关于房建工程的屋面渗漏原因及防治措施

【摘要】房建工程屋面的渗漏是最常见的建筑质量问题之一,特别是卷材屋面渗漏在当前施工过程中出现的问题也相当突出,在工程完工后不仅会造成房屋渗漏维修和翻修的费用惊人,而且还会对整体房屋的结构造成严重后果,这样不仅会影响人们对房屋的使用,严重时也会影响人们的生命财产安全。本文主要分析了房屋工程的屋面渗透原因,并就出现这类的原因提出一系列的防治措施。

【关键词】房建工程;屋面渗漏;原因;防治措施

【 abstract 】 roof leakage of the fittest engineering is the most common building quality problem, especially in the current coil roof leakage problems appeared in the course of construction is also outstanding, completed the project in not only can cause house leakage repair and overhaul cost of amazing, but also to the structure of the overall housing causing serious consequences, so will not only influence people to the use of the house, serious when also can affect people's lives and property security.This paper mainly analyzes the reasons of the housing projects roof penetration, and appear this kind of reason put forward a series of measures for the prevention and cure.【 key words 】 fittest engineering;Roof leakage;Reason;Prevention and control measures

中图分类号:K826.16文献标识码:A 文章编号:

随着我国经济建设不断发展,也使得建筑行业得到了迅猛发展,而屋面防水工程又是房屋建筑的一项重要工程,越来越引起人们的关注。由于房建工程的屋面不仅发挥着功能保障的作用,也直接关系到建筑物的使用寿命,从而直接关系到人们的生产生活环境和卫生条件,所以对屋面渗漏要认真对待。在处理屋面渗漏时,要根据房屋所处的自然条件等,严格按照屋面防水等级来进行设防。

1、房建工程常出现屋面渗漏的原因

施工中存在的隐患是造成房建工程常出现屋面渗漏的最主要因素,具体来讲,其又可以分为以下方面:

(1)在施工过程中,施工人员对施工所用的防水材料没有得到有效控制,施工工人在施工过程中操作不认真,如边缝封口作为卷材防水层的关键,如果封口不严密就会使水进入。同时,找平层的施工也不能得到施工人员的足够重视。

(2)常常在结构施工完成后装修阶段来进行防水层施工的,而与此同时经常是交叉作业,就常会使防水层遭到破坏。在这一阶段造成防水层破坏却不能及时发现,该现象是比较常见的。

(3)防水施工的最后一个关键环节就是防水层的保护工作。而往往在最后一个关键环节会在屋面上安装一系列的配套设备,从而使防水层遭到破坏。

(4)在防水施工过程中,保温层施工的技术对屋面渗漏影响很大,还会出现找平层与细部节点施工质量低劣等现象。

2、房建工程中屋面渗漏具体的防治措施

作者基于多年关于房建工程的实践经验,在此提出若干防治屋面渗漏的施工措施。

2.1 提高屋面的整体性

在平顶屋面中,现浇钢筋混凝土屋面板屋面防水性能普遍比装配式楼板屋画防水性能好,装配式钢筋混凝土空心板屋面又比加气混凝土屋而好,故楼房顶层层面的整体件和刚度对屋面防水性能的影响很大。因此,楼房屋面不应使用加气混凝土屋面板,最好采用现浇钢筋混凝上屋面板,加气混凝土保温层也应增强强度,最好采用焦渣保温层,刚度好,造价低

屋面渗漏主要在山墙、女儿墙、檐口、屋面板缝位置和烟囱、管道穿过屋面处产牛。产生的原因可能是结构变形、受温差效应影响产生裂缝、分格缝位置未与板缝对齐、分格缝油膏嵌填不实、油膏老化等。所以,提高屋面的整体性,屋面板的刚度要复核,以减少结构变形:屋面板灌缝时,缝底应托板,缝内湿润后用细石混凝土认真灌实;嵌缝材料及施工质量应符合规范;穿过屋面的构件应先于细石混凝土防水层施工;泛水高度应足够,泛水部位与大面积部位应一次施工,仔细操作;易漏水部位可增做防水涂膜、卷材粘贴等其他防水措施。

2.2 加强对屋面反梁过水孔的防治

屋面上的反梁都设有过水孔,一般情况下过水孔太小,施工困难,容易出现堵塞、积水、渗漏。在实际施工防治中,应根据结构层面考虑找坡层、成平层、防水层、保护层的厚度留设过水孔。过水孔的高度不应小于150nmm,宽度不应小于250mm;如果用预埋管时,其管径不应小于75mm。反梁过水孔防水不宜采用卷材防水,应采用防水涂料或密封材料防水,薄涂多遍,其厚度也不应小于2mm,预埋管道的两端周围与混凝土接触处应留20mm×20mm的凹槽,内嵌填密封材料,封闭严密。如采用卷材防水层,应在过水孔处增加一道卷材附加层,管口进水处剪开贴向管内。出水门外卷材剪齐贴入管口周围预留的槽口内,用密封材料嵌填密实,然后铺贴反梁和屋面防水层。

特别的,针对屋面反梁过水孔过高积水渗漏的维修,应将保护层、防水层、找坡层、保温层按顺坡要求剔凿、铲除平整,然后用聚合物水泥砂浆抹压找平层,其厚度不小于15mm,与原找平层措接密实;待达到养护要求并干燥厄,按规范要求铺设防水层,防水层收头处用密封材科封闭严密;防水层与原防水层搭接不小于150mm,搭接缝用密封材料封闭,其宽度不小于10mm,最后做防水层的保护层。对于屋面反梁过水孔过小积水渗漏的维修,需要先将立面上的保护层、防水层铲掉,对过水孔两侧及顶部的找平层、结构层进行剔凿,达到宽度和高度的要求;然后用聚合物水泥砂浆抹压找平层,达到养护和干燥要求后,按规范要求铺设防水层和找平层。

2.3 加强现浇钢筋、混凝土等施工原料控制

在施工过程中,必须对水灰比以及稠度进行严格的控制,在建筑施工过程中的找平层一般用C20的细石混凝土或1:2.5的水泥砂浆做成。对于基层的含水率应该不超过6%,倘若基层的含水量达不到规定的要求,就会对施工质量造成严重后果,破坏防水效果。关于找平层的裂缝,主要是由混凝土或砂浆内部空隙水分蒸发所引起的不规则裂缝,它主要分为横向裂缝以及位置、形状、大小各不相同的裂缝,对于平面间隙允许的最大值为5mm,并且在1m长度之内间隙不能多于1处;对于接口应做好处理,避免棱角、陡边现象的发生,接口边缘也要平缓地展开。为了避免发生水口堵塞不畅和排水倒流等现象,在对天沟雨水口进行安装时,一定要不高于表面20mm,并且要在它周边半径100mm的范围之内确保漏斗状放坡,这样才能确保水流加快。例如,采用坐浆挤压法贴实波瓦进行屋面施工,要求灰浆挤满瓦缝,以防波瓦空鼓;为使波瓦与混凝土板面结合牢固,施工时基层板面洒水湿润,波瓦要充分吸水待用,在板上先刷一道纯水泥结合层,再用1:2.5水泥砂浆铺贴波瓦,并按要求做纤泛水、屋面变坡等部位的瓦面搭接,以增强屋面整体的防渗能力。

2.4 加强卷材搭接缝的粘结

致使屋面渗漏的原因很多,特别容易出现的原因,如基层变形、结构变形、温差变形等易产生开裂的重要部位。为了保证防水层的质量,所实施的一个重要环节就是对卷材搭接缝的粘结。在施工之前一定要将接缝的结合面清洗干净,还要排净接缝间的空气,然后使用胶粘剂均匀涂刷。在粘合时,要确保辊压粘牢,接缝口密封严实,认真控制好涂刷与粘合之间的间隔时间,以确保防水层的整体防水功能。在使用卷材时,一定要对卷材的收头认真处理,收头应使用水泥钉钉压并要用密封材料封严。如果收头工作处理不好,就会造成卷材起边、张口等不良现象的发生,同时也要注意檐口、出入口、水落管是否漏水。

2.5 提高施工人员的素质

在屋面防水施工过程中,施工队伍的施工水平相当重要,因此必须选用技术过硬的施工队伍,严格禁止非防水专业的施工队伍来对房屋进行施工。在屋面防水施工过程中,必须按照国际以及相关部门的规定来进行具体的施工操作,并且要对工期进行科学合理的安排。要对工程屋面加强管理,做好防止防水层遭到损坏的工作,一旦防水层遭到不同程度的破坏,必须及时进行补正,从而避免防水层破坏越来越严重。

4、总结

综上所述,屋面防水需要综合考虑方方面面的因素,具体对策要从设计合理,选择材料合适,施工正确,维修及时。只有这样才能真正确保屋面防水工程质量达到要求,只有按照以上四种对策严格执行,才能保证屋面防水的工程质量,才能给使用者提供一个良好的生产或生活环境,而不仅仅只是一句空话。

【参考文献】

[1]陈国红.房建工程中常见渗漏及预防措施研究[J].现代商贸工业,2011.[2]陈建城.常见房屋工程渗漏质量通病预防浅析[J].成铁科技,2007.

[3]黄耀安.论述房建工程中渗漏主要问题及防治策略[J].城市建设理论研究,2011.[4]刘志忠.浅议房建工程施工阶段的质量控制[J].科学之友,2009.[5]胡开智,林峰.浅谈房建工程的屋面渗漏原因及防治[J].黑龙江交通科技,2009.

第二篇:浅析屋面渗漏原因及防治措施

浅析屋面渗漏质量问题及防治措施 章俊杰

【摘要】 屋面渗漏是民用建筑房屋使用过程中最突出的问题之一,渗漏不但影响建筑物的正常使用功能,危害建筑装饰效果,还侵蚀建筑物结构主体,缩短建筑物使用寿命,造成经济损失。本文通过对屋面渗透原因分析,从设计控制、材料选择、施工质量、维护管理等方面提出屋面渗漏防治措施。

【关键词】渗漏原因;施工质量;防治措施 一:

1、屋面渗漏的原因分析

由于建筑物地基生产不均匀沉降导致屋面板开裂;气候温差变化大混凝土胀缩产生屋面板裂缝;屋面上荷载过集中使板的扰度增大产生变形裂缝;屋面板与支承结构连接处受力不均使屋面板开裂;这些都将导致屋面板开裂发生屋面渗漏,还有防水材料质量是产生屋面渗漏最直接的原因之一,是保证屋面防水工程质量的关键,对材料的物理性能技术指标了解不透,有关选材方面对屋面渗漏等原因应引起管理单位的高度重视。

2、设计方面的原因

由于设计者防水意识淡薄或设计实践经验不足,没有根据建筑物的使用功能,结构特点及使用环境等不同技术性的材料或不同的施工方法;有的节点处理或泛水做法设计不合理也会造成渗漏,有的部位直接未设计防水层。目前我国的防水设计基本上都由建筑设计专业完成,多数建筑设计师只注重建筑物的功能布局,立面处理,室内装修上;对屋面防水不够重视;设计过于简单,使用范围及使用条件了解不透,不能根据建筑物的具体情况选用防水材料;有的在一道防水材料上进行二道热融防水,以致造成一道材料热烤融化,无法起到二道设防作用。结构设计师也未对屋面防水做足够的重视,未对屋面板做适当的提高配筋率、采用抗渗混凝土等技术措施。有些设计人员对一些重要的结构节点不出施工大样图,设计不全面、设计深度不够,造成施工困难。还有些设计人员不根据实际情况;在没有认真研究基础资料是否相符的情况下盲目照搬其他工程屋面防水做法。

3、施工质量原因

缺乏防水专业施工队伍,有的单位请不懂防水技术的工人去进行屋面防水施工操作。屋面排水坡度不能满足设计要求,未按施工规范要求设置分隔缝,涂膜防水油膏的厚度、均匀度不满足验收规范要求,露出屋面的管根、水落口、天沟、檐沟、泛水等未按施工规范及设计要求做处理,保护层不符合要求;屋面泛水等未按施工规范及设计要求做处理,保护层不符合要求,屋面泛水做法,细部做法达不到施工要求等,施工质量问题是导致屋面渗漏的主要原因。

4、材料方面的原因

防水材料质量控制包括原材料、成品、半成品、构配件等的质量控制。材料质量是屋面防水质量的基础,材料质量不符合要求,工程质量就等于不符合标准,加强材料质量控制是提高工程质量的重要保证,对材料质量重点控制其物理;力学性能及化学性能。在施工中必须对材料严格检查、验收并且正确使用,建立管理台账,做好收、发、储、运等各个环节监督,避免将不合格的原材料使用到防水工程上。进入现场的工程材料必须有产品合格证或质量保证书、性能检测报告并满足设计标准要求。

5、使用维护管理方面的原因

工程竣工交付使用后必须做好房屋工程的维护管理工作,对确保屋面防水使用年限很重要,由于屋面长年累月处于外界自然条件下,收到房屋结构变形及经常性冷热交替变化的影响,导致屋面防水层不可能保证长期完好无损,有的人还在防水层上凿眼打洞等,加速了屋面防水层的腐烂、老化,造成屋面逐渐出现渗漏。二:屋面渗漏的防治措施

确保屋面防水工程质量设计为前提,材料是基础,施工是关键。影响屋面渗漏因素诸如设计不合理性,结构质量、防水材料质量差、施工工艺及施工质量差,维护管理不到位等。把控好屋面防水设计关、选择质量好的防水材料、做好检测试验、制定科学合理的防水施工方案是提高屋面防水工程质量的有力措施。

施工单位在屋面防水工程施工前应通过图纸会审,掌握施工图中的细部构造及有关技术要求,并编制屋面防水施工方案技术措施。此外,防水工程必须由专业的防水施工队来施工,并进行书面施工技术交底,施工中严格按施工工序进行检查验收,合格后方可进行下一道工序施工。

1、屋面防水设计控制

设计人员必须掌握防水技术、材料性能及屋面防水设防要求,依据工程性质、重要程度、使用功能以及耐用年限设计屋面防水等级,同时根据工程特点,地区自然条件等按照屋面防水等级要求进行防水构造设计,防水重点部位设有施工详图。坚持以柔性为主,按防排结合、刚柔并济,多道防水、节点密封,加强保护的原则进行材料选择、结构设计,再按照规范和标准图集中细部构造进行防水细部节点设计。设计深度要符合要求,施工前要进行专项设计交底和施工图纸会审,对不明确、不合理,现场监理及施工技术人员要给与提出,设计者要予以变更处理解决。现场监理及施工技术人员要给与提出,设计者要预计变更处理解决。结构设计者对屋面板要适当提高配筋率并采用抗渗混凝土,提高屋面板混凝土的抗裂性,抗渗性能,在屋顶结构施工图中要明确防水构造做法。

2、材料选材控制措施

择优选用和合理使用时关键问题,根据防水等级和设防要求选材,根据设计师单一品种还是同种材料叠层使用;是采用刚柔材料结合或者是卷材与涂料复合使用;如何对变形缝等细部构造提出选材条件与要求等等,这些还需要考虑与地区气温、气候、环境等各种因素相结合。

3、提高屋面结构防水施工质量措施

选择防水材料要与建筑物等级及标准相适应,控制进入施工现场的防水材料质量,按规定进行抽样复试,有效防止不合格的防水材料用在屋面防水工程上。防水工程质量取决于设计质量、材料质量、工序质量、施工工艺水平、工人操作水平、成品保护水平、施工管理水平等要素。

屋面防水以防排为主,专门对屋面进行定期清扫、检查疏通天沟、檐口、排水口,将雨水及时排走。屋面找坡时无论是建筑找坡,还是结构找坡,都要按设计规范搞好屋面找坡,有效地控制屋面排水坡度和坡向是提高屋面防水质量的主要环节。找坡层浇筑时一定要用滚筒和尺方滚、压赶使其密实平顺。

要防治屋面渗漏控制好屋面板施工质量也是关键。屋面板混凝土强度高、抗渗性能好是防治屋面渗漏的根本保证。现浇钢筋混凝土屋面板的钢筋保护层厚度准确,加强混凝土振捣使之密实,不漏浆、无蜂窝、麻面、露筋等现象。浇捣混凝土连续进行,严禁出现浇捣中断、漏振现象。混凝土表面经滚筒碾压,提浆收水后用铁板压光,然后铺盖草席或塑料膜覆盖养护,养护时间不小于7天。

4、屋面找平层施工质量控制措施

控制好基层施工质量是搞好屋面防水的基础。施工前将基层清理干净,屋面不得有积水。如果找平层内部不密实、坡度不够、表面不平、砂浆拌和不均匀、施工质量低劣,会直接影响防水层施工质量。准确控制分仓缝的位置。采用水泥砂浆(宜掺10%的U型膨胀剂)或细石混凝土(抗裂纤维)的找平层分仓缝间距不得大于5M,并留置在易开裂处。分仓缝要事先预留,不得后割,缝宽宜为20mm~30mm,选择高质量的密封材料嵌缝。施工时要随时检查找平层的赶平压光质量、密封材料嵌缝质量,做到挤压密实,养护工作达到施工规范要求。

5、增加附加层施工质量控制措施

屋面防水层在某些部位上由于应力集中、变形频繁、雨水冲刷严重或外力损害,会较早地出现局部损坏,导致整个防水层耐用年限缩短。因此,在防水工程设计和施工中,对容易造成局部损坏的薄弱部位设置一至二层增附加层。找平层分仓缝处应设置空铺附加层。附加层的宽度要超过加强部位250mm,如为涂膜附加层必须带有胎体增强材料,应先施工附加层,后施工防水层。板端缝增强层应有较强的适应基层变形能力,可采用卷材增强层,采用加胎体的防水涂料作增强层,涂料可采用与大面积防水层相容的高分子涂料或集合无改性,沥青涂料。

6、涂膜隔离层施工质量控制

首先要对基层进行检查与清扫,若存在凹凸不平、起砂、起皮、裂缝、预埋件固定不牢等质量缺陷,应及时进行修补。另外,基层干净是防水涂料施工的首要条件,也是确保涂刷层与找平层之间粘结力的关键因素。根据屋面工程技术规范要求,在屋面与墙面链接处隔气层应从墙面向上连续涂刷,且高出保温层上表面不得小于150mm。隔气层厚度为3mm,为确保涂层厚度和提高涂层成品质量,因此在施工中应采取多次薄涂的施工工艺。另外,在施工前应通过试验确定没到涂料材料用量,并对原材料仔细搅拌确保涂刷均匀。与此同时,每道涂料在施工时必须等上一道涂料充分干燥后进行。在大面积涂刷前,先对阴阳角、雨水口、采光窗端壁等细部构造处进行附加增强处理,其宽度不应小于200mm,分隔缝处空铺一层聚酯无纺布附加层(一边固定),铺设宽度为200-300mm。收头处的胎体增强材料应裁剪整齐,如有凹槽应将其压入槽内,不得有翘边、皱折、透底等缺陷,最后用密封膏密封。涂膜隔气层严禁在雨天、雪天和五级风以上时施工,施工环境温度应不低于5℃。

7、保护层施工质量控制措施

对卷材防水层和涂膜防水层都要求在其上面设置保护层,常用的有反射膜、颗粒、块料、水泥砂浆、细石混凝土等多种保护层,各有其优缺点。一般情况下上人屋面采用水泥砂浆或细石混凝土做保护层,块料保护层和细石混凝土保护层的施工应设置分仓缝嵌填密封材料,分仓面积应符合规范和设计要求,平面变化处及墙根位置应设置分仓缝。对大量的有架空隔热的层面涂膜防水层,采用20mm厚的1:2.5水泥砂浆(掺微膨胀剂)一次抹平压光作保护层。水泥砂浆保护层应预设表面分隔缝并注打密封胶,其纵横间距均不得大于1.5m。

8、屋面转角处施工质量控制措施

铺涂柔性防水层的所有水平、竖向的阴角和阳角基层,均做半径为50mm ~ 80mm的圆角。在阴阳角处的基层涂胶后要用密封膏涂封距角每边100mm,再铺一层卷材附加层。

9、泛水收头处施工质量控制措施

将屋面的卷材继续铺至垂直墙面上形成卷材防水,泛水高度不小于250mm。在屋面与垂直女儿墙面的交接缝处,砂浆找平层应抹成圆弧形或45度斜面,上涂刷卷材胶粘剂,使卷材胶粘密实,避免卷材架空或折断,并加铺一层卷材。做好泛水上口的卷材收头固定,防止卷材在垂直墙面上下滑。在垂直墙面中预留通长的凹槽,将卷材收头压入槽内,用防水压条钉压后再用密封材料嵌填封严,外抹水泥砂浆保护。凹槽上部的墙体也应做防水处理。

10、加强使用维护管理措施

工程竣工交付使用时,施工单位要向建设单位管理人员针对维护管理使用说明进行交底,施工单位做到定期回访。使用单位应认真按照维护使用说明进行管理,不上人屋面决不可以堆放杂物、上人玩耍等。三:结语

屋面防渗漏是一项系统工程,要从设计防水层构造、材料质量,施工细部构造及基层处理等方面进行质量控制,应选择符合质量要求的防水材料,进行可靠、耐久、合理、经济的设计,精心策划、精心施工、建立维修、保养管理制度,只要有一个环节未达到设计及施工规范要求都有可能导致屋面发生渗漏。屋面防渗漏问题需要建各方共同努力,严格控制各阶段、各环节工作的质量,使屋面防水工程达到房屋使用功能及耐久性要求,杜绝屋面渗漏质量问题发生。

第三篇:刚性屋面渗漏原因及防治措施

浅析刚性屋面渗漏原因及防治措施

【摘要】刚性屋面渗漏是建筑工程中最常见的质量通病,也是一直难以解决的问题,屋面工程质量的好坏直接影响公司信誉、建筑物的寿命及业主的利益。作者结合设计和工程实践,从设计、材料、施工、使用等方面对从屋面渗漏的原因进行了分析,提出其渗漏的防治措施。

关键词

刚性屋面

渗漏 措施

一、屋面防水工程质量问题分析

(一)设计方面问题

许多设计单位未能根据建筑物的性能、重要程度、使用功能、结构特点及使用环境等不同而选用不同技术性能的材料或不同的施工方法,有的节点处理或泛水做法不合理,有的屋面防水设计方案不当等,普遍存在着脱离实际情况的理想化设计。所设计的结构层及防水层即使都能按照规定来施工,但在钢筋混凝土屋面上进行卷材防水层的施工过程中仍会出现因施工作业人员的技术水平不高,责任心不强而导致的女儿墙与天沟檐口之类的薄弱环节上出现接缝不严情况,进而造成屋面漏水。尤其是屋面的刚性防水,在其防水层施工完成之后,或因太阳照射、气候变化导致屋面热胀冷缩而产生裂缝,或因屋面板受力发生起翘变形、墙体受力发生坐浆收缩、地基发生不均匀沉降等产生裂缝。

(二)材料方面问题

材料控制包括原材料、成品、半成品、构配件等的质量控制。各类工程材料是工程施工的物资条件。材料质量是工程质量的基础,材料质量不符合要求,工程质量就不可能符合标准。所以加强材料的质量控制是提高工程质量的重要保证。在施工中必须对材料严格检查、验收并且正确使用,建立管理台账,做好收、发、储、运等各个环节的管理,避免将不合格的原材料使用到工程上。对材料质量,主要是控制其力学性能、化学性能、物理性能。进入现场的工程材料必须有产品合格证或质量保证书,性能检测报告,并能符合设计标准要求,凡需复试检测的建材必须复试合格才能使用。防水材料的材性材质也是影响防水效果的一个关键因素。工程所使用的一些防水材料没有达到国家规定的质量标准,还有的将假冒伪劣产品应用进来。例如:塑料防水油膏中减少或取消关键性的原料以降低成本;防水油膏质量低劣等造成的防水材料在抗冻融、高温、流淌性、抗老化等关键技术指标上达不到国家规范规定的要求,使其失去了防水功能, 最终导致屋面出现渗漏水。

(三)施工质量问题

排水坡度不足,未按规范要求设置分仓缝,涂膜防水厚度不足,出屋面的管根、水落口、天沟、檐沟、泛水等未做处理,保护层不符合要求,屋面泛水做法不规范,细部做法不符合要求等施工质量问题是导致屋面渗漏的主要原因。屋面防水施工没有严格按操作规程及设计要求来进行,还有局部地方所采用的防水措施不当。施工时对于女儿墙、山墙、天沟、檐口、屋面板缝或雨水管穿过防水层处,都没有采取严密的防范措施,最终导致屋面渗漏水。此外,砼是一种非均匀材质,并且在板内布有许多大小不同的微细空隙。可以将空隙分为两类:一个是施工空隙;另一个是构造空隙。分析其原因主要有:砼的振捣不密实,造成蜂窝麻面和肉眼难以观察到的空隙,这属于施工空隙;砼配比不当,导致砼在凝结硬化过程中产生的空隙,此类属于构造空隙,容易引起渗漏。

(四)使用中维护与管理问题

工程竣工交付使用后,必须做好房屋工程的管理维护工作,这对确保防水的使用年限很重要,由于屋面长年累月处于外界自然条件下受到房屋结构变形及经常性的冷热交替变化的影响,以致屋面防水层不可能保证长期完好无损。有的人甚至在防水层上凿眼打洞等,加速了防水层的腐烂、老化,因而屋面逐渐出现渗漏。在目前的建筑使用中,这方面的工作比较欠缺。建筑工程的屋面施工管理不到位。有的建筑工程完成主体以及屋面防水施工后,为了使建筑物更美观,还要在建筑工程的外墙进行装饰工程施工,在施工的过程中,需要安装吊篮或者搭设临时脚手架。但是,在安装这些临时施工设施时,总会因成品保护的管理不善而破坏屋面的防水层,屋面漏水在所难免。此外,在建筑工程竣工并交付使用之后,因部分业主在刚性屋面上安装卫星接收器、太阳能热水器等设备,并随意在屋面上埋置地脚螺栓,这样必然会破坏屋面的防水体系,导致屋面漏水。

二、屋面防水工程质量通病防治措施(一)应规范设计

设计人员必须掌握防水技术、材料性能及屋面防水的设防要求深化设计,依据工程性质、重要程度、使用功能以及耐用年限研究屋面防水等级,同时应根据工程特点、地区自然条件等按屋面防水等级要求进行设防。按防排结合、刚柔相济、多道防水、脱离分仓、节点密封、加强保护的设计原则进行用材选择、层次结构设计,再按照《规范》中导向性的细部构造示意进行防水细部节点大样图设计。设计深度要符合要求,施工前要进行专项设计交底和施工图纸会审,对不明确、不合理处,施工者应给予提出,设计者要予以解决。比如将分仓缝隙的做法改为温度伸缩缝的形式,并将此缝隙贯通于整个防水层,直至保温层上表面。为了防止出现漏水,在缝内嵌满塞实防水油膏,同时在缝隙的上部再加铺25cm 宽的二布三油压缝条。另外,在刚性防水层下方要涂满二度滑石粉,使刚性防水层可以克服约束力而实现自由伸缩。采用此种方式来处理,不仅能把规律而又不规则的裂缝控制在温度伸缩缝之中,还能减小刚性屋面因热胀变形而引起的温度应力,从而减轻了刚性屋面因温度而产生的裂缝和渗水现象。再比如可以改进烟囱、立管穿过防水屋面的作法。具体操作为:对阴角处泛水应分次做成光滑的圆弧形,避免形成台阶,使雨水停滞。改进板与板之间的灌缝砼。由于板与板之间的灌缝是新老砼交界处,强度不一,收缩应力不一,极易沿板缝开裂。砼将C20 细石砼改用C20 微膨胀砼,这样可以增强侧板之间的抗剪强度,并且能使相邻板之间更好地共同作用。(二)提高屋面结构防水施工质量

屋面采用建筑找坡与结构找坡相结合的做法。先按3%的结构找坡后,再在结构层上用1:6水泥炉渣或水泥膨胀砼石找坡,再做25mm厚1:2.5水泥砂浆找平层,建筑找坡时,一定要找准泛水坡度,流水方向,将最高点与泄水口之间用鱼线拉直、打点、打巴、泄水口处厚度不得低于30mm。浇砌时,一定要用滚筒和尺方滚、压赶、使其密实。屋面找坡时.无论是建筑找坡还是结构找坡,如果不按设计或者规范做好屋面找坡,就很难保证屋面防水问题,将导致卷材松软,加速卷材的老化和腐烂,微裂缝增加。因此做好屋面找坡工作,不但可以有效地控制屋面排水坡度和坡向,而且还是提高屋面防水质量的主要环节。现浇钢筋混凝土屋面须要求钢筋保护层正确,浇捣混凝土时派钢筋工跟班随时整理钢筋。混凝土要振捣密实,不得漏浆,无蜂窝、麻面、露筋等现象。混凝土浇捣必须连续进行,严禁出现冷缝。混凝土表面经滚筒滚压,提浆收水后用铁板油光,然后铺盖麻袋保护,养护时间不小于7天,养护初期不得上人。

(四)屋面找平层施工质量控制

找平层是在原结构面因存在高低不平或坡度而进行找平铺设的基层,如水泥砂浆、细石混凝土等,有利于在其上面铺设面层或防水、保温层。屋面施工时常易忽视找平层施工质量。如找平层内部不实、坡度不够、表面不平、砂浆拌和不均匀、施工质量低劣等是造成屋面渗漏的主要原因。所以要预防屋面漏水要先搞好基层质量,控制找平层的施工质量是搞好屋面防水的基础。

平面图中画出分仓缝的位置。水泥砂浆(宜掺10%的U型膨胀剂)或细石混凝土找平层分仓缝的间距不得大于6m,且应设置在易开裂处(如板端)。分仓缝应预留,不得后割,缝宽宜为20mm--30mm,选择中档以上密封材料嵌缝。施工时应注意找平层的赶平压光,加强养护,嵌缝密封材料应挤压密实。

(四)附加层

在结构板易裂处(如屋面大角及平面刚度变化处)应设置1层—2层附加层;在出屋面管根、水落口、天沟、檐沟、檐口、泛水、屋面转角等易渗部位应设置附加层;找平层分仓缝处应设置空铺附加层。附加层的宽度要超出加强部位250mm,如为涂膜附加层必须带有胎体增强材料,应先施工附加层,后施工防水层。

(五)铺贴防水层施工质量控制

(1)涂刷基层处理剂前要首先检查找平层的质量和干燥程度并加以清扫,符合要求后才可进行。在大面积喷涂前,用毛刷对屋面节点、周边、拐角等部位先行处理,胶粘剂涂刷应均匀、不露底、不堆积。

(2)屋面防水层应遵循的工艺程序为:基层表面清理、修补→喷、涂基层处理剂→节点附加增强处理→铺贴卷材→收头处理、节点密封→清理、检查、修整→保护层施工。(3)铺贴前的准备工作:卷材铺贴前必须清理基层,保证基层干燥、干净、平整,铺贴前应测试基层含水率,并做好记录。施工前要弹出控制线,严格控制相邻卷材边缝顺直以及搭接宽度一致。

(4)防水卷材粘贴采用满粘贴法。铺时,应从底到高铺贴,从檐口处向层脊处铺贴,从落水口处向两边“分水岭”处铺贴,卷材短边、长边搭接长度均为100mm,短边搭接应错开。

(5)屋面泛水立面高度最小不少于300mm,女儿墙采用凹泛水,凹槽为60X50mm,用水泥钉固定卷材,每幅卷材至少有两点固定,收头用防水油膏封闭。

(6)防水层施工时,先做好节点、附加层和屋面排水比较集中部位的处理,然后由屋面最低标高处向上施工。

(7)卷材铺贴时避免过分拉紧和皱折,基层与卷材间排气要充分,向横向两侧排气后方可用辊子压平粘实。不允许有翘边、脱层现象。

(8)卷材铺贴方法、搭接顺序符合规定,搭接宽度准确,接缝严密,不得有皱折、鼓泡和翘边,收头固定、密封严密。

(9)施工时须注意天气变化,雨天和雨天过后未到达施工要求时严禁施工。

(10)防水层完工后并经验收合格后,做好成品保护。(六)保护层

对卷材防水层和涂膜防水层均要求在其上面设置保护层,常用的有反射膜、粒料、块料、水泥砂浆、细石混凝土等数种保护层,各有其优缺点。一般情况下,上人砂浆或细石混凝土做保护层,块料保护层和细石混凝土保护层的施工应设置分仓缝,嵌填密封材料,分仓面积应符合《规范》和设计要求,平面变化处及墙根(包括突出物)应设置分仓缝。对大量的有架空隔热的住宅屋面涂膜防水层,采用20 mm厚的1:2.5水泥砂浆(掺微膨胀剂)一次抹平压光作保护层较为合适。水泥沙浆保护层应预设表面分格缝(不得后切割)并注打密封胶,其纵横间距均不得大于1.5m。

(七)屋面转角

铺涂柔性防水层(非沥青防水卷材)的所有水平、竖向的阴角和阳角的基层,均做半径为50mm--80mm的圆角。

(八)泛水收头

(1)将屋面的卷材继续铺至垂直墙面上,形成卷材防水,泛水高度不小于250mm。(2)在屋面与垂直女儿墙面的交接缝处,砂浆找平层应抹成圆弧形或45度斜面,上刷卷材胶粘剂,使卷材胶粘密实,避免卷材架空或折断,并加铺一层卷材。(3)做好泛水上口的卷材收头固定,防止卷材在垂直墙面上下滑。在垂直墙中预留通长的凹槽,将卷材收头压入凹槽内,用防水压条钉压后再用密封材料嵌填封严,外抹水泥砂浆保护。凹槽上部的墙体亦应做防水处理。

(九)维护管理

工程竣工、交付使用时,施工单位要向建设单位作出有关使用、保养、维护的说明,施工单位要定期回访。使用单位应认真按照“使用说明”进行使用,非上人屋面决不可堆放杂物、上人、饲养宠物,否则不仅仅造成使用功能的烦恼,还会造成经济损失。

三、结论

在实际工作中,引起屋面渗漏的原因很多,甚至可以说是多方面的,也是错综复杂的。因此,只有通过工业与民用建筑中防水部位出现渗漏的原因进行科学地分析,找到产生渗漏的主要因素,才能针对渗漏的原因,制定具体的修补方案。能做到有效的防治才能更好的服务于以后的建筑。

第四篇:屋面及外墙渗漏防治措施

住宅工程屋面及外墙渗漏防治措施(暂行)

鉴于进几年公司承建的住宅工程中屋面及外墙渗漏问题日益突出,造成业主投诉索赔,影响公司声誉,为提高建筑工程质量,满足设计使用功能,消除渗漏隐患,特制定此防治措施,此措施限于西安分公司住宅楼工程。

第一章:屋 面

应做到“先排后防”,即首先不能有积水,要将水在短时间内顺畅地排出。其次必须强化结构自防水功能,每一处节点均要对结构本身的防水功能给予充分的重视。

第一条:结构期间浇注顶层楼板混凝土应采用抗渗混凝土,其强度等级同设计强度。

第二条:采用地泵、汽车泵进行混凝土输送时,混凝土坍落度必须满足泵送要求,必须专人监测塌落度,同时严禁司机、作业人员对混凝土进行额外加水。第三条:顶层楼板混凝土浇注必须设置行人马道,同时应做到随收面随覆盖塑料薄膜,且严格控制上人上料时间。

第四条:出屋面烟风道应随顶板混凝土浇筑一次成型,振捣密实,不得二次砌筑或浇捣。

第五条:女儿墙若采用二次浇注时,其根部应设置遇水膨胀橡胶止水条,且根部第一排穿墙螺杆应采用止水螺杆。

第六条:保温层施工前,将楼板裂缝、管道根部、烟风道根部、吊洞等易渗漏部位宜采用聚氨酯防水涂料或JS防水涂料涂刷封闭,进行结构闭水试验或淋水试验并对渗漏处进行修补。

第七条:防水卷材施工前,必须对基层进行检验,基层应保证干燥、平整、无起砂、脱皮等现象,将1平米卷材干铺于基层表面,静止3h~4h掀起检查,找平层覆盖部位与卷材表面未见明显水印,视为合格。

第八条:屋面防水卷材性能指标必须符合设计要求,材料进场按相关规范规定取样复试,同时过程中加强检查材料质量,尤其是夜间施工作业时,值班人员要重点排查防水材料质量,避免出现偷换材料现象。第九条:屋面卷材施工其搭接部位必须采用滚压溢油方法施工,以保证其粘接强度,搭接长度不小于100mm,重点控制收边收口密封处理。

第十条:设施基座与结构层相连时,防水卷材应包裹至设施基座上部,并应在地脚螺栓周围做密封处理。

第十一条:女儿墙部位防水应满粘,防水收头应卷入凹槽内,用金属压条钉压固定,并应用密封材料封严。

第十二条:屋面雨落口、变形缝、出屋面管道、出屋面构筑物、出屋面排气管、女儿墙泛水等部位防水收头严格按设计图纸及相关图集要求施工,如设计无具体做法时,屋面女儿墙及构筑物优先考虑留设挑檐或凹槽。

第十三条:在确定屋面防水上返高度时,应综合考虑屋面找坡层和各层做法,任何部位防水上返高度均不应低于屋面面层向上250mm。对不能满足要求的部位可与设计协商确定做法,或采取相应的技术措施。

第十四条:屋面烟风道盖板与墙交接部位应进行防水密封处理,严禁盖板顶于保温墙面安装。

第十五条:出屋面管道,主管与套管之间填充宜采用浸透的油麻膏填充密实,填充高度宜为套管高度2/3,剩余1/3高度范围内采用混凝土掺防水剂填塞密实至套管上口5mm~10mm处,留设凹槽,凹槽内灌入聚氨酯防水密封膏。防水收口部位采用金属箍固定并涂刷密封膏。

第十六条:侧排雨水口直径宜选用不小于250mm铸铁侧排,以保证排水通畅,侧排应涂刷防腐剂。

第十七条:屋面出入口防水收头应压在混凝土踏步下,防水不得外露。第十八条:屋面防水施工完毕后应检验屋面有无渗漏和积水,排水系统是否通畅,按要求做蓄水或淋水试验,找坡层最高点蓄水不到位的地方宜采用淋水试验,蓄水试验不得少于24小时,淋水试验不得少于2小时。

第二章:外 墙

第一条:外墙窗洞口、空调板、阳台等砌筑部位均应浇注上返200mm混凝土返台,并应与结构一次性浇注完成,其强度等级不小于C20。

第二条:外门窗洞口等后砌填充墙外侧必须抹灰处理,抹灰砂浆应选用聚合物防水砂浆,且砌体与结构墙交接部位宜采用聚氨酯涂刷密封。第三条:外窗框下部填充宜采用聚合物水泥防水砂浆填实,抹成微斜坡状,两侧上返150mm,外侧涂刷聚氨酯防水涂料。

第四条:外窗外侧四周宜采用胶粉聚苯颗粒收口,外窗台应设置不小于5%坡度。第五条:集团公司强条规定,外门窗框(副框)安装应与结构洞口的间隙控制在15mm以内,其间隙用弹性闭孔材料填充饱满,外侧用密封胶密封。外门窗框(副框)与结构洞口的间隙大于15mm时,应按以下原则处理:

(1)外门窗框(副框)与结构洞口的间隙在15mm-50mm时,应先进行分层挂网抹灰收口至合适位置,再进行门窗框(副框)安装;

(2)当外门窗框(副框)与结构洞口的间隙大于50mm时,应先进行植筋、支模、浇筑细石混凝土至合适位置,再进行门窗框(副框)安装;

(3)结构洞口收口应综合考虑外门窗口侧面的保温厚度和装修面层做法。第六条:门窗框与洞口之间缝隙严禁填塞保温板。

第七条:结构预留空调管,在浇注混凝土前应检查空调孔洞位置是否准确,安装是否牢固,不得遗漏。当外墙面有保温时应用小一号套管将预留套管接长,并与保温墙面平齐,接管应胶接或采用牢固且不渗漏的连接方式。

第八条:当砌体结构需留置空调孔时,应采用预制混凝土块内预埋套管方法砌筑,并标明砌块内外面,以免用错。当外侧有保温时,预制混凝土块内套管应加长至保温面层平齐。

第九条:空调管道应做到内高外低,内外高差宜为10mm~20mm。

第十条:外墙螺栓孔应随爬架提升一次封堵到位,不得遗留,作为验收分项。第十一条:外墙穿墙螺栓孔封堵,两端应采用干硬性膨胀水泥防水砂浆,封堵深度不小于60mm,中间填充聚氨酯发泡剂,且外墙外侧螺栓孔表面涂刷聚氨酯防水涂料不少于两遍,总厚度1.5mm。

第十二条:混凝土结构墙面预留外脚手架、塔吊、施工电梯、悬挑工字钢等穿墙孔洞封堵措施:直径小于50mm孔洞,按第九条螺栓孔洞封堵措施处理,大于50mm孔洞采用混凝土掺(防水剂+膨胀剂)施工,并于外墙外侧涂刷聚氨酯防水涂料。

第十三条:屋面女儿墙、机房女儿墙、及屋面装饰墙等顶部外侧均应设置挑檐,挑檐宽度应遮盖保温板,以不影响保温面层施工且不出现朝天缝为宜。(剖面图 第十四条:顶层飘窗板、阳台板,以及与主楼交接通风井盖板,均应向外1%找坡,且应涂刷防水处理,防水上返至立面不小于250mm。

第五篇:房屋工程渗漏原因及防治措施

摘 要.................................................错误!未定义书签。第一章 房屋工程渗漏问题概述..........................错误!未定义书签。第二章 地下室渗漏种类及防治对策.......................................1 2.1 墙根与底板交界处漏水...........................................1 2.2 蜂窝、麻面、沟洞未处理或处理不彻底导致渗漏.....................2 2.3 钢筋保护层厚度不够造成渗漏.....................................2 2.4 支模钢筋造成底板渗漏水.........................................2 2.5 穿墙支模螺栓处理方法不当造成漏水...............................2 2.6 混凝土中有杂物造成渗漏.........................................3 2.7 沉降缝止水带偏位造成漏水.......................................3 第三章 屋面渗漏原因与防治............................错误!未定义书签。

3.1 钢筋砼现浇板、保温层上做刚性防水的屋面渗漏.....................4 3.1.1 现浇板渗漏原因及防治方法.................................4 3.1.2 刚性屋面开裂渗漏的原因及防治文法.........................4 3.1.3 雨水管口渗漏的原因及防治.................................4 3.2 拒水粉防水层的屋面渗漏.........................................5 3.3 钢筋砼斜层面、波形瓦对缝贴的屋面渗漏...........................5 3.4 卷材屋面的渗漏.................................................6 3.5平改坡铁皮屋面的渗漏...........................................7 第四章 墙体渗漏原因及防治............................错误!未定义书签。

4.1 外墙渗漏原因分析...............................................7 4.1.1 材料原因.................................................7 4.1.2 设计原因.................................................7 4.1.3 施工原因.................................................8 4.1.4 门窗洞口周围渗漏.........................................9 4.1.5 外墙装修引起的渗漏.......................................9 4.2 外墙渗漏的防治措施.............................................9 4.2.1 选用合格的砌筑材料.......................................9 4.2.2 灵活设计方案............................................10 4.2.3 把好墙体砌筑质量关......................................10 4.2.4 门窗应安装牢固,周边不留缝隙............................10 4.2.5 做好外墙装修前的基层处理................................11 第五章 楼板渗漏原因及防治............................错误!未定义书签。

5.1 厨房和卫生间地面渗漏产生的原因................................12 5.1.1 管道预留洞位置不符合规范................................12 5.1.2 管道堵洞不严密..........................................12 5.1.3 灌水试验不严格..........................................12 5.1.4 防水质量不达标..........................................12 5.1.5 管道与板间变形产生裂缝..................................13 5.2 厨房和生间地面渗漏的的预防措施................................13 5.2.1 卫生间楼板降低..........................................13 5.2.2 改进卫生间给水和排水管线安装布管方式....................13 5.2.3 提高堵洞质量............................................14 5.2.4 合理布置地漏位置且严格地漏标高..........................14 5.2.5 严把卫生间地面每道工序的施工质量........................15 5.2.6 立管集中于管道井........................................15 第六章 建筑防水工程施工质量控制......................错误!未定义书签。

6.1建筑防水工程施工质量控制概述...................................15 6.2关键过程分析...................................................16 6.2.1防水工程施工阶段质量职能与任务...........................16 6.2.2防水工程施工质量控制系统组织.............................17 6.2.3防水工程施工质量控制系统检验工作程序.....................18 6.2.4防水工程施工质量控制依据.................................20 6.2.5防水施工质量监控方法.....................................20 6.3关键过程控制技术...............................................21 6.3.1防水施工方案的及相关技术文件质量控制.....................21 6.3.2施工工序质量控制.........................................22 6.4本章小结.......................................................26 第七章 结论..........................................错误!未定义书签。参考文献..............................................错误!未定义书签。

造成渗漏的部位主要有地下室、屋面、墙体及楼板。其产生的主要原因有;设计方面的,比如屋面防水工程,有的不重视排水设计,对排水不畅的因素未充分考虑,致使屋面有的局部长期有水浸蚀,加速了防水材料的老化和霉烂,降低了防水的耐久性。再有未能按屋面防水等级确定防水标准,确定设防层数及每层构造厚度与要求、材料的种类与选择、细部节点的构造设计等;施工方面的,又如屋面防水工程,有的节点细部与找平层质量差,防水层厚度不够,保护层处理不当等;是用户任意进行室内改造,改变使用性能,如有的在无防水性能的楼面上设暗沟排水等。

第二章 地下室渗漏种类及防治对策

2.1 墙根与底板交界处漏水

将墙根与地面抹灰层剔掉15cm~30cm宽,发现二者交界处有漏水点,将该部分剔凿之后上部墙面渗水大大减轻,说明墙面渗水很大程度受墙根漏水的影响。分析其渗漏原因,是由于振捣下一步底板混凝土时,前一步已振捣完的底板和墙根20cm~30cm高混凝土受牵连振动,墙根混凝土在模板支护下没有下沉,而底板混凝土受振动下沉,则在墙根处拉裂。同时,该部位应力过于集中,养护不及时也造成干裂引起渗漏。因此,在振捣下步混凝土时,不要将振捣棒插到上步混凝土内及两步混凝土交界处,应大于振捣棒振幅距离,避免已振捣完的底板和墙根混凝土再受到振捣;浇筑20cm~30cm高墙根混凝土应比底板晚3h~5h,注意振捣棒不要插入已初凝的底板混凝土内。

2.2 蜂窝、麻面、沟洞未处理或处理不彻底导致渗漏

由于振捣混凝土不密实,出现蜂窝、麻面、沟洞、而处理时,未剔到混凝土密实处即抹砂浆,且砂浆又不密实,导致混凝土疏松产生渗漏。

2.3 钢筋保护层厚度不够造成渗漏

外部地下水通过底板外侧很薄的钢筋保护层进入底板钢筋周围,顺钢筋方向地下室内渗水,这种现象在底板堵漏进曾多次发现。因此建议设计地下室时,底板外侧、外墙外侧钢筋保护层应适当加厚,施工单位翻样、加工、绑扎钢筋时应取负差,避免钢筋由于胀模造成几乎无保护层。

2.4 支模钢筋造成底板渗漏水

为支设外墙板模板,在底板上埋设支模钢筋,施工后在底板上表面切割钢筋,由于钢筋没有保护层,形成化学腐蚀,造成严重渗水。如洛阳某工程地下室外墙板堵漏完成后,墙面、墙根均不漏水,后发现地面墙根约63cm处渗水,经剔凿发现是支模钢筋周围向上渗水。处理时,沿模钢筋周围将混凝土剔凿约4cm深,在此部位切割钢筋,再对钢筋坑进行堵漏后,地面不再漏水。

2.5 穿墙支模螺栓处理方法不当造成漏水

外墙穿墙螺栓止水板焊接不严密,或穿墙螺栓在外墙面切割时留头较长,外部抹砂浆时未能将钢筋头盖严,特别是钢筋头露在抹灰层之外,做防水时穿破防水层,在地下水作用下形成化学腐蚀,并不断向内墙方向腐蚀造成深情漏水。

2.6 混凝土中有杂物造成渗漏

混凝土中有木楔、木板,木方、聚苯板、砖头、编织袋等杂物时易造成渗漏,必须将靠近内墙面10cm范围内的杂物取走,也可以通过高压喷灯浇掉,清理干净后再堵漏。

2.7 沉降缝止水带偏位造成漏水

沉降缝漏水比较普遍,由于缝中橡胶止水胶带不易固定牢靠,浇筑混凝土时经常跑位,有的跑位严重,特别是顶板和底板止水带常落到下层钢筋上。水平止水带下方混凝土不易密实,常形成沟洞、蜂窝和麻面等。因此,施工中应焊接钢筋骨架将止水带固定在准确位置上,待水平止水带下方混凝土浇捣密实后,再固定止水带。

3.1 钢筋砼现浇板、保温层上做刚性防水的屋面渗漏

3.1.1 现浇板渗漏原因及防治方法

现浇板渗漏的原因有两点:现浇板内预埋接线盒上浮,使雨水直接从接线盒渗下;现浇板内穿线管上浮,造成板顶局部裂纹,雨水顺管壁外侧流向接线盒。防治方法:用铁钉或铁丝将板内穿线管及接线盒等物件固定在模板上,以保证现浇板内预埋物保持在现浇板的下部,使板内线盒、线管上有足够高度的砼层,并在接线盒上面配置钢筋网片,确保盒、管上面的砼不开裂。

3.1.2 刚性屋面开裂渗漏的原因及防治文法

产生原因:钢筋砼内网筋应保持在钢筋砼的上表面下1厘米处,由于施工人员的疏忽,使细石砼内钢筋网落在了砼的下部,致使刚性防水层的上部,成为素砼层,从而造成了刚性防水层的开裂渗漏现象。防治方法:浇砼时,应有专人负责将钢筋网片达到设计高度,再覆盖顶部砼,最后用平板振动器振实,压光养护。

3.1.3 雨水管口渗漏的原因及防治

产生原因主要有:由于屋面为内落水,管口盖应盖在刚性防水层上表面下0.5厘米处。为保证这个尺寸,却疏忽了管盖与管口间的结合关系,从而使雨水从管口直接渗漏进保温层,顺着板顶裂缝渗进室内造成屋面渗漏。防治方法:预埋雨水管时,应适应预埋高一些,然后根据刚性防水的充筋高度截去多余管头,使管盖与管口连为一体。这样既满足了管口的美观,又使雨水直接流入雨水管内,从而避免了从管口渗进屋面的现象。

3.2 拒水粉防水层的屋面渗漏

砂浆面层的裂缝宽度较大,走在上面,拒水粉就向外飘。处理方法:第一次将该屋面全部铺贴帮毡三油防水层,处理后经过雨水的检验,发现沿外墙及其附近顶棚渗水量依然很大,检查油毡层及收口处均无问题,设想问题出现在女儿墙上。经观察,发现女儿墙压顶的中间有一道粉刷施工缝,第二次将女儿墙粉刷缝切成2厘米宽的直缝,然后嵌入防水油膏。经过多次雨水检验,再未出现屋面渗水情况。预防措施有拒水粉是轻质干燥粉末,风吹雨打均可使它轻易流失。因而保护层必须由钢筋砼制作,方可长期阻止其外流。女儿墙与屋面直接相连,雨水将避开屋面防水层直接流向层顶结构层。造成屋顶甚至外墙渗漏,因而女儿墙必须砌筑密实,压顶应该采用钢筋砼制作,同时认真做好滴水线,以隔断雨水沿女儿墙向室内渗漏的途径。

3.3 钢筋砼斜层面、波形瓦对缝贴的屋面渗漏

现浇斜屋面由于其厚度小,不能在上表面安装模板施工,因而砼不可用插入振动器充分振实,只能用平板振动器由下而上慢慢拖动振实,容易出理局部不密实情况。当波形瓦对缝粘贴在砼表面后,瓦缝间的裂纹与瓦下的某些空鼓正好形成了砼屋面波形瓦下进水,不易蒸发,致使某些原本薄弱的砼屋面渗漏。处理方法:将渗漏处的砼从下面凿掉不密实处,然后用膨胀水泥砂浆分层补平压实,雨水后没有再次渗漏。预防措施:该屋面一旦渗漏,若想重新改变防水做法或进行维修,都会因工作量大而难以进行。预防这一现象的方法是,将对缝贴瓦的做法改成压缝贴瓦,或是在砼自防水结构上增设一道柔性防水层,然后再粘贴波形瓦。也有很多情况是高居屋顶的波形瓦,其建筑效果并不能被路上的行人所看见,因而选择水

泥吵浆面层涂刷彩色涂料,这是更加经济实用的做法。

3.4 卷材屋面的渗漏

屋面水落口处卷材破损漏雨,屋面大面积起鼓、出现裂纹,以及卷材搭接处开裂漏雨。女儿墙龟裂造成渗漏。原因分析及处理方法:水落口处卷材由于施工时采用小块卷材粘贴,当雨水量大时,排水受限于水落口的宽度,在水落口处积存的雨水对卷材的浸泡,时间长了造成卷材搭接处翻卷,造成漏雨。处理方法:将此处铺贴卷材面积加大,让卷材搭接处远离水落口,并在粘贴时对搭接处卷材做到充分热熔,粘贴密实。经雨天实践后,效果明显。屋面大面积起鼓、出现裂纹主要是由于施工时对基层处理不当,有灰尘杂物,在刷过底油后,铺贴卷材时未做到平整密实,造成部分卷材出现空鼓现象,经过冬季的冻涨,春季春融后,卷材空鼓出现裂纹,导致屋面漏雨。处理方法:将出现空鼓处的卷材按鼓起面积部分裁剪掉,并对基层进行清理,清理干净后,刷底油两遍,并裁剪大于缺损处的卷材重新进行铺贴,新卷材与原有卷材搭接要保证不小于10cm。经雨天实践后,达到了防漏目的,该处不再漏雨。屋面卷材搭接处漏雨主要原因,施工卷材搭接宽度不够,经过四季的热胀冷缩造成的漏雨以及搭接处施工粘贴不密实,卷材翻卷造成的漏雨。处理方法:将搭接宽度不够的搭接处在原卷材上进行不贴卷材,确保卷材搭接宽度符合要求。对翻卷的卷材搭接处,进行裁剪,并采用新卷材将缺损处进行补贴,保证粘贴密实,搭接宽度符合要求。女儿墙龟裂漏雨主要原因,女儿墙抹灰龟裂后,雨水顺裂缝进入墙体,造成屋面漏雨。处理方法:女儿墙采用沥青底油刷涂,雨后发现还有部分地方渗漏,这次采用卷材对女儿墙上表面进行粘贴,雨后发现不再渗漏,达到了防漏的目的。

3.5平改坡铁皮屋面的渗漏

渗漏现象:房屋冬季开棚内产生蒸汽,冷凝成冰,春季开化,造成漏雨。原因分析及处理方法:原因是原有下水排气孔及烟道在外节上屋面时采用PVC 管,部分施工单位,在棚内将多处气孔连接,汇到一起由烟道处接出屋面,冬季气温低,管内的气体冷凝成水,在平行管道中存留,结冰,管外侧也挂冰溜。当气温有所回升后化水,造成屋成漏雨。

处理方法:将每个气孔分别用PVC管接出屋面,并在屋面外用玻璃胶进行填塞粘接。

4.1 外墙渗漏原因分析

4.1.1 材料原因

当前填充材料多数是加气混凝土块、混凝土空心砖、灰砂砖和陶粒空空砌块,这些新型材料由于有较大的干缩变形,砌块的吸水率较大,砌块很容易吸收抹灰吵浆中的水分,影响吵浆硬化和强度的发展,使砂浆与墙面粘结力减小、结合不牢,而产生起鼓、开裂。墙体所用的砖或砌块抗拉、抗剪强度偏低砌块表面光滑,粘有脱模剂、粘土和浮灰等污物,使抹灰砂锅浆与砌块粘结困难另外,砌块块体较大,墙面灰缝少,减少了砌体灰缝对外墙的嵌固作用,增加了抹灰起亮的可能性,从而引起渗漏。

4.1.2 设计原因

屋面挑檐沟由于无保温层,受温度影响而发生变形。当前挑檐设计多为现浇,与檐沟圈梁相结合,整体刚度很大,变形时不能自由伸缩,与之

相连的平屋面即使设计采用保温层,但一般兼作找坡层,靠外墙处最薄,保温效果较差,仍易受温度影响而发生明显变形,因而与檐下墙连结处容易产生较在剪力,导致裂缝产生,引起渗水。窗户设计过大,窗间墙应力增大及集中,难以承受墙体荷载,导致窗台墙开裂渗水。由于窗台受力类似于反梁,当窗间墙荷载过大,砌体强度相对偏低时,在负弯矩作用下,大宽度窗户墙极易开裂。

4.1.3 施工原因

外墙抹灰。很多施工企业在房屋的主体工程施工时,没有采取有效的来保证结构的垂直度,导致施工主体结构的垂直底偏差较大。施工单位在外墙抹灰时用抹灰厚度去调整,使得抹灰层过厚。由于砂浆的干燥收缩,从而导致墙面开裂。同时框架结构建筑中外墙直译墙砌筑时于梁底接触面未予填密,亦是渗水原因。外墙饰面砖。现在大部分房屋的外墙装修都是采用条面砖或小方砖饰面,外墙饰面砖本身是防水材料,但是施工镶贴饰面砖时四边灰浆不饱满形成空洞,饰面砖之间的勾缝砂浆产生裂缝后,由于毛细管的作用产生水泵效应,雨水在风压作用下,易通过裂纹渗入到墙体内,再渗透到内墙表面。窗的安装。安装铝合金窗、钢窗时,窗框与墙体的连接处,没能用水泥吵浆和石棉填满。别外窗下框在安装前,很多施工单位没有按设计要求用油膏填塞下框凹槽防水处理。窗安装后,施工单位只是用一般的水泥砂浆作密封处理,有些窗台向外的排水坡度做得不够,比较平缓,甚至导致窗台外高内低,窗框与窗台的连接处的砂浆极易出现裂缝,形成渗水通道,窗口上部没按要求做好漏水线、断水槽。管道的施工安装。雨水管、自来水管等穿过墙体、楼板,有些施工单位没有按照设计要求预埋套管,安装时才后凿别另外,雨水管、自来水管等与预埋的套管之间的防水施工单位没有处理好,造成渗水。

4.1.4 门窗洞口周围渗漏

门窗本身材质较差,刚度不够而变形产生缝隙同,或所用柔生材料塞缝不实门窗框上口未封闭,门窗框周边未设置胀缩缝,抹灰后门窗框未嵌填密封胶门窗框边墙基不够坚固,连接件过长或过短造成门窗框开裂渗水另外,门窗扇碰撞振动使门窗框周围抹灰出现裂缝卢壳、脱落等,导致窗框塞缝与饰面开裂渗水。

4.1.5 外墙装修引起的渗漏

抹灰时,墙面不平整、凹凸过大,或砌块缺损、脚手洞未镶砌等原因,基层处理不好,墙面浇水不透或不匀,影响底层砂浆与基层的粘结性能。抹灰砂浆材料不合格、配合比不准、和易性不好引起渗水外墙壁抹灰层在温度效应下变形,抹灰层产生龟裂夏季施工吵浆失水过快,或抹灰后没有浇水养护,造成抹灰砂浆开裂。由于外墙饰面砖自重大,使底灰刮槽与基层之间产生较大的剪应力,粘结层与底子之间也产生较小的剪应力,加之施工操作不当,各层这间粘结强度很差,面层就产生空鼓。饰面层各层长期受大气温度的影响,由表面到基屋的温度梯度和热胀冷缩,在各层中也会产生应力,面砖如果粘贴砂浆不饱满,面砖勾缝不严,雨水渗透后受冻膨胀和应力共同作用,使面层受到破坏,从而引起裂缝。

4.2 外墙渗漏的防治措施

4.2.1 选用合格的砌筑材料

砌筑材料要选择信誉较好的生产厂家,所用材料要有出厂合格证。在施工使用前,对砌筑材料要进行抗拉、抗压强度试验,达到强度标准的方

可使用,并清除其表面留存的脱模剂、粘土、浮灰等污物。严禁使用有裂纹的砌体材料,砖或砌块在砌筑前一定要提前浇水湿润,从面增大与饰面吵浆的粘结力。

4.2.2 灵活设计方案

现浇挑檐沟、平屋面过长时适当设置伸缩缝檐口圈梁上增设女儿墙檐沟加贴防晒层,以降低太阳直接辐射吸收的热量平层面采用结构找坡,统一厚度并加厚保温层通过提高砌筑强度,纵墙丁型交接处增设构造柱,顶层窗洞以上檐下墙通长配筋等措施增强砌体刚度施工中,为防止檐下墙因砂浆龄期未到、强度不够,受温度效应影响开裂,现浇屋盖最好避开盛夏施工。

4.2.3 把好墙体砌筑质量关

施工中规范砌筑方法,要做到一铲灰一砖一揉压,确保砂浆饱满度达到规范要求,严禁用铺灰法砌筑,不得留有缝隙,形成渗水通道。梁下填充墙当砌到距梁底时,应做技术性间歇数天同,待灰缝干缩墙体沉实后再续砌顶部斜砖应保持度的角度,中部用楔形砖填实,以求吻合,斜角缝隙砂浆挤满挤实。对于框架结构与填充墙结合陪分,竖缝砂浆要饱满压实,按配置拉接筋,下料长度规范化,拉接筋开端必须有弯钩,插入拉接筋钩柱筋,施工中不得因拆模有难度而随意剪断钢筋,从而埋下裂缝隐患。

4.2.4 门窗应安装牢固,周边不留缝隙

选择铝合金或型钢原材料满足刚度、厚度要求,下料尺寸要准确,拼缝应嵌填硅酮胶封闭窗框安装时,门窗洞口四周窗必须牢固可靠,不能锚

固在空心砌块或加气混凝土砌块上,可专门预制同模数的混凝土块或者改用混凝土灰砂砖砌在墙内,门窗框锚件同时固定在此。塞缝前要对塞口松散砂浆,灰土油污清除干净,用发泡聚氨酸胶将所有缝隙压力灌实。饰面抹灰打底时先刷一遍聚合物水三泥浆,再刷一遍聚合物防水砂浆塞严缝隙,同时在窗边四周压出一道凹槽,待窗边砂浆干透后,清除表面浮浆灰尘,用耐候硅酮胶三沿窗边四周凹槽嵌填密实并压平,使窗框在有轻微扰动情况下不至于开裂渗水。

4.2.5 做好外墙装修前的基层处理

砌体施工完毕,清除基层表面的灰尘、浮浆、污垢,修补墙面深度较大的缝隙和脚手空洞等,并把穿过墙面的管线以及固定于墙面上的预埋密实,适当间隔一段时间,使其充分沉降稳定后再抹灰,以防砌体沉降拉断抹灰层渗水。抹灰时要按操作要求分层进行。为防止抹灰层因基层温度变化膨胀不同而产生裂缝,梁柱与墙体的结合部位加钉钢丝网片,增加拉接作用。对于表面光滑的混凝土墙面和加气混凝土墙面,抹底灰前应涂刷一道胶素水混浆结合层,以增加与光滑基层的粘结力,并可能通过高分割条,掺搞裂防水粉加以防范夏天还应注意适时对抹灰面逃匿水养护,避免空鼓裂缝、渗水。选购质外墙饰面砖,确保施工质量,杜绝渗漏现象。外墙装饰砖应采用优遁形墙面砖,不得有暗痕和裂纹面砖在使用前必须清洗干净,并进行隔夜浸泡,晾干后再用在粘贴饰面砖过程中,粘贴砂浆配合比要准确、和易性要好,一次成活,不易多动,应做到表面光滑,认真勾缝,灰浆饱满,砖缝平直,缝宽一致,勾成凹槽缝缝面平整、光滑、无砂眼饰面砖与粘结层不得有空鼓、翘曲裂缝等质量缺陷外墙的窗洞口、窗套、腰线、雨篷、挑檐等部位按规范要求做好滴水线槽,确保外墙无渗漏现象发生。

5.1 厨房和卫生间地面渗漏产生的原因

5.1.1 管道预留洞位置不符合规范

结构施工期间,由于施工人员不认真,检查不到位等原因,导致管道预留洞位置不准确甚至遗漏,在安装管道时大范围剔凿,破坏了楼板混凝土的整体性,从而产生渗漏。

5.1.2 管道堵洞不严密

排水管外壁表面光滑,如果管道安装完毕后,管道堵洞不能按照施工工艺的相关规范进行,就容易造成细石混凝土或砂浆与管壁结合不严密,使上、下层间顺管漏水/ 5.1.3 灌水试验不严格

排水管道安装完成后,要进行防水层施工,待防水层完全干透后,应进行24h 灌水试验,洪水高度应达到坡层最高点水位2.00以上。但在实际施工中,由于质检人员检查不仔细,不能及时发现问题,导致渗漏产生。

5.1.4 防水质量不达标

目前,厨房、卫生间的防水材料普遍采用聚投氨酯防水涂膜。找平层施工时容易忽略地面找坡,再加上阴阴角道听部位,尤其是阴角圆弧做得不好,管根部位圆弧做法不正确,找平层清扫不到位,找平层温度过大等,给后续的防水工作带来一定难度。另外,防水施工队偷工减料,施工人员操作不当,导致涂腊百度及高度不够瞧也是影响施工质量的原因之一。此

外,成品保护不到位,防水施工完成后,没有及时进行保护层的施工,导致其他工程施工时破坏了防水层,也是造成楼板渗漏的原因之一。

5.1.5 管道与板间变形产生裂缝

管道与楼板混凝土的肿胀系数等特性不同。建筑投入使用后,厨房=、卫生间的楼板要不断地随使用荷载,因此,会产生变形,而管道内介质温度长期处于不断的变化中,引起管道不断地热用冷缩,经过若干年后,管道与楼板间产生裂缝,造成厨房卫生间地面渗漏。

5.2 厨房和生间地面渗漏的的预防措施

5.2.1 卫生间楼板降低

住宅楼卫生间地面通常比室内地面低2.00~3.00cm,坐便器给水、排水管均穿卫生间楼板,考虑到维修方便,须给水管安装套管。在卫生间现浇板施工时,应采用基层防水措施,在卫生间墙板上做一道上返高60.00mm的混凝土止水带,要与现浇板同时施工,预留好各种管洞,避免以后在上凿洞口,留下渗水隐患;楼板混凝土施工时必须振捣密实,特别是管子四周及墙角处,必免不平,技术员要严把质量关,不合格处必须返工。

5.2.2 改进卫生间给水和排水管线安装布管方式

卫生间可采用下沉式、垫层式和管道墙3种给水和排水管线暗装的布管方式。不同的布管方式有不同类型的坐便器与之配套。下沉式布管方式是卫生间的结构局部下沉,在下沉的楼板面上做防水,按设计标高和坡度敷设给水、排水管道,并将混凝土预制板架空设置,找平后再做一层防水

和面层。为符合卫生间净高2.20m的规定,下沉空间控制在0.35~0.40m之间。结合工程实际情况,也可用焦砟轻质材料填实,代替架空混凝土板。垫层式布管方式是将给水、排水管道敷设在轻质材料的垫层中,垫层高度在0.15~0.20m之间,居室地坪与卫生间地坪有高差,选用性能好的多通道地漏。这两种作法保证了水平给水、排水管敷设在本户内,避免了检修时牵涉邻居的弊端。管道路墙式布管方式是在了、卫生间洁具方加设一堵墙,间隔0.20m左右,形成布置管道的专用空间,户内排水支管标高高于本户楼板,卫生间内给水和排水干管、水平管以及竖向管均敷设在夹墙内,这种作法适宜于卫生间面积较大的扇形,并须选用悬挂式洗面器和坐便器,结合工程实际情况,也可用柱式洗衣面器和后排水式坐便器代替。

5.2.3 提高堵洞质量

管道安装完毕后,堵洞应由土建派专人水暖式配合完成。一方面,保证了立管垂直度及管道的平面位置;另一方面,可以提高堵洞质量。堵洞时,要求洞底吊模紧贴楼板底,堵洞后的混凝土上口要略低于楼板一面,避免管道周围出现“混凝土鼓包”,选用与楼板同标号的混凝土做堵洞材料,内加适量的膨胀剂,堵洞时要求用钢筋棍将混凝土振捣密实。

5.2.4 合理布置地漏位置且严格地漏标高

地漏虽然仅是建筑产品中的一个小细胞,但它直接影响到相关工序的施工质量。为满足使用功能,地漏应尽量靠近浴盆及洗脸盆,并离墙面500.00mm以上,这样便于地面找坡及饰面砖施工,也便于将地漏作为清扫口使用。卫生间地面一般比居室低2.00cm,地面找坡2.00cm,所以,地漏的标高以比50.00cm控制线低55.00~60.00cm为宜。

5.2.5 严把卫生间地面每道工序的施工质量

在找平层施工时,基层要清扫干净并洒水湿润找平要以门口为水线分别向地漏找坡,坡度一般以1%为宜,并在阴阳角位置做好圆弧。如果采用聚氨酯防水涂膜,管根周围的找平层宜做成倒圆弧,这样在防水施工时,可以将涂料灌入倒圆弧中,增加了防水层的厚度,为水的通行设置了一道屏障。防水层施工时要加强过程控制,涂料遍数、厚度及高度都要达到设计要求及相关材料的使用说明,聚氨酯涂膜的厚度应在1.50mm以上。防水施工完成后应做1~2次蓄水试验,发现渗漏要查找原因及时修补,把问题消灭在萌芽状态。

5.2.6 立管集中于管道井

管道井是包容各种立管和计量表的空间,其位置应围绕管道和表具最多的厨房和卫生间设置,为使竖向于管靠近对应的设备,减少水平管道长度,心服及考虑查表不入户,户内可分设几个管道井。其平面布局可定位在厨房的内墙角,其断面尺寸应符合模数标准,与操作台或排气道的深度尺寸协调,也可设在与厨房相邻的隔墙处。卫生间内的管道井可定位于坐便器一侧的内墙角或相邻的隔墙处,断面尺寸符合模数标准,可与排气道统筹设计。

6.1建筑防水工程施工质量控制概述

防水工程施工质量控制可定义为:为达到防水工程施工质量要求所采取的作业技术和活动。其质量要求主要表现为防水工程合同、设计文件、规范规定的质量标准、作业手册等。因此,防水工程施工质量控制就是为

了保证达到防水工程合同规定的质量标准而采取的一系列措施、手段和方法。

防水工程施工阶段是根据防水设计图纸(或方案)的要求进行实施,形成防水过程实体的过程。其质量要求与前几个阶段的质量要求是不同的,如果说防水材料质量控制阶段是解决“能否做、做什么”的问题,设计阶段是解决“如何做”的问题,而施工阶段则要解决的是“做出来、做好”的问题。防水工程施工阶段是生产实践,是生产和操作的质量问题。质量控制工作量最大的阶段就是施工阶段。所有与建设活动有关的单位都要在此时参与质量形成的活动。所以施工阶段的质量控制是防水工程质量控制的重点,也是最重要的阶段,是保证整个防水工程能否达到预期质量目标的关键。

6.2关键过程分析

6.2.1防水工程施工阶段质量职能与任务

防水施工阶段的质量控制,是一个由投入物质量控制到施工过程质量控制到产出物质量控制的全过程、全系统的控制过程。由于工程施工也是一种物质生产活动,因此在全程系统控制过程中,应对影响工程项目实体质量的五大因素实施全面控制。五大因素是指:人(Man)、材料(Material)、机械(Machine)、方法(Method)、环境(Environment),简称4MIE质量因素。如图6-1所示。

图6-1 4MIE质量因素

将上述五大因素在施工阶段以时间为进程展开,即明确了防水工程施工阶段质量控制的三大任务,也就是说,施工阶段质量控制职能主要是:事前控制,在正式施工活动开始之前进行的质量控制;事中控制,在施工过程中进行的质量控制;事后控制,是指对施工过的产品进行质量控制。

防水施工阶段的质量控制,实质上是施工单位按防水工程合同和设计图纸规定的质量标准进行建设的过程。三者之间,事先控制是先导,事中控制是关键,事后控制是弥补。因此,应当建立完善的防水工程施工质量保证体系来履行自己的工作职责。

6.2.2防水工程施工质量控制系统组织

防水工程施工质量控制高度重视逻辑思维程序,工程技术只有通过科学的组织管理才能充分发挥其效能。组织是管理的一项重要职能。质量控制系统组织的功能是通过任务结构和权力关系的设计,来协调工程项目施工中各方面的共同努力。其组织模式大致有直线制、职能制、直线职能制、矩阵制等。一般防水工程项目常采用直线制或直线职能制的模式。

6.2.3防水工程施工质量控制系统检验工作程序

防水工程施工质量控制系统的组织模式,划分系统人员的工作职责,确定质量控制系统的检验工作程序,均属于制定预防措施的范畴。为了使质量控制系统能够有条不紊地运转,每当一个分部分项或单位工程完工后,防水工程承包商应请业主或监理工程师对分部分项或单位工程进行质量检验并进行阶段验收。承包商向业主或监理工程师提出质量检验申请,必须在24小时以内送给业主或监理工程师,业主或监理工程师必须及时转达有关信息,进行协调工作,避免影响承包商的工作进度及随之而来的索赔。质量控制系统的检验工作程序见图6-2所示。

图6-2 质量控制系统的检验工作程序

6.2.4防水工程施工质量控制依据

合同文件、防水设计文件(图纸、方案)、防水工程质量评定标准与方法,是防水工程施工阶段质量控制的共同依据。除此之外,在施工过程中,工序质量控制及原材料、半成品、构配件的质量控制还须以专门法规或规定作为控制依据:

①有关防水工程作业的操作规程。②有关工程防水施工规程及验收规范。

③凡采用新材料、新工艺、新技术的工程,均应事先进行试验,并提交权威技术检验部门关于其技术性能的鉴定书或相应级别的技术鉴定。

④有关试验、取样的技术标准。

⑤有关材料验收、包装、标志的国家标准。

6.2.5防水施工质量监控方法

在防水施工阶段实施动态跟踪控制,动用质量控制系统在工程项目施工过程中进行连续不断的评价、验证及纠偏,是防水施工项目现场质量监控的基本任务。其监控的具体内容、使用方法如图6-3所示。

图6-3 防水施工质量监控

6.3关键过程控制技术

6.3.1防水施工方案的及相关技术文件质量控制

(一)防水施工方案的控制

这里所指的防水施工方案的控制,包含防水工程项目整个施工过程内所采取的技术方案、工艺流程、组织措施、检测手段、施工组织设计等的控制。尤其是施工方案正确与否,是直接影响整个防水工程项目的进度控制、质量控制、投资控制三大目标能否顺利实现的关键。往往由于防水施工方案考虑不周而拖延进度,影响质量,增加投资。为此,在参与制定和审核施工方案时,必须结合工程实际,从技术、组织、管理、工艺、操作、经济等方面进行全面分析、综合考虑,力求方案技术可行、经济合理、工艺先进、措施得力、操作方便,有利于提高质量、加快进度、降低成本。防水施工方案选择的前提是一定要满足技术的可行性。

(二)防水工程相关技术文件的质量控制内容

1、审核有关技术资质证明文件;

2、审核开工报告,并经现场核实;

3、审核有关材料、半成品的质量检验报告;

4、审核反映工序质量动态的统计资料或控制图表;

5、审核设计变更、修改图纸和技术核定书;

6、审核有关质量问题的处理报告;

7、审核有关应用新工艺、新材料、新技术、新结构的技术鉴定书;

8、审核有关工序交接检查,分项、分部工程质量检查报告;

9、审核现场有关技术鉴证、文件等。

6.3.2施工工序质量控制

按照全面质量管理的思想,过程质量管理是质量形成的重要阶段,是对生产过程或服务过程进行的质量管理。而工序质量则是构成过程质量活动的基本单位,也是证实产品符合规定要求以及质量体系有效运行的重要证据。因此,要想经济合理的施工出正确体现顾客使用功能要求的优质防水工程和优质服务,关键在于对防水施工工序的管理,使防水工程质量形成的各有关过程始终处于受控状态。同时,为了把工程质量从事后检查把关,转向为事前控制,达到“以预防为主”的目的,也必须加强防水施工工序的质量控制。

(一)基本概念

1、工序

工序是指施工工序,它是产品(工程)构配件或零部件生产(施工)制造过程的基本环节,是构成生产的基本单位,也是质量检验和管理的基本环节。通常所说的一道工序,是指一个或一组作业工人在一个工作地对一个或者若干个劳动对象(工程、产品、构配件或零件等)进行物理和化学变化的过程。

如果劳动对象不变,而操作地变换时,就成为另外的工序,从现场管理角度看,从工序的组合和影响工序质量的多个因素看,工序就是人、机、料、法和环境对产品(工程)质量起综合作用的过程。

2、工序质量控制

工序质量控制是管理者把工序质量检验反馈来的关于防水工程产品性能特征的各方面质量数据进行分析,而后针对存在的差异问题采取必要的措施,以尽量消除这些差异,使质量达到要求,并保持稳定的调节管理过程。

(二)工序质量控制的目的和作用

1、目的

影响建筑防水工程产品质量的原因有两大方面,即偶然性因素和异常性因素。当防水施工工序仅在偶然性因素的作用下,其工程产品的性能特征数据(计量值数据)分布基本是算术平均值及标准差固定不变下的正态分布。工序处于这样的状态称为稳定状态。当工序既有偶然性因素又有异常性因素作用影响时,则算术平均值及标准差将发生不规律的变化,这时的工序状态称为异常状态,并采取必要的措施不断的消除,使工序处于管理状态,确保工程产品质量。

2、作用

①有效的控制防水施工生产过程,及时发现异常原因,便于采取有效措施,防止不合格项目发生,保证防水工程质量。

②有助于防水施工企业的各项管理工作的改进和提高。通过质量控制活动中的工序条件质量的分析和解决,促进企业与施工生产活动有关的业务部门和管理人员的协同工作,促使其改进本部门或本岗位的工作,提高工作质量,以保证工序条件质量的改善。

(三)工序质量控制内容

工序质量控制是防水施工技术质量职能的重要内容,也是现场质量控制的重点。工序质量控制的对象从直观来看是按工序控制的目的来控制工序形成的质量特征值(几何尺寸、粗糙度、公差等)的波动范围,即控制其分散程度同时还要控制特性值波动的中心位置。由于工序形成的质量特性值的波动范围和中心值,受众多因素的影响,因此,工序质量控制的对象是对工序因素的控制,特别是对主导因素的控制。实践证明控制住了主导因素,工序就能稳定,继而保证防水工程(产品)质量,所以防水工程施工工序质量控制的核心也就是管因素、管过程,并不单纯的是管结果。为此:

1、严格遵守防水工艺规程。防水施工工艺和操作规程是进行施工操作的依据和法规,是确保工序质量的前提,任何人都必须严格执行,不得违犯。

2、主动控制工序活动条件的质量。将活动条件的主要因素切实有效地控制进来,使它们处于被控制状态,确保工序投入品的质量,避免系统性因素变异发生,就能保证每道工序质量正常稳定。

3、及时检验工序活动效果的质量。工序活动效果是评价工序质量是否符合标准的尺度。必须加强质量检验工作,对质量状况进行综合统计与分析,及时掌握质量动态。自始至终使工序活动效果的质量满足规范和标准的要求。

4、设置工序质量控制点,控制点是指为了保证工序质量而需要进行控制的重点,或关键部位或薄弱环节,以便在一定时期内,一定条件下进行化管理,使工序处于良好的控制状态。

(四)工序质量控制原则程序步骤

工序质量控制实际上是通过对工程产品的一部分(子样)的统计性质来判断总体(母体)的性质,进而对工序实行控制。其控制的原则步骤为:

1、描绘工作,对通过有关途径和手段搜集来的质量数据资料进行整理

归纳,并利用有关图表及借助必要的统计特征数,把数据的主要特征表现出来。

2、分析工作,对经过整理、归纳或得到的有关数据进行分析,发现这些数据所遵循的规律,即分析其波动的倾向、趋势及其影响这种波动的原因。

3、推断工作,根据子样对母体所遵循的规律进行推测性的判断,并据此预测母体将来可能出现的情况。这是最有意义的一项工作。但在做推断工作时,必须注意子样与其所代表的母体基本条件不应有所改变。

4、处理工作,根据对工序是否处于稳定状态的判断及原因分析,决定采取响应的对策办法,来限制异常性原因的影响。

(五)质量控制点的设置原则

施工过程质量控制点设置的原则,是根据工程的重要程度,即质量特性值对整个工程质量的影响程度来确定。设置施工过程质量控制点,是对工程质量进行预控的有力措施。

(六)工序质量的检验

工序质量检验工作的内容主要有下列几项:

1、标准具体化;

2、度量;

3、比较;

4、判定;

5、处理;

6、记录。

(七)工序质量控制预控

防水工程施工工序质量的预控,是事先对要进行防水施工的项目分析在施工中可能或最容易出现的质量问题,从而提出相应的对策,采取质量

预控的措施予以预防。通过对工程实施质量预控的方法,可以达到提高操作人员技术水平,有目的有预见的采取有效措施,把施工中常见的质量通病和质量事故消灭在萌芽状态中。做到心中有标准,施工有准则,施工后能达到预定目标。

6.4本章小结

本章首先对建筑防水工程质量控制的关键环节——施工阶段的质量控制作了系统概述,然后对施工阶段质量控制的关键过程如:防水工程质量职能与任务、质量控制的系统组织、质量控制系统的检验工作程序、质量控制的依据、质量监控的方法等作了分析,重点对防水施工阶段质量控制的关键因素:施工方案、工序及质量成本的控制从全面质量管理的角度作了研究,目的在于找到防水工程施工阶段质量合适的控制方法,保证防水工程从设计图纸到工程实体的可控实现。

下载关于房建工程的屋面渗漏原因及防治措施word格式文档
下载关于房建工程的屋面渗漏原因及防治措施.doc
将本文档下载到自己电脑,方便修改和收藏,请勿使用迅雷等下载。
点此处下载文档

文档为doc格式


声明:本文内容由互联网用户自发贡献自行上传,本网站不拥有所有权,未作人工编辑处理,也不承担相关法律责任。如果您发现有涉嫌版权的内容,欢迎发送邮件至:645879355@qq.com 进行举报,并提供相关证据,工作人员会在5个工作日内联系你,一经查实,本站将立刻删除涉嫌侵权内容。

相关范文推荐

    卷材屋面渗漏的原因及防治措施(精)

    卷材屋面渗漏的原因及防治措施 1、屋面结构层 1.1屋面找坡无论是建筑找坡,还是结构找坡,若不按设计规范搞好屋面找坡,屋面防水问题就难以保证,屋面上就会长期积水,导致卷材松软,空......

    装修工程防水渗漏原因及防治措施

    装修工程防水渗漏原因及防治措施 1、 屋面防水渗漏及防治 在屋面施工中主要存在以下几方面问题: (1) 在基层与突出屋面的连接处,及基层的转角和管道根部,未按施工要求做卷材附......

    地下室渗漏原因及防治措施

    1、地下室底板渗水 1.1、后浇带的节点做法:后浇带中垃圾、积水处理不到位,会导致混凝土夹渣,强度降低等影响后浇带混凝土质量,增加渗漏风险,可以从后浇带的节点设计上来预防此类......

    地下室渗漏原因及防治措施

    地下室渗漏原因分析及预防措施 Cause analysis and prevention measures in the basement leakage 叶春欣 (杭州欣盛房地产开发有限公司, 浙江 杭州 310014) 摘要:地下室渗漏的......

    屋面渗漏原因与防治[精选]

    屋面渗漏原因与防治 论文 由于屋面造型、建筑做法的多样化,屋面渗水的原因也多种多样。本文针对不同情况的屋面渗漏分别予以论述。 一、钢筋砼现浇板、保温层上做刚性防水的......

    屋面渗漏原因

    渗漏原因 一. 产生原因 1.屋面板安装质量差,安装前不找平、不座浆,造成空心板因搁置点不实,减弱了铰支作用,增大了砼刚性防水层出现裂缝的机率; 2.灌缝工艺控制不严,嵌缝不饱满,......

    屋面渗漏质量常见问题防治措施

    附件2 屋面渗漏质量常见问题防治措施 1设计 1.1屋面防水工程的设计应符合现行国家标准《屋面工程技术规范》(GB50345-2012)的规定。屋面防水工程应根据建筑物的类别、重要程......

    屋面渗漏质量通病防治措施

    屋面渗漏质量通病防治措施 1设计 1.1屋面防水工程的设计应符合现行国家标准《屋面工程技术规范》(GB50345-2012)的规定。屋面防水工程应根据建筑物的类别、重要程度、使用功能......