4、当脚手架基础下有设备基础、管沟时,必须采取加固措施。

1.The project manager shall be show the regulations for technical operation on the operation worker, about scaffold in this scheme.2.All the material must be check and acceptance, and no qualification no use.3.The qualification material shall be stack-up regularity and firmness.The place shall be no water.4.When it has equipment foundation, pipe duct under the base of scaffold, it must to be consolidation.(二)脚手架搭设的要求:Requirement of scaffold

1、所搭设的脚手架要坚固、稳定,保证在施工期内及各种载荷和气候条件下不产生变形,不倾斜、不摇晃,安全可靠。

2、根据搭设空间,选用适宜的脚手架钢管长度。必须有足够的空间,满足操作、材料堆放及行人的要求。

3、脚手架的搭设宽度根据构造要求不能小于1-1.3m,作业层大横杆间隔La/2m,小横杆间隔不能大于纵距的1/2,立杆横距不能大于1-1.3m,立杆纵距不能大于1.5-2.0m。

4、K201-K202整体脚手架重大约16T,搭设面长10.3米宽4.6米高度30米,搭设时层面和作业平台连接.支撑以减少整体负荷, 施工人员上下可利用原有设施,作业平台和施工平面须使用梯子上下。

1.The scaffold must be firmness, steadiness.During the useful time, it must be no deformation, no inclination, no sway and safety on the kind of load and climate.2.The pipe of the scaffold must be select the suitable length by the building space, and the space must be enough to suitable for operate, material stack-up and passage.3.The width of the scaffold shall be more than 1-1.3m.In the operating lay, the big traverse bar shall be distance La/2m, and the small traverse bar shall be less than 1/2 of longitudinal distance.The traverse distance of vertical shall be less than 1-1.3m, and longitudinal less than 1.5-2.0m.4.The scaffold weight of the equipment K201-K202 is about 16T,length about 10.3m, width 4.6m, and height about 30m.When it’s building, the operating lay join the platform to reduce the load.The worker may be use the device, when they up and down, but on operating lay must be use the ladder.A、立杆构造要求:Vertical

1、脚手架必须调协纵、横向扫地杆。纵向扫地杆应用直角扣件固定在距底座上皮不大于200mm处的立杆上,横向扫地杆应用直角扣件固定在紧靠纵向扫地杆下方的立杆上。

2、当立杆基础不在同一高度上时,必须较高处的纵向杆向低处延长,与立杆固定,高低差不应大于1m。

3、立杆接长除顶层顶步可采用搭接外,其余各层各步接头必须采用对接扣件连接。

1.When the scaffold build, it shall be harmonize the vertically and horizontally pipe.The vertically pipe shall be fix the base with the right-angle fastener and less than 200mm.The horizontally pipe shall be fix under the vertically pipe tightly with the right-angle fastener.2.When the vertical base is not on the same plane, it shall be extend from highness to lowness, and the gap shall be less than 1m.3.When the vertical join each other, it must be use the butt joint fastener, but the top.B、纵向水平杆的构造要求:Longitudinal horizontal bracing

1、纵向水平杆宜设置在立杆内侧,其长度不宜小于3跨。

2、纵向水平杆接长宜采用对接扣件连接,也可采用搭接。

3、当使用木脚手板时,纵向水平杆应作为横向水平杆的支座,用直角扣件固定在立杆上。

1.Longitudinal horizontal bracing shall be inside the vertical and length shall be more than 3 span.2.Longitudinal horizontal bracing may be use the butt joint or lap joint with the fastener.3.When use the scaffold board, longitudinal horizontal bracing is the base of the transverse horizontal bracing, and fix the vertical with the right-angle fastener.C、横向水平杆的构造要求:Transverse horizontal bracing

1、主节点处必须设置一根横向水平杆,用直角扣件扣紧且严禁拆除。

2、主节点处两个直角扣件的中心距不应大于150mm。

3、作业层上非主节点处的横向水平杆,宜根据支承脚手板的需要等间距设置,最大间距不应大于纵距的1/2。

1.The central node must be set one transverse horizontal bracing and forbid backout.2.The two right-angle fastener of the central node shall be less than 150mm each other.3.The transverse horizontal bracing of the other node on the operating lay which is not the central, shall be set base on needs, and the max distance shall be less than 1/2 of the longitudinal.D、脚手板的设置:Scaffold board laying

1、作业层的脚手板应铺满、铺稳。

2、脚手板应设置在三根横向水平杆上。当脚手板的长度小于2m时,可采用两根横向水平杆支承,但应将脚手板两端与其可靠固定,严防倾翻。

3、脚手板可采用对接平铺或搭接铺设。

4、作业层上端部脚手板探头长度应取150mm,其板长度两端均应与支承杆可靠固定,可用直径3.2mm的镀锌铁丝固定在支承杆杆上。1.The scaffold board of the operating lay shall be pave the all and fixedness.2.The scaffold board shall be lay on three transverse horizontal bracing, when length less than 2m, it may be use the two, but must fix on the ends.3.The scaffold board may be butt joint or lap joint.4.The ends of the scaffold board on the operating lay shall be overstep about 150mm and fix it on the knighthead with the 3.2mm galvanized wire.E、剪刀撑:X-bracing

1、脚手架的两端、转角处及每隔5-7个立杆必须设剪刀撑,并由底至顶连续设置,斜杆与地面的夹角为45°-60°,中间各道剪刀撑之间的净距不应大于15mm。

2、剪刀撑斜杆的接长宜采用搭接。

1.The scaffold must set the X-bracing on the ends, turns and alternation 5-7 vertical.It must be from bottom to top.The diagonal’s angle is 45-60°to the ground.Each X-bracing distance shall be less than 15mm.2.The distance of X-bracing shall be use the lap joint.F、扣件:Fastener

1、扣件规格必须与钢管外径相同。

2、对接扣件开口应向上或向内。

3、各杆件端头伸出扣件盖板边缘的长度不应小于100mm。

1.The spec of fastener must be same as the external diameter of pipe.2.The open of butt joint fastener shall be up or entad.3.The length shall be more than 100mm, which overstep the fastener on the ends of pipe.(三)脚手架的使用:Requirement of use the scaffold

1、没有经过验收的脚手架一律严禁使用。

2、脚手架使用前,必须认真检查脚手架是否完好、牢固,如有异常应立即提出整改,合格后方能使用。

3、应定期检查安全防护措施是否符合要求,扣件螺栓是否松动及是否超载等。1.The scaffold must be check and acceptance.2.Before use the scaffold, it must to checked.If it has abnormity, it must to refit.3.It must check the means of safety termly, and must be up to the mustard.(四)脚手架的拆除:Demolition the scaffold

1、应根据现场情况及业主要求,及时进行脚手架的拆除工作。

2、脚手架拆除前,应清除脚手架上杂物及地面障碍物。

3、拆除作业应由上而下逐层进行,严禁上下同时作业。

4、拆下的脚手架材料应及时运走,不乱堆乱放。

5、拆除后,应及时对现场清理,保持场地清洁。

1.It shall be dismantle the scaffold in time, by the requirement of the owner and case of the locale.2.Before dismantle the scaffold, it must be clean the sundries on scaffold and the abattis on the ground.3.Dismantle the scaffold shall be from up to down.Prohibit labour at one time.4.The material which is dismantle shall be carry out in time.5.After finish, it shall be clean the locale in time, keep up the cleanness.五、注意事项:Notice proceeding

1、安装钢脚手架时,禁止使用弯曲、压扁或有裂缝的钢管,连接部分要完整无损,以防倾倒或移动。

2、钢脚手架的立杆,必须垂直稳放在垫木的钢板上,在安置垫木前要将地面夯实、整平,并采取防滑措施。

3、搭设脚手架人员必须按规定穿戴好防护用品。

4、安全网应按有关规定搭设和拆除。

5、在脚手架使用期间,禁止拆除主节点处纵、横向水平杆和纵、横向扫地杆。

6、搭拆脚手架时,地面应设围栏和警戒标志,并派专人看守,严禁非操作人员入内。

1.When build the scaffold, that pipe which has bend, bruising or crack, is prohibit to use.And the part of join shall be intactness.2.When build the vertical, the ground shall be tamp, flattening and avoid slip.3.The workers, who build the scaffold shall be dress the protective measure that necessary.4.Safety netting must be accord the code when it building and demolition.5.During the scaffold use, prohibit demolition the vertically and horizontally bracing on the central node.6.When demolition the scaffold, it shall be set up the sign, and prohibit come into who is not the workers.2013年9月

Sep.9.2013

第四篇:基坑施工脚手架搭设方案(定稿)

边坡施工脚手架搭设方案

一、工程概况

本工程位于……..,属于高边坡施工。

根据实际情况,以边坡施工为编制对象最高为8~10米的外脚手架,密目网围护。

二、搭设材料

1、搭设脚手架全部采用ф48mm,壁厚3.5mm的钢管,其质量符合现行国家标准规定。

2、脚手架钢管的尺寸、横向水平杆最大长度2.2m,其它杆最大长度为6.5 m,每根钢管的最大质量不小于25KG。

3、钢管表面平直光滑,无裂缝、结疤、分层、错位、硬弯、毛剌、压痕和深的划痕。

4、钢管上严禁打孔,钢管在便用前先涂刷防锈漆。

5、扣件材质必须符合《钢管脚手架扣件》(GB15831)规定。

①新扣件具有生产许可证,法定检测单位的测试报告和产品质量合格证。对扣件质量有怀疑时,按现行国家规定标准《钢管脚手架扣件》(GB15831)规定抽样检测。对不合格品禁止使用。

②旧扣件使用前,先进行质量检查,有裂缝、变形的严禁使用,出现滑丝的螺拴进行更换处理。

③新、旧扣件均进行防锈处理。

6、脚手片用毛竹脚手片,无发霉、腐蚀。

7、密目式安全网必须有建设主管部门认证的产品。

三、地基与基础

1、脚手架地基与基础的施工,根据脚手架搭设高度,原土或回填土必须事先进行夯实,(地基能承受0.8kg/c㎡的压力)后用C20砼浇筑厚度大于10cm硬化,2m平面沿杆基础周边位置,基础和能承受上澡结构荷载。

2、脚手架底面标高高于自然地坪50mm

3、立杆基础外侧设置截面20cm×20cm的排水沟。

四、脚手架设计尺寸

1、脚手架底步距为1m,其余每步为1.8m。

2、立杆纵距为1.5m,横距为1.2m。边坡上纵、横距均为1.5m。

3、踢脚杆、防护杆从第二步起设置分别为0.3m和1.2m,顶排防护栏不少于二道,高度分别为0.9m、1.3m。

4、剪刀撑设置为间距为9m(6跨)一排剪刀撑。

5、连墙杆件设置为竖向每层、水平向为四跨。

五、纵向、横向水平杆、脚手板、防护栏杆、踢脚杆

1、纵向水平杆设置在立杆内侧,其长度不小于3跨。纵向水平杆接长采用对接扣件连接,交错布置,两根相邻纵向水平接头设置相互错开不小于500mm,各接头中心至最近主节点的距离不大于纵距的1/3。

2、纵向搭接长度不小于1米,并等间距设置3个旋转扣件固定,端部扣件盖板边缘至搭接纵向水平杆杆端的距离不小于100mm。

3、纵向水平杆的各节点处采用直角扣件固定在横向水平杆上。

4、横向水平杆的各个节点处必须设置并采用直角扣件扣接且严禁拆除。

5、脚手片必须垂直于墙面横向铺设,满铺到位,不留空位。四角用18铁丝双股并联绑扎,固定在纵向水平杆上,要求绑扎牢固,交接处平整,无空头板。

6、脚手片底层满铺,中间每隔三层,操作层的上下层顶层都必须满铺。

7、脚手片外侧自第二步起必须设1.2m高同材质的防护栏和30cm高处的踢脚杆。

六、立杆

1、每根立杆垂直稳放在垫板上。

2、脚手架里立杆距离边坡净距为20cm,大于20cm处的须铺凤站人脚手片,并设置平稳牢固。

3、脚手架怕须设置纵、横向扫地杆。纵向扫地杆采用直角扣件固定在距离底座上不大于200处的立杆上。横向扫地杆亦采用直角扣件固定在紧靠纵向扫地杆下方的立杆上。当立杆基础不在同一高度上时,必须将高处的纵向扫地杆向低处延伸长两跨与立杆固定,高低差不小于1m。靠边坡上方的立杆轴线到边坡的距离不小于500mm。

4、立杆必须用连墙件与边坡可靠连接。

5、立杆接长除顶层步可采用搭接外,其余各层各步接头必须用①、对接扣件连接。对接、搭接均须符合下列规定。

立杆上的对接扣件交错布置,两根相邻立杆的接头相互错开,不设置在同步内,同步内隔一根立杆的两个相隔接头在高度方向错开的距离不小于500,各接头中心至主节点的距离不大于步距的1/3。

②、搭接长度不应小于1m,应采用不小于2个旋转扣件固定,端部扣件盖板的边缘至杆端距离不应小于100mm.七、连接件

1、连接件数量的设置,坚向间距为每层,横向间距为4跨。

2、连接件的布置;

①宜靠近主节点设置,偏离主节点的距离不应大于300mm。

②应从底层第一步纵向水平杆处开始设置。

③宜优先采用菱形布置,也可采用方形,矩形布置。

④采用锚杆与边坡锚入连接,可采用Φ48钢管预埋打入边坡中,钢管与钢管用扣件连接方式。

八、剪刀撑、安全网

1、每道剪刀撑跨越立杆的根数6根(小于9m)。

2、与地面的倾角宜在450~600之间。

3、应在外侧立面整个长度和高差上连接设置剪刀撑。

4、剪刀撑斜杆的接长宜采用搭接,搭接长度不应小于1m:两根撑杆须交错布置,同立杆的交错相同。

5、剪刀斜杆应用旋转扣件固定在与相交的横向水平杆的伸出端或立杆上,旋转扣件中心线至主节点的距离不宜大于150mm。

6、一字型、开口型双排脚手架的两端均必须设置横向斜撑,中间宜每隔6跨设置一道。

7、脚手架外侧必须用建设主管部门认证的合格的密目式安全网封闭,且应将安全网固定在脚手架外立杆里侧,应用18#铅丝张持严密。

九、斜道

1、采用之字型斜道,宜附着外脚手架或建筑物设置。

2、人行斜道宽度不宜小于1m,坡度宜采用1:3。

3、拐弯处应设置平台,其宽度不上于斜道宽度。

4、斜道两侧及平台外围均应设置栏杆及踢脚杆,栏杆高度应为1.2m,踢脚杆高度仅为0.3m,内侧应挂密目网封闭。

5、脚手板横铺时,应在横向水平杆下增设纵向支托杆,纵向支托杆间距不应大于500mm。

6、脚手板上应每隔250~300mm设置一根防滑木条,木条厚度宜为20~30mm。

十、避雷装置

1、脚手架顶部高于2m,四角设置(长度大于35m,应中间设几根)避雷针。

2、用16mm2黄绿双色铜芯线作引下线,途中用磁瓶,导线绑扎。

3、接地装置的接地线应采用三根导体,在不同点与接地体作电气连接,垂直接地体应采用5×50角钢、Φ48钢管或Φ22圆钢,长度2.2m,不得采用螺纹钢,接地电阻不大于4Ω。

十一、脚手架搭设质量和安全要求

脚手架的搭设应将质量要求和安全要求有机地统一起来,确保搭设过程以及以后的使用和拆除过程的安全与适用。

(一)、搭设前的准备工作

1、搭设前,单位工程负责人应按脚手架搭拆方案的要求,对架子工进行安全技术交底,交义双方履行签字手续。

2、熟悉边坡图纸和施工现场看,掌握建筑平面和立面的构造特点,环境条件,按照<<建筑施工扣件式钢管脚手架安全技术规范>>(JGJ130-2001)中构造要求,决定脚手架步距等等,具体施搭设步骤。

3、材料准备。对进场的钢管、扣件、脚手架、安全网等进行检查验收。

4、搭设场地准备。根据脚手架搭设高度、搭设场地土质情况与现行国家标准<<地基与基础工程施工及验收规范>>(JBJ202)做好脚手架地基与基础的施工要求,坚实平整,不积水,砼硬化。经验收合格后,按方案的要求放线定位。

5、架子工应持有效的特种作业人员操作证上岗作业。必须戴好安全帽、佩安全带、必须穿鞋,严禁穿塑料底鞋,皮鞋等硬底易滑的鞋子登高作业。操作工具及小零件要放在工具袋内,扎紧衣袖口,领口以及裤腿口,以防钩挂发生危险。

(二)搭设过程中的质量和安全要求

1、扣件式双排钢管脚手架搭设一般顺序是:里立杆→外立杆→小横杆→大横杆→扫地杆→脚手片→防护栏杆和踢脚杆→连墙杆→安全网

2、脚手架必须配合施工进度搭设,一次搭设高度不应超过相邻连墙件以上二步,保证搭设过程中和稳定性。

3、脚手架搭设中累计误差超过允许偏差,难经纠正,每搭完一步脚手架后,按规定校步距、纵距、横距、立杆的垂直度。

4、竖立杆时应由两人配合操作。大、小横杆与立杆连接时,也必须两人配合。

5、当有六级及六级以上大风和雾、雨或雪雨、雪天气时,应停止脚手搭设作业。雨、雪后上架作业应注意防滑,并采取防滑措施。

6、非操作层脚手架上严禁堆放材料,且必须保持清洁,操作层脚手架上材料堆放不能集中,不能超高,堆放要稳固,每平方米的堆放不得超过300kg,工作完成后及时清除干净。

7、脚手架搭设后由施工企业组织分段验收(一般不超过3步架),办理验收手续。验收表中应写明验收的部位,内容量化,验收人员履行验收签字手续。验收不合格和,应在整改完毕后重新填写验收表。脚手架验收合格并挂合格牌后方可使用。

十二、拆除方案

1、外架拆除前应由单位工程负责人召集有关人员对架子工程进行全面检查与签证确认,建筑物施工完毕,且不需要使用时,脚手架方可拆除。

2、拆除脚手架应设置警戒,张挂醒目的警戒标志,禁止非操作人员通行和地面施工人员能行,并有专人负责警戒。

3、长立杆、斜杆的拆除应由二人配合进行,不宜单独作业,下班时应检查是否牢固,必要时应加设临时固定支撑,防止意外。

4、拆除外架前应将通道口上的存留材料杂物清除,按自上而下先装后拆,后装先拆的顺序。

5、拆除顺序为:安全网→踢脚杆→防护栏杆→剪刀撑→脚手片→搁栅杆→连墙杆→大横杆→小横杆→立杆,自上而下拆除,一步一清,不得采用踏步式拆除,不准上、下同时作业。

6、如遇强风、雨、雪等气候,不能进行外架拆除。

7、拆卸的钢管与扣件应分类堆放,严禁高空抛掷。

8、吊下的钢管与扣件运到地面时应及时按品种规格堆放整齐。

第五篇:脚手架搭设施工方案110

脚手架搭设施工方案

一、编制依据:

建筑施工安全施工标准JGJ59—99,建筑施工高处作业安全技术规范JGJ80—91,密目式安全网GB16909—1997,河北省建筑工程施工安全管理培训教材《高处作业脚手架》,》《建筑施工手册(第二版)》,工程设计图纸,《施工组织设计》。

二、工程概况:

阿尔卡迪亚帝景园3#楼为框架、剪力墙结构,陶粒砼空心砌块填充墙。地下一层,地上十一层带跃层,使用功能:住宅楼,建筑高度36.69米,由A区,B区,C区三个单体组成,占地面积1663.58平方米,总建筑面积21943.33平方米。

开工日期:2004年5月10日,竣工日期:2004年12月15日。

三、防护形式及施工方法:

防护形式的确定:根据现场施工平面布置、各单体结构特点,外围护采用三层一挑的单排脚手架,待结构主体施工完毕后,将架体拆除,利用吊篮做外墙外保温,脚手架首层沿主体周围搭设水平支撑网,外架用密目网全封闭。

材料准备:按物资计划表,将4m、6m长钢管、各种形式扣件、脚手板、密目网、水平支撑网准备好,按规定刷好油漆,横杆、立杆均刷黄色,剪力撑用钢管刷成蓝色,两端1m范围内均刷成黑色,使用前对各种材料进行质量检查。

预埋件的埋设:在浇筑的一、四、七、十层顶板前,将加工好的吊环绑扎于顶板内作为挑架支撑,按图示

小横杆与柱拉结,与立杆间距不大于30cm预埋φ14钢筋1500立杆间距1.2m挑杆间距1.5m,外挑1m

脚手架的搭设方法:搭设方法如图2所示,将4m长的钢管穿于楼板留设的吊环内,外挑 m,沿建筑物四周每1.2m一根挑杆布置6m立杆用十字扣件与挑杆连接再用横杆将立杆连接间距1.5m,形成一个整体,下设3m长拉杆将外架与建筑物连接,外挂密目网,下设水平支撑网,架体高于 m时,外侧用剪力墙加固,剪力墙搭接不小于1 m,搭接范围内扣件不少于3个。

变形缝处脚手架的搭设及防护:

在变形缝剪力墙处每层支设剪力墙摸板时预留φ80预留孔间距1000mm。,拆摸后用钢管穿过两预留孔,上面满铺5cm厚脚手板。同时搭设双排架至上层顶板处,满铺5cm厚脚手板,用以上层支设剪力墙摸板使用。在无剪力墙处,浇注顶板砼前满铺脚手板进行防护,浇注完拆除梁摸后,应重新铺板固定加以保护。

脚手板钢管双排架剪力墙剪力墙φ80@1000预留洞2m钢管400 1800变形缝处脚手架搭设与防护

四、脚手架构配件质量标准 ⒈钢管及扣件

钢管采用外径48㎜、壁厚3.5㎜焊接钢管,采用力学性能适中的Q235A钢,其力学性能应符合国家现行标准《碳素结构钢》GBT200中Q235A钢的规定,扣件应符合GB15831-1995《钢管脚手架扣件》的规定。

⒉底座

扣件或钢管脚手架的底座有标准底座和焊接底座两种,标准底座的材质要求同焊接底座的要求,采用Q235A钢,焊条应采用F43型,几何尺寸应符合图示要求分别如下:

最边缘作业点束筋物图1-1平网安装示意图

五、脚手架的用途及极限荷载值

砌筑脚手架,装修用脚手架及外围封闭脚手架搭设高度48米,脚手架外立杆内侧满挂密目网全封闭,脚手架的荷载:结构架3000N/㎡。

六、⒈搭设顺序

放置纵向扫地杆,自角部起依次向两边竖立底立杆,底端与纵向扫地杆扣接固定后,装设横向扫地杆并也与立杆固定(固定立杆底端前,应吊线确保立杆垂直)每边竖起3-4根立杆后,随即装设第一步纵向水平杆(与立杆扣接固定)各横向水平杆(小横杆靠近立杆并与纵向水平杆扣接固定)接正立杆垂直和水平杆水平使其符合要求后,按40~60NM力拧紧扣件螺栓,形成脚手架心起始段,按要求依次延伸搭设,直至第一步架交圈完成,交圈后再全面检查一遍脚手架质量和地基情况,严格确保设计要求和脚手架质量设置连墙杆(或加机械撑),按第一步架的作业程序和要求搭设第二步、第三步……随搭设进程及时装设连墙件(或加机力撑)装设作业层间横杆,(在脚手架横向杆之间架设的用缩小铺板支撑跨度的横杆)铺设脚手架板和装设作业层程杆挡脚板及密目网全封闭。

⒉一般基础做法

首先进行搭设场地平整、夯实工作,从建筑物主体向外围3-5%找坡,回填土夯实后上面铺设厚5㎝、20㎝以上宽木脚手板建筑物周围长装置之后在木脚手板上放置钢底座,钢底座上放置立杆,按设计的立杆间距进行放线定位,铺设木脚手板要平移,不得悬空。

⒊排水措施

在距脚手架外排立杆外侧0.5米外设置一排水沟在最低点设置积水坑,水流入坑内,用潜水泵将水排出,排水沟坡度为3-5%。

⒋构造要求

⑴立杆的间距、垂直度

立杆间距用1.5米,允许搭设偏差±5㎝,立杆垂直度允许搭设偏差±10㎝。

⑵扫地杆设置

从垫板往上20㎝处设置扫地杆,扫地杆采用对接接长,扫地杆在端头立杆交接处伸出扣件长度不小于10㎝。

⑶横杆间距、平整度

横杆间距采用1.8米,采用对接方法接长,横杆两端高差,不能超过2㎝,纵向水平杆全长平整度不能超过±10㎝。

⑷立杆、横杆接长的详细做法

立杆上的对接扣件应交错布置,两个相邻立杆的接头不应设在同步同跨内,两相邻立杆接头在高度方向错开的距离不应小于500㎜,各接头中心距立节点的距离不应大于步距的1/3。

纵向水平杆对接接头应交错布置,不应设在同步,同跨内相邻接头水平距离不应小于500㎝,并应避免设在纵向水平杆的跨在(见附图)

水平网横杆立杆图1-2 6宽水平网 ⒌架体与建筑的结构的拉结要求 ⑴构造形式

采用刚性连接方式,连墙件的连墙杆采用两根50㎝短管用直角扣件中间夹垫木因定于墙上,具体做法见附图。安全网钢丝绳斜杆横杆钢丝绳图1-3层间网支搭示意图 ⑵布置要求

连墙杆在垂直间距不应大于4米,水平间距不大于6米的位置上设置,设置时易靠近立节点,距离不应大于30㎝,必须从底部第一根纵向水平杆处开始设置,布设形式可以采用花排,也可采用并排,宜优先采用花排,门窗洞口采用短向拉结钢管长度过门窗洞口边缘250㎜以上。

七、剪刀撑的搭设方法

在建筑物四周转交外必须设置剪力撑,每道剪力撑跨立柱的根数宜在5-7根之间,每道剪力撑的宽度不应小于4跨,且不小于6米,斜杆与地面的倾角宜化45~60之间,由底部横向连续设置,中间每道剪力撑的净距不应大于15米。

剪刀撑斜杆应用旋转扣件固定在与之相交的横向水平杆的伸出端或立柱上,旋转扣件中心线距端点的距离不应大于15㎝,剪力撑接长采用搭接接长,搭接长度不小于100㎝,用3个扣件等距离布置,扣件扣在钢管端头处不小于10㎝,剪刀撑下端一定要落地。

八、小横杆的设置

每一端点处必须设置一根横向水平杆并采用直角扣件扣紧在纵向水平杆上部,端头处伸出长度不小于10㎝立杆轴线偏离立节点的距离不应大于150㎝,在双排架中,靠墙一侧的外伸长度不应大于50㎝。

九、脚手板的防护栏杆

脚手板一般应设置3根小横杆上,要铺满、铺密,在两侧设置180㎜以上高踢脚板,操作层上部护栏1.2米高,下部防护栏距踢脚板0.6米处。

十、脚手架体与建筑物之间封闭办法 ⒈密目网垂直封闭 ⑴密目网的质量要求

要四证齐全,要有阻燃性能,其续燃、阻燃时间均不得大于4秒,要符合GB16909的规定,每10㎝×10㎝=100㎝的面积上有2000个以上的网目。

0⑵密目网贯穿试验

做耐贯穿试验时将网与地面成30角拉平,在其中正上方3米处用5㎏重的钢管(管径48-51㎜)垂直自由落下,不穿透即为合格产品。

⑶密目网的绑扎方法

用缆绳将密目网绑扎至立杆或大横杆上,使网与架体牢固的连接在一时起,缆绳的材质应符合GB16909的规定。

⒉兜网封闭

用大眼安全网(平网)将脚手架与建筑物之间封闭起来,每隔10米一道。

十一、脚手架的上下通道

脚手架架体要设置安全通道:⑴马道宽度不小于1米,坡度比1:3(高:长)为宜;⑵马道的立杆间距应与脚手架相适应,基础按脚手架要求处理,立面设剪刀撑,人行横道小横杆间距不超过1.5米;⑶马道上满铺脚手板,板上钉防滑条;⑷设置护身栏杆,上部护身栏杆1.2米,下部护身栏杆距脚手板0.6米,同时设180㎜宽挡脚板。

十二、脚手架的卸料平台

卸料平台上面挂牌标明控制荷载,要有荷载计算书,要有专门搭设方案,要严格按照施工方案施工。

十三、脚手架交底与验收

脚手架必须严格按照施工方案搭设,要有严格的技术交底,要有节点构造详图,操作人员必须严格执行,所有偏差数值必须

0控制在允许范围内。

要由专门人员对已搭设好的脚手架按照搭设方案进行验收,验收时要有量的内容,如:横立杆间距的数值,立杆的垂直度,横杆的平整度等都应详细记载在验收记录当中,不能只用符合要求来代替。

十四、脚手架的拆除方法

制定拆除方案:方案应包括拆架的步骤和方法,安全措施等,拆除顺序应遵守由上至下,先搭后拆,后搭先拆的原则,即先拆栏杆,脚手架剪力撑、斜撑,而后小横杆、大横杆、立杆并按一步一清的原则依次进行,严禁上下同时进行拆除作业,同时周围设围栏或竖立警戒标志并且有专人指挥,以免发生事故。

十五、脚手架搭设时注意事项

⒈外径48㎜与51㎜的钢管严禁混合使用;

⒉立节点处,固定横向水平杆(或纵向水平杆)剪力撑,横向支撑等扣件的中必线距立节点的距离不应大于150㎜;

⒊各杆件端头伸出扣件端头边缘的长度不应小于100㎜; ⒋对接扣件的开口应朝向架子的内侧,螺栓应朝上,直角扣件的开口不得朝下,以确保安全。

⒌当脚手架外侧遇有低压电线时,而且外侧边缘距外电架空线路外侧边线的安全距离小于规范规定时,应做专门电防护方案,并严格执行;

⒍上架体作业人员必须持证上岗,戴安全帽、系好安全带; ⒎严格按搭设方案施工,连墙件和剪刀撑应及时设置,不得滞后超过两步;

⒏在搭设过程中,应注意调整脚手架的垂直度,最大允许偏差100㎜。

施工组织设计大全,全套5张光盘,由杭州嘉意德科技有限公司整理销售。嘉意德公司其他产品介绍如下:

工程竣工资料制作软件:首家基于word平台开发的资料软件,具有简单易用、功能强大、性能稳定等特点,涵盖了施工工程过程中技术文件、质量验收资料、质量保证资料、工程管理资料、监理资料和安全资料等各类文件、表格的编制和管理。适用于工程中各方主体的相关人员使用,如工程资料员、监理工程师以及工程文件整理、归档单位的工程竣工资料管理人员等。嘉意德资料软件表格样式齐全,操作简便!是全国版本最全的资料软件主流品牌,共有70多个各地方版本及行业版本,如公路资料、电力资料、节能资料、水利资料等。

施工安全验算软件:含脚手架、模板、用水用电、塔吊、基坑支护、钢筋支架、结构吊装、混凝土工程、降排水等九大模块。是现场安全管理必不可少的软件之一。软件将施工安全技术和计算机科学有机结合起来,符合施工现场特点和要求,依据有关国家规范和地方规程,根据常用的施工现场安全设施类型进行计算和分析,为施工企业安全技术管理提供了便捷的计算工具。同时生成规范化专项方案计算书,为施工组织设计的编制提供了可靠的依据。

标书制作与管理软件:是一个集标书制作与标书管理功能于一身的招投标软件,用于快速编制各类标书和施工组织设计。内置模板源自建设系统各大企业的实际工程,设计水平高、文字素质好。庞大的素材库包含工业、民用、水电、路桥的综合施工组织总设计,以及各类结构形式、各种高度的工业、民用、路桥、水电等单位工程的施工组织设计,还提供了特种工程、建筑、安装、乃至钢结构的施工组织设计,几乎囊括了编标所需的所有内容。

智能网络计划编制软件:该软件系统采用图形编辑方式,不需画草图,不需记住工作的代号,只需用鼠标就可以在网络图中进行添加、修改工作和调整逻辑关系,而不需再去输入紧前、紧后关系,并实时计算关键线路,自动添加工程标尺,横道图自动生成,非常快捷、方便。

施工平面图绘制软件:本软件提供了多种绘图工具,具备强大的绘图操作功能,并集成了多个图远库,包括建筑及构筑物库、材料及构件堆场库、施工机械库、交通运输库等等,可直接调用,您只需移动鼠标,就能够方便绘制出一张完整而又准确的施工平面图。

临时用电设计计算软件:是国内第一款对施工临时用电配置设计及计算类软件,软件严格按照国家规范进行编制。采用领先图形模式进行配电设计,及根据JGJ46-2005规范8.1.1条规定采用三相附和平衡计算法,使计算结果更加合理,软件还对配电箱、用电设备的开关、漏保、熔断器等电气的选择电流进行专门有正对的计算(考虑了尖峰电流等情况对电气设备的影响),使选择的电气设备更合理。本软件采用领先的.Net技术开发而成,具有易学、易用、高效等特点。任何购买过施工组织设计大全的用户购买以上我公司任一款软件均按8折优惠!

杭州嘉意德科技有限公司

电话:0571-88980586

*** 网址:http://www.xiexiebang.com

下载脚手架搭设施工方案word格式文档
下载脚手架搭设施工方案.doc
将本文档下载到自己电脑,方便修改和收藏,请勿使用迅雷等下载。
点此处下载文档

文档为doc格式


声明:本文内容由互联网用户自发贡献自行上传,本网站不拥有所有权,未作人工编辑处理,也不承担相关法律责任。如果您发现有涉嫌版权的内容,欢迎发送邮件至:645879355@qq.com 进行举报,并提供相关证据,工作人员会在5个工作日内联系你,一经查实,本站将立刻删除涉嫌侵权内容。

相关范文推荐

    外排脚手架搭设施工方案

    一、工程概况: 本工程为锅炉房抗震加固工程工程。 二、使用材料 1、本工程外排脚手架主要材料是采用外径48mm、壁厚3.5mm的扣件式钢管双排搭设,用于立杆、大横杆和斜杆的钢管......

    脚手架搭设施工方案[大全5篇]

    恒升府第11#楼脚手架搭设施工方案脚 手 架 搭 设 施 工 方 案一、 脚手架的作用及要求:因为架子的搭设质量对施工人员的人身安全、工程进度、工程质量有直接关系,如果架子搭设......

    悬挑脚手架搭设施工方案

    《建筑施工扣件式钢管脚手架安全技术规范》JGJ130―2001的5.1.7条备注中规定:扣件螺栓拧紧力矩值不应小于40Nm,且不应大于65Nm。 为了保证扣件内壁与钢管外壁之间具有足够摩......

    外防护脚手架搭设施工方案

    融侨半岛B3-B组团 外墙防护脚手架搭设施工方案 1. 编制依据: 1. 1《建筑施工安全检查标准》(JGJ59-99) 1. 2《建筑施工高空作业安全检查标准》(JGJ80-91) 1. 3渝建发[2000]3......

    门式脚手架施工搭设方案

    门式脚手架施工搭设方案来源:全球五金网 日期:2009-6-14 点击:112作者:宁波脚手架 公司产品 公司商机 公司招商 公司新闻脚手架规范,脚手架施工方案,门式脚手架规范,门式脚手架......

    满堂脚手架搭设施工方案(5篇范文)

    满堂脚手架搭设施工方案一、工程概况本工程是农业灌溉生产用房,根据现场实际情况,结合施工荷载和结构自重等各方面因素,使用满堂红钢管脚手架的部位比较多,综合考虑模板及其支架......

    门式脚手架施工搭设方案

    门式脚手架施工搭设方案一、搭设准备工作1. 编制脚手架工程施工组织设计,要求及计算内容同扣件式脚手架,见第4章4.7.1。2. 脚手架大赦前,工程技术负责人应按《建筑施工门式脚手......

    外脚手架搭设拆除施工方案

    脚手架搭设拆除施工方案工程名称:八家小区3#6#住宅楼 建设单位:赤峰市松山区五三镇八家村 监理单位:赤峰市华虹监理公司 施工单位:赤峰市添柱建筑公司 编 制 人: 审 核 人: 批 准......