钻孔灌注桩施工专项安全方案(大全5篇)

时间:2019-05-13 04:35:50下载本文作者:会员上传
简介:写写帮文库小编为你整理了多篇相关的《钻孔灌注桩施工专项安全方案》,但愿对你工作学习有帮助,当然你在写写帮文库还可以找到更多《钻孔灌注桩施工专项安全方案》。

第一篇:钻孔灌注桩施工专项安全方案

中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

目 录

一、编制依据················································································································································ 1

二、适用范围················································································································································ 1

三、编制原则················································································································································ 1

四、安全目标················································································································································ 1

五、工程概况················································································································································ 1

六、工程地质情况 ········································································································································ 3

七、钻机选择、施工 ···································································································································· 4

八、灌注桩施工安全操作规程 ····················································································································· 4

九、钻机操作、钻孔安全、文明措施 ········································································································· 4

十、施工安全保证措施 ································································································································ 7

中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

钻孔灌注桩专项安全施工方案

一、编制依据

⑴《中华人民共和国安全法》

⑵《铁路桥涵工程施工安全技术规程》(TB10303-2009)⑶ 陕西宝鸡至甘肃兰州第10合同段施工图设计。⑷《铁路路基施工安全技术规程》(TB1032-2009)⑸《高速铁路设计规范》(TB10621-2009)

⑹《高速铁路桥涵工程施工质量验收标准》(TB10752-2010)⑺《高铁工程施工安全技术规程》(TB10303-2009)

二、适用范围

陕西宝鸡至甘肃兰州第10合同段项目经理部一工区彭家咀中桥、王家岔大桥、郑家川大桥、蛟龙大桥、华尖川特大桥的全部桩基工程。

三、编制原则

1、安全第一的原则

在安全方案编制中始终按照技术可靠、措施得力、施工顺序合理、确保安全的原则确定施工方案。

2、坚持规范、规程原则

贯彻执行铁路路基施工技术规程、铁路工程安全施工技术规程。执行业主针对本工程建设制定的各项安全管理办法、细则和规程。施工时按照设计方案进行施工。

四、安全目标

1、杜绝死亡。

2、不发生高处坠物伤人事故。

3、不发生施工人员高处坠落

4、杜绝因施工造成的道路中段、管道、通信、电力管线损坏等施工责任事故。

五、工程概况 中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

根据设计图纸,桥梁结构形式及桥位处工程地质情况如下:

彭家咀中桥,桥梁全长84.70m,本桥上部采用3-24m简支箱梁,下部结构桥台为钻孔灌注桩基础、双线矩形空心桥台、圆端形实体桥墩、盖梁。地质该处土层主要为第四系全新统冲击风砂粘质黄土、粘质黄土、细圆砾土、第四系上更新统风积砂质黄土,基底为上第三系泥岩。

王家岔大桥,桥梁全长128.10m,本桥上部采用1-32m+2-24m+1-32m的简支箱梁,下部结构采用钻孔灌注桩基础、双线矩形空心桥台、圆端形实体桥墩、盖梁。地质该处土层主要为第四系上更新统风积砂质黄土、冲积的砂质黄土及粘质黄土,沟底出露为上第三系泥岩。

郑家川大桥,桥梁全长144.10m,本桥上部采用4-32m简支箱梁,下部结构采用钻孔灌注桩基础、双线矩形空心桥台、圆端形实体桥墩、盖梁。地质该处土层主要为第四系全新统冲击砂质黄土、粘质黄土、细圆砾土、第四系上更新统风积砂质黄土及上第三系泥岩。

蛟龙大桥,桥梁全长144.10m,本桥上部采用4-32m箱梁,下部结构采用钻孔灌注桩基础、双线矩形空心桥台、圆端形实体桥墩、盖梁。地质该处土层为第四系上更新统冲积砂质黄土、粘质黄土,沟底出露为上第三系泥岩。

华尖川特大桥,桥梁全长4578.92m。本桥上部采用51孔32m+1孔24m+73孔32m+3孔24m+6孔32m+1孔24m+1孔32m+1孔24m+4孔32m简支箱梁。下部结构采用钻孔灌注桩基础,双线矩形空心桥台,圆端形空心桥墩、盖梁。地质该处地层主要为第四系全新统冲积砂质黄土、粘质黄土、粉土、中砂、砾砂、细圆砾土,基地为上为第三系泥岩。

桩基全部采用钻孔灌注桩施工。中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

六、工程地质情况

1、地形、地貌

彭家咀中桥位于定西市安定区彭家咀,DK910+280C处有一冲沟,土质沟床沟型较顺直,沟内植被良好,季节性流水。

王家岔大桥位于定西市安定区宁远镇,地貌上属黄土梁沟壑区,地形起伏较大,地面高程1980-2030m最大相对高差为50m。

郑家川大桥位于定西市安定区彭家咀,地貌上属于牛谷河南岸黄土梁沟壑区,地势平坦。

蛟龙大桥位于定西市安定区宁远镇蛟龙村附近,地貌上属于黄土梁沟壑区。

华尖川特大桥位于东河河谷阶地区,地形平缓,地面高程1951-1972m最大相对高差约为20m。岸坡坡度不大,岸坡稳定。

2、气象、水文

根据设计图纸提供的水文气象资料可知,项目区属于典型的中温带大陆性气候,总的气候特点是:冬季漫长而寒冷,项目夏季炎热而短促,春秋气温变化剧烈。全年降雨少而集中,多集中在7、8两个月,降雨年际变化大,最低年份仅为143.5mm,最高年份为635.5mm,年平均417.5mm,蒸发量年平均为2093mm。每年一月最冷,平均最低气温-19℃,极端最低温度为-34.5℃;极端最高气温为37.5℃,无霜期约118-152天,初霜日平均为9月30日,终日为5月7日。最大风速24.5m/s,最大积雪厚度12cm,年平均相对湿度55﹪。

3、工程地质

主要以山前冲洪积平原为主,河流冲积平原为辅,岩土类型较为稳定,工程地质条件较好。

区内地下水较丰富,主要为第四系松散层空隙潜水和基岩裂隙水,地下水位在丘陵顶部埋藏较深,而河谷附近则埋藏较浅。平均流量1.1亿立中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

方米,最大流量2840立方米∕秒。

七、钻机选择、施工

本工程钻孔选用YTR220型钻孔机6台,按拟定的施工顺序分段开始施工,主桥按单独工期体系进行安排施工。钻机安装就位严格按照《建筑机械使用安全技术规程》(JGJ33-2001)操作规程施工,钻机安装就位后用水平尺使底座保持水平,钻杆上下垂直。

八、灌注桩施工安全操作规程

1、电器设备要设置漏电开关,并保证接地有效可靠。

2、登高检修与保养的操作人员,必须穿软底鞋,并将鞋底淤泥清除干净。

3、作业区要严加安全管理,任何人不准进入,主钢丝绳要经常检查,三股中发现断丝数大于 10丝时,应立即更换。

4、使用钻杆作业时,要经常检查限位结构,严防脱落伤人或落入孔洞中;检查时避免用手指伸入探摸,严防轧伤。

5、钻杆与钻头的连接要勤检查,防止松动脱落伤人。

6、采用泥浆护壁时,对泥浆循环系统要认真管理,及时清扫场地上的浆液,做好现场防滑工作。

7、钻孔后,混凝土浇灌顶标高比地面低时,应在孔口加盖板封挡,以免人或工具掉落孔中。

8、吊置钢筋笼时,要合理选择捆绑吊点,并应拉好尾绳,保证平稳起吊,准确入孔,严防伤人。

九、钻机操作、钻孔安全、文明措施

1、安装钻孔机前,应掌握勘探资料,并确认地质条件符合该钻机的要求,中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

地下无埋设物,作业范围内无障碍物,施工现场与架空输电线路的安全距离符合规定。

2、安装钻孔机时,钻机钻架基础应夯实、平整。钻架下应铺设枕木。

3、钻机的安装和钻头的组装应按说明书规定进行,竖立或放倒钻架时,应有熟练的专业人员进行。

4、钻架的吊重中心、钻机的卡孔和护进管中心应在同一垂直线上,钻杆中心允许偏差为20㎜。

5、钻头和钻杆连接螺纹应良好,滑扣时不得使用。钻头焊接应牢固,不得有裂纹。钻杆连接处应加便于拆卸的垫圈。

6、施工区域设置警戒线,有专人负责看护。

7、作业前重点检查项目应符合下列要求:

1)各部件安装紧固,转动部位和传动带有防护罩,钢丝绳完好,离合器、制动带功能良好。

2)润滑油符合规定,各管路接头密封良好,无漏油、漏气、漏水现象。

3)电气设备齐全、电路配置完好。

4)钻机作业范围内无障碍物。

8、作业前,应将各部操纵手柄先置于空档位置,确认一切正常后,方可作业。

9、开机时,应先送浆后开钻;停机时,应先停钻后停浆。泥浆泵应有专人看管,对泥浆质量和浆面高度应随时测量和调整,保证泥浆浓度合适。停钻时,出现漏浆应及时补充。并应随时清除沉淀池中杂物,保持泥浆纯净和循环不中断,防止塌孔和埋钻。中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

10、开钻时,钻压应轻,钻速应慢。在钻进过程中,应根据地质情况和钻进深度,选择合适的钻压和钻速,均匀给进。

11、变速箱换档时,应先停机,挂上档后再开机。

12、加接钻杆时,应使用特制的连接螺栓均匀紧固,保证连接处的密封性,并做好连接处的清洁工作。

13、钻进中,应随时观察钻机的运转情况,当发生异响、吊索具破损、漏气、漏渣,以及其它不正常情况时,应立即停机检查,排除故障后,方可继续开钻。

14、提钻、下钻时,应轻提轻放。钻机下和井孔周围2米以内及高压胶管下,不得站人。严禁钻杆在旋转时提升。

15、发生提钻受阻时,应先设法使钻具活动后再慢慢提升,不得强行提升。如钻进受阻时,应采用缓冲击法解除,并查明原因,采取措施后,方可钻进。

16、钻架、钻台平车、封口平车等的承载部位不得超载。

17、使用空气反循环时,其喷浆口应遮拦,并应固定管端。

18、钻进进尺达到要求时,应根据钻杆长度换算孔底标高,确认无误后,再把钻头略为提起,降低转速,空转5—20min后再停钻。

19、钻机的移位和拆卸,应按照说明书规定进行,在转移和拆运过程中,应防止碰撞机架。

20、作业后,应对钻机进行清洗和润滑,并应将主要部位遮盖妥当。

21、严格按照文明卫生施工要求,提高职工素质,确保工程完成。作业时,禁止直接或间接向河道排放泥浆,禁止泥浆外泄污染环境,泥浆池周边中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

设置醒目安全警示标牌,并用安全网围护,防止小孩入内观望。

22、未及时灌注的桩孔及护筒需用安全平网严实遮盖,防止路人误撞入,每台钻机上设置醒目安全警示标牌,时刻警示操作人员及他人。

十、施工安全保证措施

(一)、施工中的安全措施

1、施工人员必须戴安全帽,穿绝缘胶鞋,孔周边作业人、监护人员,必须戴安全帽,严禁穿拖鞋、赤脚、酒后上岗作业。

2、施工现场电源线路,必须按“三级配电”“二级漏电分级”分段保护。

3、各孔井用电必须分闸,严禁一闸多孔和一闸多用。必须一机一闸一漏一箱进行敷设。

4、孔上电线、电缆必须架空。

5、电箱一律采用铁质电箱,电箱应有严密的防雨措施,安装位置合适,安装牢固,进出线整齐,拉线牢固,熔丝不得用金属代替,箱内不得放其它物品。

6、现场电源线路及电气设备,由持证电工负责安装维护,经验收合格后,方准投入使用。

7、施工现场所有设备和机具必须做好保护接零。

8、所有机械设备的传动部位,必须装设防护罩。

9、垂直起重设备必须经常性检修维护,保证机件能够运转正常,操作灵活,按钮开关、减速器、钢丝绳、绳卡、吊钩、吊桶、吊笼等,不得带病作业。中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

10、垂直起重设备支架应牢固,应能承受一定的冲击力不至翻倒,垂直起重设备必须经检验合格后,方可投入使用。

(二)、施工现场安全防护措施

1、夜间施工时,要有足够的照明,施工危险区域,白天悬挂明显标志,夜间悬挂标志灯。

2、事故易发部位,如本工程高空作业处,起吊区,用电机械等安排专职的安全员进行指挥与监督;

3、现场施工特种作业人员要佩带专门的防护用品,如电焊工要佩带护目镜和面罩,高空作业系好安全带。

4、所有现场施工人员严禁酒后上岗。

5、现场施工道路的交叉处或拐弯处设立安全警告标志。

6、变压器周围设高度不低于1.7米的安全护栏,四周挂上“小心!高压危险”的警告牌。

7、定期进行安全生产检查工作,对检查出的不安全因素和隐患应立即整改,整改不力的悬挂警告黄牌,直至整改完毕。

8、工地入口处设安全告示板,宣传施工安全信息,安全检查记录,整改情况。

9、办公室加强与气象部门联系,重点收集高温、洪水等方面的资料,一旦发现有危及工程安全及人员安全的灾害气象预兆时,立即上报项目领导,及时采取措施。

(三)、突发事件发生时的处理应急方案

1、应急救援处置预案机构 中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

1)工区应急救援处置预案指挥机构为安全生产领导小组。在应急抢险队人员、通讯、交通车辆、物资器材、工具、资金等方面实施抢险救援中起绝对保证作用,满足抢险救援。其应急抢险救援领导小组成员如下: 组 长:李传州

副 组 长:孙尔林 赵春寿 王京龙 高先峰 张兆奎 汪叶滨 组 员: 王亮 张宏 刘永胜 李双平王志明

2、几种意外事故的应急救援程序

1)雪灾灾害事故。班组、作业队要立即报告项目部,项目部再视灾害程度组织应急队抢救的决定。作业队要立即组织人员抢险,保护员工,减少财产损失。

2)发生地震灾害事故,基层作业队要立即组织员工疏散,同时立即报告项目部,项目部下令调派应急队赶赴现场进行救援抢险。

3)发生消防火灾事故。一旦发生火灾险情,早发现早扑灭采取果断措施扑灭火灾和防止火势蔓延,疏散人员,抢救财产,并立即报告项目部,项目部再视情况报告消防部门和当地政府、林业部门呼救“119”支援抢险。

4)发生爆炸事故。一旦发生爆炸事故,项目部安全生产领导小组立即组织抢险队员抢险,并拨打“110”报警电话,请求地方公安部门支援。

5)发生雷电灾害事故。一旦遇暴风骤雨天气有雷电情况发生,工人要立即暂停施工,回棚(房)躲避,并远离大树下、铁吊架下等,撑伞不能紧握金属支撑杆。当雷雨现象比较严重时,要立即切断动力电源,并且关掉一切用电器。尽量少使用手机等无线射频设备。

6)停水、停电事故。起用储备用水,根据停水时间合理供应水;起用发电中国水电路桥工程有限公司宝兰客专甘肃段项目经理部一工区 桩基工程安全专项施工方案

机,保证重要设备、施工供电;将外部供电线路总闸断开,接到供电通知后再使用外部供电。

7)有毒有害气体油料泄露事故。接到泄露报告后,项目部安全生产领导小组立即组织人员抢修,抢修人员必须佩戴防毒面具,收集或稀释泄露物质。

8)中毒、急性传染病事故。项目部安全生产领导小组立即组织专业人员进行抢救,安排车辆将病员以尽快速度送往医院,或者拨打“120”请求支援。

9)设备大修、故障事故。主管部门立即联系租用或起用备用设备,组织人员抢修设备。

3、施工常见事故的应急救援程序

1)发生轻伤事故后,首先抢救伤员,事故现场有关人员要立即报告,采取措施防止事故的扩大。轻伤事故由班组、作业队组织有关人员调查处理,作业队登记,报项目部存查。项目部、作业队按《安全生产管理办法》有关规定处罚

2)发生重伤、死亡事故,事故现场有关人员要立即报作业队和项目部,同时立即抢救伤员保护现场。作业队和项目部在收到事故报告后,立即组织工会、技术、安全部门等组成事故调查组,立即赶赴现场调查了解,分析事故原因,在24小时内报当地劳动安全监督管理局和检察院,由当地县(市)一级政府调查处理批复结案,然后项目部再按《安全生产管理办法》有关规定进行处罚处分。

3)发生交通事故,首先当事者立即抢救伤员、保护现场,立即报告当地公安交警部门赶赴现场调查处理,同时立即报告作业队和项目部

第二篇:钻孔灌注桩施工专项安全方案

钻孔灌注桩专项安全施工方案

一、编制依据

中华人民共和国安全法

公路工程施工安全技术规程JTJ076-95 准格尔至兴和运煤高速公路大路至永兴段第A9合同段两阶段施工图设计。

准格尔至兴和运煤高速公路大路至永兴段第A9合同段招标文件项目专用本

公路路基施工技术规范 JTG F10-2006 公路桥涵施工技术规范 JTG/T F50-2011 公路工程质量检验评定标准 JTG F80/1-2004 公路工程施工安全技术规范 JTJ 076-95 内蒙古兴托重载高速公路有限公司、总监办、驻地办有关质量、进度、安全、文明施工、环保的规定和要求。

内蒙古有关安全、文明施工、环保、水土保持、文物保护的法规、规定和要求。

现场调查资料。

二、编制范围

准格尔至兴和运煤高速公路大路至永兴段第A9合同段新店子大桥全部桩基工程。

三、编制原则

1、安全第一的原则

在安全方案编制中始终按照技术可靠、措施得力、施工顺序合理、确保安全的原则确定施工方案。

2、坚持规范、规程原则

贯彻执行公路路基施工技术规程、公路工程安全施工技术规程。执行业主针对本工程建设制定的各项安全管理办法、细则和规程。施工时按照设计方

案进行施工。

四、安全目标

1、杜绝死亡。

2、不发生高处坠物伤人事故。

3、不发生施工人员高处坠落

4、杜绝因施工造成的道路中段、管道、通信、电力管线损坏等施工责任事故。

五、工程概况

根据设计图纸,桥梁结构形式及桥位处工程地质情况如下:

K72+245大桥,桥梁全长390m,本桥上部采用13-30m装配式预应力混凝土连续T梁,左幅宽0.5m+净-11.5m+0.75m,右幅宽0.5m+净-13.25m+0.75m,全桥共设4×30m+5×30m+4×30m三联,下部结构桥台为钻孔灌注桩基础、承台、墩柱、盖梁。在4号桥墩、9号桥墩处设置160型伸缩缝,地质该处土层结构以亚砂土为主,从上到下可分为5层。

桩基全部采用钻孔灌注桩施工。

六、工程地质情况

1、地形、地貌

本段公路所经地区位于和林县新店子镇境内,地貌类型以低中山丘陵为主,岗峦起伏,丘陵广布,海拔高度在1000~1600m之间,相对高差22m。主要为土质丘陵沟梁区、浑河北岸低丘区、剥蚀低山丘陵区。

2、气象、水文

根据设计图纸提供的水文气象资料可知,项目区属于典型的中温带大陆性气候,总的气候特点是:冬季漫长而寒冷,项目夏季炎热而短促,春秋气温变化剧烈。全年降雨少而集中,多集中在7、8两个月,降雨年际变化大,最低年份仅为143.5mm,最高年份为635.5mm,年平均417.5mm,蒸发量年平均为2093mm。每年一月最冷,平均最低气温-19℃,极端最低温度为-34.5℃;极端最高气温为37.5℃,无霜期约118-152天,初霜日平均为9月30日,终日为5月7日。最大风速24.5m/s,最大积雪厚度12cm,年平均相对湿度55﹪。

区内地下水较丰富,主要为第四系松散层空隙潜水和基岩裂隙水,地下水位在丘陵顶部埋藏较深,而河谷附近则埋藏较浅。浑河发源于山西右玉县的骆驼山,经杀虎口流入和林县,横穿和林县后流入清水河县,和林县境内长度75公里,平均流量1.1亿立方米,最大流量2840立方米/秒。

3、工程地质

主要以山前冲洪积平原为主,河流冲积平原为辅,岩土类型较为稳定,工程地质条件较好。

区内地下水较丰富,主要为第四系松散层空隙潜水和基岩裂隙水,地下水位在丘陵顶部埋藏较深,而河谷附近则埋藏较浅。浑河发源于山西右玉县的骆驼山,经杀虎口流入和林县,横穿和林县后流入清水河县,和林县境内长度75公里,平均流量1.1亿立方米,最大流量2840立方米∕秒。

七、钻机选择、施工

本工程钻孔选用GPS-

15、20型钻孔机各5台,按拟定的施工顺序分段开始施工,主桥按单独工期体系进行安排施工。钻机安装就位严格按照《建筑机械使用安全技术规程》(JGJ33-2001)操作规程施工,钻机安装就位后用水平尺使底座保持水平,钻杆上下垂直。

五、灌注桩施工安全操作规程

1、电器设备要设置漏电开关,并保证接地有效可靠。

2、登高检修与保养的操作人员,必须穿软底鞋,并将鞋底淤泥清除干净。

3、作业区要严加安全管理,任何人不准进入,主钢丝绳要经常检查,三股中发现断丝数大于 10丝时,应立即更换。

4、使用钻杆作业时,要经常检查限位结构,严防脱落伤人或落入孔洞中;检查时避免用手指伸入探摸,严防轧伤。

5、钻杆与钻头的连接要勤检查,防止松动脱落伤人。

6、采用泥浆护壁时,对泥浆循环系统要认真管理,及时清扫场地上的浆液,做好现场防滑工作。

7、钻孔后,混凝土浇灌顶标高比地面低时,应在孔口加盖板封挡,以免人或工具掉落孔中。

8、吊置钢筋笼时,要合理选择捆绑吊点,并应拉好尾绳,保证平稳起吊,准确入孔,严防伤人。

六、钻机操作、钻孔安全、文明措施

1、安装钻孔机前,应掌握勘探资料,并确认地质条件符合该钻机的要求,地下无埋设物,作业范围内无障碍物,施工现场与架空输电线路的安全距离符合规定。

2、安装钻孔机时,钻机钻架基础应夯实、平整。钻架下应铺设枕木。

3、钻机的安装和钻头的组装应按说明书规定进行,竖立或放倒钻架时,应有熟练的专业人员进行。

4、钻架的吊重中心、钻机的卡孔和护进管中心应在同一垂直线上,钻杆中心允许偏差为20㎜。

5、钻头和钻杆连接螺纹应良好,滑扣时不得使用。钻头焊接应牢固,不得有裂纹。钻杆连接处应加便于拆卸的垫圈。

6、施工区域设置警戒线,有专人负责看护。

7、作业前重点检查项目应符合下列要求:

1)各部件安装紧固,转动部位和传动带有防护罩,钢丝绳完好,离合器、制动带功能良好。

2)润滑油符合规定,各管路接头密封良好,无漏油、漏气、漏水现象。

3)电气设备齐全、电路配置完好。

4)钻机作业范围内无障碍物。

8、作业前,应将各部操纵手柄先置于空档位置,确认一切正常后,方可作业。

9、开机时,应先送浆后开钻;停机时,应先停钻后停浆。泥浆泵应有专人看管,对泥浆质量和浆面高度应随时测量和调整,保证泥浆浓度合适。停钻时,出现漏浆应及时补充。并应随时清除沉淀池中杂物,保持泥浆纯净和循环不中断,防止塌孔和埋钻。

10、开钻时,钻压应轻,钻速应慢。在钻进过程中,应根据地质情况和钻进深度,选择合适的钻压和钻速,均匀给进。

11、变速箱换档时,应先停机,挂上档后再开机。

12、加接钻杆时,应使用特制的连接螺栓均匀紧固,保证连接处的密封性,并做好连接处的清洁工作。

13、钻进中,应随时观察钻机的运转情况,当发生异响、吊索具破损、漏气、漏渣,以及其它不正常情况时,应立即停机检查,排除故障后,方可继续开钻。

14、提钻、下钻时,应轻提轻放。钻机下和井孔周围2米以内及高压胶管下,不得站人。严禁钻杆在旋转时提升。

15、发生提钻受阻时,应先设法使钻具活动后再慢慢提升,不得强行提

升。如钻进受阻时,应采用缓冲击法解除,并查明原因,采取措施后,方可钻进。

16、钻架、钻台平车、封口平车等的承载部位不得超载。

17、使用空气反循环时,其喷浆口应遮拦,并应固定管端。

18、钻进进尺达到要求时,应根据钻杆长度换算孔底标高,确认无误后,再把钻头略为提起,降低转速,空转5—20min后再停钻。

19、钻机的移位和拆卸,应按照说明书规定进行,在转移和拆运过程中,应防止碰撞机架。

20、作业后,应对钻机进行清洗和润滑,并应将主要部位遮盖妥当。

21、严格按照文明卫生施工要求,提高职工素质,确保工程完成。作业时,禁止直接或间接向河道排放泥浆,禁止泥浆外泄污染环境,泥浆池周边设置醒目安全警示标牌,并用安全网围护,防止小孩入内观望。

22、未及时灌注的桩孔及护筒需用安全平网严实遮盖,防止路人误撞入,每台钻机上设置醒目安全警示标牌,时刻警示操作人员及他人。

七、施工安全保证措施

(一)、施工中的安全措施

1、施工人员必须戴安全帽,穿绝缘胶鞋,孔周边作业人、监护人员,必须戴安全帽,严禁穿拖鞋、赤脚、酒后上岗作业。

2、施工现场电源线路,必须按“三相五线”制,TV-S系统要求布置,并按“三级配电”“二级漏电分级”分段保护。

3、各孔井用电必须分闸,严禁一闸多孔和一闸多用。必须一机一闸一漏一箱进行敷设。

4、孔上电线、电缆必须架空。

5、电箱一律采用铁质电箱,电箱应有严密的防雨措施,安装位置合适,安装牢固,进出线整齐,拉线牢固,熔丝不得用金属代替,箱内不得放其它物品。

6、现场电源线路及电气设备,由持证电工负责安装维护,经验收合格后,方准投入使用。

7、施工现场所有设备和机具必须做好保护接零。

8、所有机械设备的传动部位,必须装设防护罩。

9、垂直起重设备必须经常性检修维护,保证机件能够运转正常,操作灵活,按钮开关、减速器、钢丝绳、绳卡、吊钩、吊桶、吊笼等,不得带病作业。

10、垂直起重设备支架应牢固,应能承受一定的冲击力不至翻倒,垂直起重设备必须经检验合格后,方可投入使用。

(二)、施工现场安全防护措施

1、夜间施工时,要有足够的照明,施工危险区域,白天悬挂明显标志,夜间悬挂标志灯。

2、事故易发部位,如本工程高空作业处,起吊区,用电机械等安排专职的安全员进行指挥与监督;

3、现场施工特种作业人员要佩带专门的防护用品,如电焊工要佩带护目镜和面罩,高空作业系好安全带。

4、所有现场施工人员严禁酒后上岗。

5、现场施工道路的交叉处或拐弯处设立安全警告标志。

6、变压器周围设高度不低于1.7米的安全护栏,四周挂上“小心!高压危险”的警告牌。

7、定期进行安全生产检查工作,对检查出的不安全因素和隐患应立即整改,整改不力的悬挂警告黄牌,直至整改完毕。

8、工地入口处设安全告示板,宣传施工安全信息,安全检查记录,整改情况。

(三)、消防措施

由于工地易燃物资较多,一旦发生火灾造成的损失是不可估量的。为此,必须要高度的重视,从最大的可能,用最有效的手段彻底消除存在火灾的隐患,保证生产的顺利进行。

1、烟区内严禁出现油烟。

2、生活区房屋、仓库的间距符合防火安全距离要求。

3、动用明火的区域、木工棚、生活区及每个墩的施工点设置足够多的消防设施,种类、规格齐全。

4、陆上高压配电间作为重点火警区进行设防。以便对不同类型的火患进行抢救。

5、对施工人员进行消防知识的宣传和教育工作,使工人能从根本上提高警惕。定期进行消防演习。

(四)、不测事件发生时的处理应急方案

1、应急救援处置预案机构

1)项目部应急救援处置预案指挥机构为安全生产领导小组。指挥部应在

应急抢险队人员、通讯、交通车辆、物资器材、工具、资金等方面实施抢险救援中起绝对保证作用,满足抢险救援。其应急抢险救援领导小组成员如下: 组 长:杨成民 副组长:朱磊、陈全贵

组 员:梁亮、项目部各科室、各施工队负责人。

2)项目部成立应急救援处置抢险队,队员为20人。

3)桥梁作业队成立应急救援处置抢险队,队员为20人。

2、几种意外事故的应急救援程序

1)雪灾灾害事故。班组、作业队要立即报告项目部,项目部再视灾害程度组织应急队抢救的决定。作业队要立即组织人员抢险,保护员工,减少财产损失。

2)发生消防火灾事故。一旦发生火灾险情,早发现早扑灭采取果断措施扑灭火灾和防止火势蔓延,疏散人员,抢救财产,并立即报告项目部,项目部再视情况报告消防部门和当地政府、林业部门呼救“119”支援抢险。

3)发生爆炸事故。一旦发生爆炸事故,项目部安全生产领导小组立即组织抢险队员抢险,并拨打“110”报警电话,请求地方公安部门支援。

4)发生雷电灾害事故。一旦遇暴风骤雨天气有雷电情况发生,工人要立即暂停施工,回棚(房)躲避,并远离大树下、铁吊架下等,撑伞不能紧握金属支撑杆。当雷雨现象比较严重时,要立即切断动力电源,并且关掉一切用电器。尽量少使用手机等无线射频设备。

5)停水、停电事故。起用储备用水,根据停水时间合理供应水;起用发电机,保证重要设备、施工供电;将外部供电线路总闸断开,接到供电通知

后再使用外部供电。

6)中毒、急性传染病事故。项目部安全生产领导小组立即组织专业人员进行抢救,安排车辆将病员以尽快速度送往医院,或者拨打“120”请求支援。

7)设备大修、故障事故。主管部门立即联系租用或起用备用设备,组织人员抢修设备。

3、施工常见事故的应急救援程序

1)发生轻伤事故后,首先抢救伤员,事故现场有关人员要立即报告,采取措施防止事故的扩大。轻伤事故由班组、作业队组织有关人员调查处理,作业队登记,报项目部存查。项目部、作业队按《安全生产管理办法》有关规定处罚

2)发生重伤、死亡事故,事故现场有关人员要立即报作业队和项目部,同时立即抢救伤员保护现场。作业队和项目部在收到事故报告后,立即组织工会、技术、安全部门等组成事故调查组,立即赶赴现场调查了解,分析事故原因,在24小时内报当地劳动安全监督管理局和检察院,由当地县(市)一级政府调查处理批复结案,然后项目部再按《安全生产管理办法》有关规定进行处罚处分。

3)发生交通事故,首先当事者立即抢救伤员、保护现场,立即报告当地公安交警部门赶赴现场调查处理,同时立即报告作业队和项目部

第三篇:《钻孔灌注桩基础施工方案》

钻孔灌注桩基础施工方案

一、施工方法

1.准备场地、测量放线:施工前应进行场地平整,清除杂物,钻机位置处平整夯实,准备场地,同时对施工用水、泥浆池位置,动力供应,砂石料场,拌和机位置,钢筋加工场地,施工便道,做统一的安排。

测量放线,根据设计图纸用经纬仪(或全站仪)现场进行桩位精确放样,在桩中心位置钉以木桩,并设护桩,放线后由主管技术人员进行复核,施工中护桩要妥善看管,不得移位和丢失。

2.埋设护筒

护筒因考虑多次周转,采用3一10mm钢扳制成,护筒内径,使用旋转钻机时比桩径大10一20cm,使用冲击钻时比桩径大20一30cm,埋置护筒要考虑桩位的地质和水文情况,为保持水头护筒要高出施工水位(或地下水位)1.5m,无水地层护筒宜高出地面0.3—0.5m,为避免护筒底悬空,造成蹋孔,漏水,漏浆,护筒底应坐在天然的结实的土层上(或夯实的粘土层上),护筒四周应回填粘土并夯实,护筒平面位置的偏差应不超5cm。护筒埋置深度:在无水地区一般为1一2倍的护筒直径。在有水地区一般为入土深度与水深的0.8一1.1倍(无冲刷之前)。

3.选择钻孔机械:

正循环钻机:粘性土、砂类土:砾、卵石粒径小于2cm,钻孔直径80-250cm,孔深30一100m。

反循环钻机:粘性土、砂类上、卵石粒径小于钻杆内径2/3,钻孔直径80一250cm,孔深泵吸<40m,气举100m。

正循环潜水钻机:淤泥、粘性上、砂类土、砾卵石粒径小于10cm,钻孔直径60一150cm,孔深50m。

全套管冲扳抓和冲击钻机:适用于各类土层,孔径80一150cm,孔深30一40m。

在钻孔过程中,钻机(架)必须保持平稳,不能发生位移和沉陷。因此钻机安装就位时,底座应用枕木垫实塞紧,顶端用风绳固定平稳。

4.制备泥浆应选用塑性指数IP>10的粘性土或膨润土,对不同上层泥浆比重可按下列数据选用:

粘性土和亚粘土可以就地造浆,泥浆比重1.1一1.2间。

粉土和砂土应制备泥浆,泥浆比重1.5—1.25:

砂卵石和流砂层应制备泥浆,泥浆比重1.3—1.5。

5.钻孔灌注桩施工

将钻机调平对准钻孔,把钻头吊起徐徐放人护筒内,对正桩位,启动泥浆泵和转盘,等泥浆输到孔内一定数量后,方可开始钻孔。具有导向装置的钻机开钻时,应慢速推进,待导向部位全部钻进土层后,方可全速钻进。

正循环钻机开孔时,应先启动泥浆泵和转盘,待泥浆进入孔内一定数量后,方可开始钻进。

用泵吸式反循环钻进时,钻头应距孔底20一30cm,防止堵塞吸渣口,在接长钻杆时,应注意接头紧密,防止漏气、漏水和钻杆松脱。

用气举式反循环钻开孔时,钻杆必须在钻孔内埋入水中约6m,才能扬水排渣。

反循环钻进时,必须注意连续补充泥浆,维持护筒内应有的水头,避免坍塌。

钻孔应连续进行,不得间断,视土质及钻进部位调整钻进速度。开始钻进及护筒刃脚部位或砂层、卵砾石层中时,应低档慢速钻进。钻进过程中,要确保泥浆水头高度高出孔外水位0.5M以上,泥浆如有损失、漏失,应及时补充,并采取堵漏措施。钻进过程中,每进2-3m应检查孔径、竖直度,在泥浆池捞取钻渣,以便和设计地质资料核对。

钻进时,为减少扩孔、弯孔和斜孔,应采用减压法钻进,使钻杆维持垂直状态,使钻头平稳回转。

终孔检查合格后,应迅速清孔,清孔方法有抽浆法(适用于孔壁不易坍塌的柱桩和磨擦桩、换浆法(用于正循环钻机)、淘渣法(适用于冲抓、冲击、成孔,掏渣后的泥浆比重应小于1.3)。清孔时必须保证孔内水头、提管时避免碰孔壁。清孔后的泥浆性能指标,沉渣厚度应符合规范要求。

不论采用何种方法清孔排渣,都必须注意保持孔内水头,防止坍孔。

清孔后用检孔器测量孔径,检孔器的焊接可在工地进行,监理工程师检验合格后,即可进行钢筋笼的吊装工作。

钢筋笼骨架,焊接时注意焊条的使用一定要符合规范要求,骨架一般分段焊接,长度由起吊设备的高度控制,钢筋笼的接长,可采用搭接焊或套管冷挤压连接等方法,钢筋笼安放要牢固,以防在砼浇筑过程中钢筋笼浮起,钢筋笼周边要安放圆的砼保护层垫块。

水下砼采用导管法进行灌注,导管内径一般为25一35cm,导管使用前要进行闭水试验(水密、承压、接头抗拉),合格的导管才能使用,导管应居中稳步沉放,不能接触到钢筋笼,以免导管在提升中将钢筋笼提起,导管可吊挂在钻机顶部滑轮上或用卡具吊在孔口上,导管底部距桩底的距离应符合规范要求,一般0.25一0.4m,导管顶部的贮料斗内砼量,必须满足首次灌注剪球后导管端能埋入砼中0.8—1.2m,施工前要仔细计算贮料斗容积,剪球后向导管内倾倒砼宜徐徐进行防止产生高压气囊。施工中导管内应始终充满砼。随着砼的不断浇入,及时测量砼顶面高度和埋管深度,及时提拔拆除导管,使导管埋入砼中的深度保持2—6m间。砼面检测锤随孔深而定,一般不小于4Kg。

每根导管的水下砼浇筑工作,应在该导管首批砼初凝前完成,否则应掺人缓凝剂,推迟初凝时间。

砼的坍落度应满足设计要求,砼浇筑应连续进行,为保证桩的质量,应留比桩顶标高高出0.5一1.0m左右的桩头,处于干处的桩头,可在砼初凝后,终凝前清除。

技术人员应对钻孔灌注桩各项原始记录及时进行整理签认。

6.环保措施

为保护施工范围内的环境卫生、农田,钻孔桩废弃的泥浆应在施工完成后,用汽车或罐车将泥浆池(槽)中的泥浆清运到指定的排放地点。

7.工艺流程

(做好各项记录,监理工程师批准)

测量定位

填筑工作平台

场地平整

钻机就位

制做护筒

埋设护筒

复核放样

钻孔

清孔

终孔检查

终孔

钢筋笼就位

测量复核定位

合格泥浆

泥浆池

钢筋笼制作

检查

导管拼接检查

下导管

检查隔水设施

水下灌注砼

砼试验

砼运输

拔出护筒

成桩检测

砼的拌合(做好记录和签认手续)

8.主要机械设备

钻机、砼搅拌机、砼运输车、吊车、空压机、水泵、导管、泵车、装载机、电焊机、发电机、水车等。

附:钻机性能比较表如下:

那个钻机型号

成孔直径

m

钻深m

转盘转速r/min

最大钻矩

KN﹒M

主机功率

KW

钻机重

t

KR2500A(河北星河厂)

Ф1.8-2.5

2*22=44

KP2000(郑州勘探厂)

Ф1.5-2.0

S-500

(台湾)

Ф1.5-2.5

150

320

GPS-25(上海探矿厂)

Ф1.5-2.5

GPS-20(上海探矿厂)

Ф1.5-2.5

END

第四篇:钻孔灌注桩施工方案

钻孔灌注桩施工方案(一)设备选择 根据本工程的地勘资料和施工组织总设计工期安排的基础工程施工工期,以及本工程招标文件和合同文件对质量的要求,结合我司的施工经验和设备配置能力,该工程机械钻孔灌注桩成孔采用旋挖钻机钻孔成孔,钻机设备暂选用2台中联重科280型旋挖钻机,根据情况调整增加。机械钻孔灌注桩混凝土工程采用近距离的商品凝土的搅拌站供应混凝土,满足机械钻孔灌注桩施工需要。

2、施工方案 a、将一期工程机械钻孔桩施工画分为五个施工区域段:

第一施工区域段:售房部;

第二施工区域段:3#商业、7号商住楼;

第三施工区域段:4#商业、6 号商住楼;

第四施工区域段:5#商业、5 号商住楼;

第五施工区域段:13号楼金融中心;

施工平面布置图附后:

b、施工顺序 售房部基础机械钻孔桩施工顺序自第一施工区域开始,第二 第三......至第五施工区域结束。

C、为了保证基础工程施工的整体性和连续性,第一施工区域范围的机械钻孔灌注桩完成后进行下一个施工段时,同时进行第一施工阶段土石方开挖和基础梁施工。象这样流水泊节的施工,延续不段的施工下去。

(二)机械钻孔灌注桩施工 1、机械钻孔灌注桩施工工艺流程 施工准备 放样定位 钻机定位 钻进成孔 制浆 清孔 选择钻进参数 泥浆循环 下钢筋笼 泥浆外运 下导管 运送钢筋笼 混凝土灌注 制作钢筋笼 检查拼接导 管好管管 起拔护筒 埋设护筒 清除障碍物 运输混凝土 回填桩孔 试块制作 2、机械钻孔灌注桩施工(1)施工准备 A、技术准备 工程开工前,组织相关施工人员熟悉施工图及相关技术规范、规程;

‚由项目技术负责人对相关施工人员进行施工技术和安全技术交底;

ƒ编制施工作业计划,并对施工作业人员进行交底。

B、人员准备 序号 工 作 名 称 人 数 备 注 1 钻孔桩钻机操作工 12 基础工程钻孔桩土石方施工作业 2 钢筋工 40 钻孔桩钢筋笼制作、加工、安装 3 混凝土工 20 混凝土浇筑施工作业 4 砖工 10 基础施工排水沟施工作业 5 值班电工 2 施工现场用电维护 6 机修工 4 施工机械修理维护 7 吊车司机 2 8 铲车司机 2 9 运渣车司机 6 10 塔吊操作工 8 11 挖机司机 4 基础机械钻孔灌注桩施工劳动力计划表 组织根据施工作业计划要求的参加机械钻孔灌注桩施工作业人员进场;

‚对项目管理人员进行机械钻孔灌注桩部分的施工管理人员落实到位;

C、施工机械准备 基础施工阶段机械设备计划表 序号 设 备 名 称 型 号 单位 数 量 容量(KW)备 注 1 塔 吊 QTZ-40 台 3 135 5、6、7号楼 垂直运输(30KV/台)2 塔 吊 QTZ-50 台 1 30 售房部、13号金融中心重直运输(40KV/台)3 混凝土搅拌机 JS70 台 3 45 搅拌混凝土使用 4 混凝土输送泵 台 1 混凝土输送 5 旋挖钻机 中联280 台 4 钻孔桩土石方钻孔用 6 水泵 台 10 钻孔桩抽水用 7 插入式砼振动器 HZ6-50A 台 10 30 基础梁施工 8 电 焊 机 BX6-200 台 2 50 钢 筋接长 焊 接 9 钢筋切断机 QJ40-1 台 5 35 钢筋加工 10 钢筋弯曲机 GW-40B 台 4 30 钢筋加工 11 钢筋调直机 GT6-12 台 4 12 钢筋加工 12 台 钻 ZLY-78 台 2 6 1.70KW 13 蛙式打夯机 HWR180 台 4 12 回填土夯实 14 吊车 16t 台 2 桩钢筋笼安装用 15 铲车 0.6m³ 台 1 除渣装车用 16 渣土运输车 5t 辆 6 渣土转运 17 挖机 台 3 按照基础施工阶段机械设备计划组织机械设备设备进场;

‚准备钢筋加工机械进场;

ƒ准备混凝土搅拌系统和浇筑机械及其它辅助机械设备进场。

D、材料准备 材料计划需求表 序号 材料名称 规格或型号 单位 数 量 进场时间 使用部位 1 钢 材 Φ8 t 50 工程开工时 基础钻孔灌注桩用  2 钢 材 Φ10三级钢 t 50 工程开工时 基础钻孔灌注桩用  3 钢 材 Φ14三级钢 t 150 工程开工时 基础钻孔灌注桩用  4 钢 材 Φ16三级钢 t 150 工程开工时 基础钻孔灌注桩用  5 柴油 0# t 39 工程开工时 基础钻孔机械用  6 水 泥 42.5R t 2100 工程开工时 基础钻孔灌注桩用  7 特细砂 长江产 m3 3500 工程开工时 基础钻孔灌注桩用 8 碎石 10~20 m3 6000 工程开工时 基础钻孔灌注桩用 9 铅丝 12# ㎏ 200 工程开工时 基础钻孔灌注桩用 注:材料在机械钻孔桩开钻时陆续进场。

(2)机械钻孔灌注桩施工进度安排 施工工期(钻孔桩部分不含地梁、回填土):75日历天。(进度计划表如下 序号 分项工程名称 工作天 工 作 时 间 六月 七月 八月 九月 15 30 10 20 30 10 20 30 10 2 售房部工程钻进成孔 13 3 售房部钢筋笼制作 12 4 售房部钢筋笼安装 10 5 售房部混凝土灌注 10 6 售房部桩基检测 1 7 3#商业、7号商住楼工程钻进成孔 15 8 3#商业、7号商住楼工程钢筋笼制作 14 9 3#商业、7号商住楼工程钢筋笼安装 13 10 3#商业、7号商住楼工程混凝土灌注 13 11 3#商业、7号商住楼工程桩基检测 1 序号 分项工程名称 工作天 工 作 时 间 六月 七月 八月 九月 15 30 10 20 30 10 20 30 10 12 4#商业、6 号商住楼工程钻进成孔 15 13 4#商业、6 号商住楼钢筋笼制作 14 14 4#商业、6 号商住楼钢筋笼安装 13 15 4#商业、6 号商住楼混凝土灌注 13 16 4#商业、6 号商住楼桩基检测 1 17 5#商业、5号商住楼工程钻进成孔 15 18 5#商业、5号商住楼工程钢筋笼制作 14 19 5#商业、5号商住楼工程钢筋笼安装 13 20 5#商业、5号商住楼工程混凝土灌注 13 21 5号楼工桩基检测 1 序号 分项工程名称 工作天 工 作 时 间 六月 七月 八月 九月 15 30 10 20 30 10 20 30 10 22 13号楼金融中心工程钻进成孔 15 23 13号楼金融中心钢筋笼制作 14 24 13号楼金融中心钢筋笼安装 13 25 13号楼金融中心混凝土灌注 13 26 13号楼金融中心桩基检测 1 机械钻孔灌注桩施工进度计划(3)土石方机械钻孔钻进施工方法 A、放样定位 工程开工前,根据轴线及桩位布置情况,在场地内建立测量控制网,然后依据控制网测放各桩位点。放线完成报监理工程师复验符合要求后进行下道工序施工;

B、钻孔机位 本工程选用自身履带爬行式钻机,钻机定位,由钻机自身配置电脑控制系统进行钻机桅杆与机身水平和垂直调整定位,钻机就位时必须稳固、竖直、水平,定位准确,钻头中心与桩位中心误差不大于10mm。

C、埋设护筒 钻机就位后,在测量和施工人员的指导下,钻尖对准桩位中心,钻机旋挖至一定深度取出土后下放护筒。一般护筒埋深1-2m,护筒直径应比桩孔直接大200mm,长度应满足护筒底进入黏土层不少于0.5m,的要求,护筒顶端高出地面0.3m,护筒埋设的倾斜度控制在1%以内,护筒埋设偏差不超过30mm,护筒四周用黏土回填,分层夯实;

护筒埋设应复测、校正桩位与护筒中心偏差:护筒埋设好后,由测量人员进行桩位复核校正。报和监理工程师确认后,进行钻进成孔。

D、钻孔机钻土石成孔 在钻进过程中,采用连续性筒式取土钻进成孔,结合以往施工经验,我方采用中联旋挖机成孔,在护筒埋设并定位后,使用ZL-280型转挖机钻进,该钻机扭矩大,转速高,成孔效率高,适合在中风化层中钻进。

E、清孔(如有扩大头才需清孔)在钻机钻至设计孔深后,将钻头降至孔底,慢转,重点是清出扩大头扩出的余泥、余渣。

F塌方、塌孔处理措施 a、有河砂、卵石层,有塌方、塌孔的现象,处理方法:

将已经塌方的土方重新钻出,立即浇满C20 素砼,待三天以后重新开始钻孔,如果河砂、卵石层厚,每钻深1米浇一次,象这样重复作业直到钻穿河砂、卵石层为至。

b地下水、於泥层也有塌方塌孔现象,处理方法:

钻机在就位时应重新测量、定位,在成孔过程中采用泥浆护壁。利用钻进过程中钻头对泥土的搅拌作用自然造浆,根据实际需要可对泥浆的比重进行调节,在施工过程中泥浆比重一般控制在1.2~1.3之间,泥浆在循环过程中在孔壁表面形成泥皮,它和泥浆的自重对孔壁形成护壁起保护桩孔作用,防止孔壁坍塌。通过成孔施工,泥浆护壁效果比较好,完全可以满足施工的需要。可通过掏渣筒掏渣以及给孔内加清水的方法来调节泥浆的比重,根据实际施工需要,泥浆比重一般控制在1.3以上,这样有利于钻进和孔壁的稳定。

3、钢筋笼制作与安装 A、钢筋笼制作 钢筋笼在现场分节制作,主筋与加强筋的交叉位置采用点焊焊接,螺旋筋与主筋采用隔点焊加固,钢筋笼制作除符合设计要求外,还应符合表8-2-1规定。制作好的钢筋笼,即进行逐节验收,合格后挂牌存放;

分段制作的钢筋笼接长时,上下主筋位置对正,保证钢筋笼的上下节的主筋在同一轴线上,钢筋接长采用单面搭接焊,焊缝长度不小于10d,封闭箍和加强环采用单侧搭接焊,主筋焊接时接头应错开,在同一截面内的钢筋接头数不得多于主筋总数的50%,螺族箍筋应大部分与主筋点焊,增加钢筋笼的强度,钢筋笼接长焊接应满足《钢筋焊接验收规程》JGJ18-2003的相关要求。

钢筋笼制作允许偏差表 8—2-1 项次 项目 允许偏差 1 主筋间距 ±10 2 箍筋间距 ±20 3 钢筋笼直径 ±10 4 钢筋笼长度 ±50 B、钢筋笼孔内安装 钢筋笼较长(超过16m)时,钢筋笼接长在孔口进行,将需要接长的钢筋笼第一节用吊车吊装安装在桩孔内固定,将第二节钢筋笼用吊车吊起,上下节钢筋笼主筋对正错头焊接,单面焊搭接倍数不小于10d,焊缝高度≥0.3d,焊缝宽度≥0.6,上下节应保持顺直,同截面接头不得超过配筋的50%,接头相互错开不小于35d。钢筋焊接完好后,应缓慢下放入孔内,严禁砸笼。

(4)下导管 导管的选择 采用丝扣连接的导管,其内径Φ250~Φ280,底管长度为4m,中间每节长度一般为2.5m。在导管使用前,必须对导管进行外观检查、对接检查。

(1)外观检查:检查导管有无变形、坑凹、弯曲,以及有无破损或裂缝等,并应检查其内壁是否有混凝土粘附固结。

(2)对接检查:导管接头丝扣应保持良好。连接后应平直,同心度要好。

经以上检验合格后方可投入使用,对于不合格导管严禁使用。导管长度应根据孔深进行配备,满足清孔及水下混凝土浇筑的需要,即清孔时能下至孔底:水下浇筑时,导管底端距孔底0.5m左右,混凝土应能顺利从导管内灌至孔底。

‚导管下放 导管在孔口连接处应牢固,设置密封圈,吊放时,应使位置居中,轴线顺直,稳定沉放,避免卡挂钢筋笼和刮撞孔壁。

(5)混凝土浇筑 混凝土采用混凝土输送泵将混凝土直接输送到需要浇筑混凝土的桩孔位置倒入料斗内,混凝土坍落度控制在18~22cm;

‚如遇水下混凝土时,在混凝土浇筑前,对不同直径、深度的桩孔分别计算出混凝土浇筑初灌量。施工中要保证混凝土浇筑初灌量。浇筑时导管埋深控制在2~6m(根据桩孔内水的深浅确定),混凝土浇筑完成拆管前安排专人测量孔内混凝土高度,并做好施工记录,浇筑混凝土接近桩顶标高时,应控制最后一次浇筑量,确保桩顶标高符合设计要求;

ƒ水下混凝土灌注施工应注意以下几点:

a下灌注导管后,进行二次清孔,确保孔底沉渣厚度符合规范要求;

b对灌注导管要检查其圆满度,垂直度及其连接密封性,定期对导管进行水封试验;

C用于灌注混凝土的导管的底部距孔底300-500mm,并做好记录;

D导管连接处的隔水塞选用与导管口径相符的橡胶皮球。保证混凝土桩截面尺寸,导管埋深不低于0.8~1.5m,连贯灌注时宜埋深2-6m,混凝土灌注灌注应连续进行;

e灌注混凝土过程中,要不定时检查混凝土上升高度,控制埋管深度。混凝土上升到骨架底口4m以上时提升导管;

导管底口高于钢筋笼骨架底部2m以上时恢复混凝土灌注,保持正常的埋管深度,灌注接近桩顶时,要保持足够的导管高度,采用接入短导管等措施,水下混凝土灌注面高出桩顶设计高程 1.0~1.5m(此高度是根据该地层裂隙发育等情况暂定,具体由设计、监理及业主方确定),以便清除浮浆,确保混凝土桩身质量。拆除导管之前测量混凝土面高程,以保证灌注混凝土达到设计高程;

f导管提升应保持与桩孔垂直,防止挂碰钢筋笼,拆下的导管要及时冲清干净;

h灌注混凝土时充盈系数控制在1.1左右,根据试验钻孔桩混凝土充盈系数为1.3,因此地层灌注混凝土时充盈系数会大于1.1,超出部分的混凝土应由甲方或监理签证认可;

g混凝土灌注接近桩顶时,由于导管内混凝土高度减小,压力降低,管外泥浆稠度比重增加,出现灌注困难,应提高漏斗高度。砼灌注完成时,适时拨出护筒,并做好孔口防护,防止发生意外事故。

(5)起拔护筒 混凝土浇筑结束后,即起拔护筒,并将浇筑设备机具清洗干净,堆放整齐。

(6)回填桩孔 桩孔混凝土浇筑完成后,应将上部未灌混凝土部分利用场地内护筒、沟、池、槽开挖出来的泥土、矿渣等进行回填,回填满后,用混凝土重新将孔口封住来保护好钢筋锚固,整块硬地坪场地。

(7)机械钻孔灌注桩施工注意事项 a安排专人负责测量钻进深度,做好日施工记录;

b进行灌注水下混凝土施工时,安排专人测量导管的埋入深度,并作好记录;

c灌注混凝土时,应做好混凝土用量记录,提出超充盈系数量的索赔依据;

d安排专人进行混凝土试块制作、养护和送检;

(三)桩基检测及验收 1、施工检验 1.1.1 施工前应进行下列检验:

a 应严格对桩位进行检验;

b 混凝土拌制应对原材料质量与计量、混凝土配合比、坍落度、混凝土强度等级等进行检查;

c 钢筋笼制作前应对钢筋规格、焊条规格、品种、焊口规格、焊缝外观和接头质量等进行检验。

1.1.2 施工过程中应进行下列检验:

a 施工钻机成孔过程中,应按照本规程有关施工质量控制要求,对已成孔的中心位置和孔深、垂直度进行检验;

b 钢筋笼制作允许偏应符合表1.1.2的要求:

表1.1.2 钢筋笼制作允许偏差 项目 允许偏差 主筋间距 ±10 箍筋间距 ±20 钢筋笼直径 ±10 钢筋笼长度 ±100 c 应对钢筋笼安放的实际位置进行检查,并填写检查记录。

d 应对地面土体和已施工的邻近桩位进行观察,若发现异常,应采取跳打、调整施工顺序及排水减压、控制成桩速率等技术措施。

1.1.3 成桩后应根据本规程表1.1.2的规定检查成桩桩位偏差。

2、检测和验收 2.1.1 工程桩应进行承载力和桩身质量检验。

2.1.2 有下列情况之一的桩基工程,应采用静荷载试验对工程桩的单桩竖向承载力进行检测,检测数量应根据桩基设计等级、工程施工前取得试验数据的可靠性,按《建筑基桩检测技术规范》JGJ106执行。

a 工程施工前已进行单桩静载试验,但施工过程中变更了工艺参数或施工质量出现异常时;

b 施工前工程未按本规程第5.4.1条的规定进行单桩静载试验的工程;

c 地质条件复杂、桩的施工质量可靠性低;

d 对于没有旋转挤压灌注桩施工经验的地区。

2.1.3 有下列情况之一的桩基工程,可采用高应变动测法对工程桩的单桩竖向承载力进行检测。

a 除本工程6.3.2条规定条件外的桩基;

b 设计等级为甲、乙级的建筑桩基静载试验检测的辅助检测。

2.1.4 桩身质量除对预留混凝土试件进行强度等级检验外,尚应进行现场检测。检测方法可采用可靠的动测法,检测数量应符合《建筑基桩检测技术规范》JGJ106的规定。

2.1.5 对抗拔桩和水平承载力有特殊要求的桩基工程,应进行单桩抗拔静载试验和水平静载试验检测。

2.1.6 当桩顶设计标高与施工场地标高相近时,基桩的验收应待基桩施工完毕后进行;

当桩顶设计标高低于施工场地标高时,应待开挖到设计桩顶标高后进行验收。

2.1.7 旋转挤压灌注桩分项工程质量验收应包括以下资料:

a 施工合同及单位资质证明文件;

b 工程地质勘察报告,桩施工图,设计变更、洽商记录;

c 经审定的施工组织设计或施工方案及执行中的变更签证情况;

d 技术交底和安全交底;

e 工程定位测量放线记录,包括工程桩位线复核签证单;

f 原材料的质量合格和质量鉴定书;

g 桩施工记录及隐蔽工程验收文件;

j 成桩质量检查报告;

k 单桩承载力检测报告;

l 桩位偏差表及桩位竣工图;

m 其它必须提供的文件和记录。

3、基础钻孔灌注桩工程施工完毕,按照《建筑桩基技术规范》JGJ94-2008的相关要求和规定进行桩基检测,每根桩要进行应变检测,且应抽取工程桩10%的桩进行超声波检测。桩基检测应由具备检测资格的单位进行,工程桩检查一应由监理工程师见证完成,检查桩的确定应由施工单位与监理工程师共同确定,既要具有代表性,又能反映出施工的真实情况。超声波检测管直径25PPR管,并封好底口捆绑在钢筋笼中间位置,顺着钢筋笼一起放下去。且在管内注入清水,胶带缠好留一小出气孔。

4、基础工程施工完成后及时整理基础竣工资料,报请监理工程师组织参建单位质量监督机构搞好工程桩的竣工验收,及时交付上部结构施工。

5、桩基竣工验收应该提交以下竣工资料:桩位测量放线图、工程地质勘察资料、材料试验记录与合格证、施工日志、桩施工隐蔽记录、桩位竣工平面布置图、桩的静动荷载试验资料、分项工程质量检验评定表等相关资料。

四、机械钻孔灌注桩工程施工的质量保证措施 (一)质量保证的组织措施 1、建立以项目经理为第一责任人的质量保证体系,建立项目质量技术管理制度。由项目技术负责人负责制定相关技术措施,做到谁主管谁负责,落实岗位责任制;

2﹑对钻孔灌注桩施工分包单位的资质进行严格仔细地审查,工程质量的把关很大程度上是靠现场工人的双手来完成的,特别是钻孔灌注桩这种对施工工艺有严格要求的工种,严格检查特殊工种的上岗证书等:

3、严格按照设计施工图,现行施工质量验收规范和技术规程和行业标准组织施工和验收。

4、完善施工的交底制度,施工前,逐层落实交底并完善相关手续。

5、严格执行施工过程中的“三检制”,注重过程控制,确保施工质量合格率100%,优良率90% 6、严格执行国家执业资格制度,特殊工种的作业人员必须经培训合格,具有从业资格后持证上岗。

7、对质量要求高、危险性大的工程部位施工,先制定有针对性的施工方案,方案严格按照程序报批和执行。

(二)质量保证的技术措施 1、研究工程地质勘察报告、桩位平面布置图、桩基结构施工图,弄清设计要求和对影响灌注桩工程质量和安全因素进行预测分析。

2﹑研究建筑场地和邻近区域的地下管线、地下构筑物、地面建、构筑物的调查资料,确保周边不受影响。

3、组织设计交底及图纸会审 设计交底与图纸会审可同时进行,以设计交底为主,设计人员讲解设计意图,重申质量标准,了解监理人员提出必要的保证质量的相关要求。

4、编制钻孔灌注桩施工技术方案,由项目技术部门组织研讨,分析论证重点:①施工程序安排是否合理;

②施工机械设备能否保证质量;

③施工方法是否符合现场条件和工艺要求,并满足国家施工规范和质量验评标准等。专项方案按照相关要求报批同意后实施。

5、测量放线的质量控制 a机械钻孔灌注桩工程施工放线使用的测量仪器必须是经检定合格的测量仪器;

b测量放线人员必须是经过培训且考试合格的持证人员;

c测量仪器及测量人员测量放线前,必须以书面形式向监理公司报验,经监理公司批准后进行测量放线工作;

d机械钻孔桩放线时,一定要做好测量放线记录,基桩轴线的控制点和水准基点应设在不受施工影响的地方,复核后妥善保护,施工中经常复测。测量放线完成后,对放线结果反复进行校核,测量放线经项目部技术部门质量检查人员检查合格后,报请现场监理工程师复核签字确认后进行下道工序施工。

6、钻孔桩土石方钻孔质量控制 a施工中严格控制机械钻孔桩的成孔工序和质量,包括孔位、孔径、孔深、垂直度、沉渣厚度等,钻杆的垂直度,钻孔开孔前先检查钻机移动轨道安装牢固、稳定情况,轨道顶平面四角要求在同一标高上,采用水准仪定时进行检查。钻机天车、转盘,孔位必须在同垂直线上,方可开始钻进施工作业。钻杆的垂直度偏差控制在0.2%以内,钻头对孔位应正确,定位时,钻头中心与护筒中心偏差宜控制在15㎜以内。桩位允许误差(D/6,且不大于100mm)。

b监督机械钻孔灌注桩桩分包单位做好清泥换浆工作,以减少孔底沉淀物。对泥浆试验和调制进行质量控制。钻孔过程中检查所用泥浆能否及时调整适应穿过各种地层的需要。一般要求泥浆粘度10~25s,含砂率﹤6%,密度1.15~1.2kg/m3,胶体率﹥95%…… c机械钻孔灌注桩桩孔孔径质量检查与控制,根据钻机性能、地基土土质情况,合理正确地选择钻头形式和直径,选择钻头形式和直径既要考虑成孔直径满足设计要求,又要不造成浪费,孔径检查可制作与钻孔桩直径相等的孔规进行检查,根据检查结果的偏差情况调整和选择适合的钻头。

d孔深质量检查与控制采用测钢尺丈量与钻具钻进记录相结合检查,钻孔深度必须满足设计要求,不得提前终孔。

e终孔时必须进行终孔验收,终孔的确定主要参照三个因素,即设计深度、钻速及浮渣取样,试钻时邀请地勘单位有经验的技术人员进行鉴定指导,报请监理工程师应检查孔深、孔径、沉渣厚度(摩擦桩沉渣厚度≤150㎜;

端承桩沉渣厚≤50㎜),并签字确认。

7、钢筋笼的制作安装质量控制(1)钢筋笼的制作质量控制 a机械钻孔桩钢筋笼的原材料控制 钢筋笼加工前首先检查原材料的材质证明书、出厂合格证,按规范要求抽取试件送检,检验合格后才能用于钻孔灌注桩钢筋笼制作。

b制作钻孔灌注桩钢筋笼钢筋的规格、型号、直径、数量必须符合设计要求。

c钢筋接长时,搭接长度必须符合设计要求,接头的位置应相互错开,同一连接区段的接头百分率应符合规范要求,采用焊接接头时,焊工必须经培训考试合格,持焊工合格证方能进行钢筋焊接作业,正式施焊前,先做试件送检,试件检验合格后才能正式施焊。

d钢筋笼加工完成后,必须实行“三检制”,经检验合格后编号依程序堆放。

钢筋笼安装的质量控制 a按照施工图对应钻孔位置,选择符合设计要求的钢筋笼进行安装;

b钢筋笼安装前,应对照施工图检查钢筋中钢筋的规格、型号、直径、数量是否合乎设计要求,经查无误后进行钢筋笼安装;

c多节钢筋笼接长采用焊接接头时,接头的位置应相互错开,同一连接区段的接头百分率应符合规范要求,采用焊接接头时,焊缝的宽度和高度必须符合规范规定;

d钢筋笼的钢筋保护层采用预制混凝土块控制,保护层混凝土预制块采用桩芯混凝土同强度等级的水泥砂浆制作,保护层垫块的数量每平方米不少于四个,沿钢筋笼均匀布设。

E钢筋笼安装过程中,应采取措施保证钢筋笼顺直。,钢筋笼下道桩孔底部的位置应满足设计要求,钢筋笼安装完成经监理工程师检查验收后才能进行混凝土灌注。

3、混凝土的质量控制 (1)混凝土的原材料质量控制 水泥:用于机械钻孔灌注桩基础施工的水泥进场时首先检查水泥的出厂化验报告,确认该批水泥合格后,再按照规范要求经监理工程师见证抽取试样送检,经检验合格后的水泥才能用于机械钻孔桩基础。

砂石:用于机械钻孔桩的砂石材料由施工项目部调查选择能满足施工需要的砂石材料供应商,在生产地抽取试样送检,经检验合格后,报请业主和监理公司对供应商和供应产地进行实地考察,砂石材料的生产数量和质量能满足施工要求后,再进行采购。每批砂石材料进场后都必须按照规范要求经监理工程师见证抽取试样送检,经检验合格的砂石材料才能用于机械钻孔桩基础。

外加剂:用于机械钻孔灌注桩基础施工的外加剂,不得选用含盐类的外加剂,外加剂进场首先检查外加剂的出厂合格证,然后经监理工程师见证取样送检,检验合格后用于机械钻孔灌注桩基础。

(2)混凝土的施工质量控制 机械钻孔灌注桩的混凝土的质量必须满足设计要求及规范规定,用于机械钻孔灌注桩的混凝土配合比必须是经试配合格的混凝土配合比;

拌制混凝土的各种原材料数量应准确,水泥、外加剂误差控制在1%以内;

砂石、水3%以内,混凝土的塌落度应控制在180~220mm范围内;

混凝土的加工质量必须符合设计要求和施工浇筑需要,拌制好的混凝土应在规范规定的时间内使用完。混凝土灌注施工应安排专人控制灌注混凝土的质量,严格控制桩顶标高,避免超灌或少灌。混凝土灌注施工时按照规范要求经监理见证取样留置试件并送检。

严格工序交接检查制度,严格执行“三检制”,坚持上道工序末经检查不准进行下道工序的原则,上道工序完成后,先由该作业班组自检,质量员专职检查,认为合格后通知现场监理到场共同检验,检验合格后验方能进行下道工序。

五、施工工期保证措施 为了保证在计划的工期内按期(或提前)完成全部施工任务,项目经理部建立以项目经理为主的项目管理班子,项目经理对进度实施全面负责,为工程进度需要的人、财、物和施工组织提供充分保障,主管生产的项目副经理负责生产调度,按照生产计划对人、财、物实行合理调配。技术负责人具体负责工程进度的计划编制、技术方案的制定和负责实施。采取以下措施保证工期按照计划的工期完成:

1、机械钻孔桩工程开工前,按照总体进度计划安排编制详细合理的施工进度计划。采用网络计划技术,对关键线路上的关键工作实施严格控制,抓住关键工序,对影响总工期的工序和具体环节给予重点控制,确保整个工程连续不间断的进行;

2、做好施工前的各项准备工作,对准备投入本工程的全部机械设备进行维修保养,这些工作包括对机械设备进行检修和维护,使机械设备始终保持能正常运行的良好状态,提高施工效率;

3、制定细致、周到、详尽的工期保证措施和赶工措施,对施工进度实施动态管理,定期召开进度分析会,发现问题及时整改。

4、选择具有资质的钻孔桩分包单位,严格控制和检查特种作业人员的持证上岗情况,杜绝“三围”事件发生。

六、基础机械钻孔桩工程施工的安全保证措施 (一)、安全施工措施 1 遇特殊天气时,施工现场应停止作业,并把桩机的重心面调至对风的方向,锁固制动器的锁定装置。螺杆桩机施工中平地行走距离不超过 100m时,可不放下桅杆;

上下坡时桅杆必须放平,回转台应有效制动。螺杆桩机或其配合作业的相关机具在工作时,必须有专人指挥,任何人员不得在工作回转半径范围内停留或通过。螺杆桩机钻孔时,如发现紧固螺栓松动时,应立即停机,重新紧固后方可继续作业。成孔后或因故停钻时,应将钻头下降接触地面,将各部件予以制动,操纵杆放到空档位置后,拉闸切断电源,锁好开关锁。各桩位周围 1.5 米和承台的沟槽边应有防滑措施和明显标志。夜间操作时,应注意工作面周边的环境是否有稳固、牢靠的防护。作业人员在导管对接时必须戴防割手套,且手套大小应合适,并应严格注意安装时手的位置,防止手被导管夹伤。严禁用手清理螺旋叶片上的泥土,防止割伤。

(二)基础钻孔桩工程施工安全的组织保证措施 1、建立以项目经理为第一责任人的安全文明施工保证体系,建立项目安全生产责任制度。将安全生产责任层层分解落实到人;

做到谁主管谁负责,管生产,必须管安全的安全生产原则。

2、严格按照《建筑施工高处作业安全技术规范》JGJ80-1991、《建筑基坑支护技术规程》JGJ120-99、《施工现场临时用电安全技术规范》JGJ46-2005、《建筑机械使用安全技术规程》JGJ33-86等相关规范和技术规程组织施工和检查验收。

3、认真做好安全生产的培训教育工作,做好劳动防护用品的配备、发放、使用和管理工作,建立施工作业交底制度。

4、建立安全生产检查制度,施工作业期间,安全生产监督管理人员必须在岗指导、监督、检查安全生产工作,制止和杜绝“三围”事故发生。

5、建立项目安全生产岗位责任制,明确各级人员安全生产岗位职责。

6、建立安全生产责任追究制度,发生事故按照“四不放过”的原则处理。

(三)基础钻孔桩工程施工安全的技术保证措施 1、建立以项目技术负责人直接责任人、质量安全管理部门、质量安全检查人员、作业班组组成的项目安全技术管理体系;

2、建立、完善专项方案的编制、报审、报验制度;

3、建立项目劳动用工管理档案,专业技术人员、特种作业人员必须持证上岗;

4、建立临时用电管理档案,施工现场的临时用电线路、用电设施的安装和使用必须符合《施工现场临时用电安全技术规范》GB46-2005的相关规定,临时用电线路、用电设备严格按照经审批的《专项方案》架设和安装。夜间施工必须有足够的照明;

5、特种设备严格安装备案和使用备案制度;

6、实行动态管理安全生产,定期和不定期组织和召开安全生产联系会,认真分析安全生产状态和形式,发现问题及时整改;

7、在施工区域内设置明显的安全警示标志标牌,定期派人维护;

8、制定《施工现场应急救援预案》并组织演练。

七、文明施工措施 1、文明施工管理目标:创建市级文明工地 2、文明施工管理措施 项目部建立以项目经理为第一责任人,由项目经理任组成,技术负责人、生产负责人任副组长、项目施工管理人员任组员的项目部安全文明施工领导小组。定期和不定期对项目安全文明施工进行检查,使施工项目的安全文明施工达到以下标准:

① 施工材料堆放整齐规范,安全警示标志、标牌醒目耀眼;

②施工场地排水通畅、规范,冲洗液循环系统根据工程施工需要合理布置,即能满足成孔需要,又要考虑排污方便,确保排污畅通;

③泥浆循环系统冲洗液不能随地处乱排,按照施工布置有组织的排放,建筑废渣、废弃物集中堆放,及时清理外运。以确保施工现场和周边环境不受污染;

④合理安排作息时间,噪声排放尽量控制在居民休息的时段(早六点至晚十点)内,做到施工不扰民。

⑤施工机械停歇时,规范停放,保持施工现场规范有序;

⑥施工现场的生产区、生活区安排专人清扫,随时保持场容场貌整洁、卫生。

仅供参考

第五篇:钻孔灌注桩施工方案(冲击钻)

钻孔灌注桩施工方案

一、工程概况

本合同段****黄庄小桥工程采用钻孔灌注桩基础。桥台桩基直径1.5米,共计12根。采用水下C25混凝土浇筑。

根据桥梁设计图纸和桥位处基本地质情况,并结合调查当地实际情况桩基施工拟采用冲击钻成孔。

二、现场组织及准备

2.1人员、设备、机具、材料配备 2.1.1人员安排

钻孔桩的施工拟投入管理人员4人;技术员3人;钢筋工10人;钻机操作人员2人;混凝土工2人;电工1人。

2.1.2机械设备、机具安排

根据施工进度要求拟投入旋挖钻机1台、25T吊2台、泥浆运输车3台、装载机2台、挖掘机1台、破碎锤1台、板车1台。

2.1.3材料进场计划

材料供应工作紧扣工程施工进度安排,材料供应提前到位。钢筋及混凝土原材料进场后要进行检验,合格后才能使用。

2.2技术准备

2.2.1施工控制网和水准网的建立:

接到设计单位交底的现场平面控制点和水准网后,立即组织测量人员

进行测量放线,根据放线情况进行施工场地的布置。同时在施工场区范围内建立施工控制网和水准网。并经监理工程师复核确认后使用。

2.2.1.1 施工控制网的建立:

根据业主和设计单位提供的平面控制基准点,利用全站仪测设建立施工平面控制网,并将测设成果整理报送监理工程师复测批准,并做为工程基础性资料备案。

2.2.1.2施工水准网的建立:

根据业主和设计单位提供的基准水准点,用S2水准仪测设建立施工水准网,平差后精度满足施工要求,并将成果报送监理工程师复测批准,并做为工程基础性资料备案。

2.2.2 现场勘察:

向业主要求,要有现场地下各种管线、电缆、电信等的详细资料,并由测量人员在现场标定。同时做现场详细堪查,通过挖探坑对能调查的地下管线尽可能弄清。

三、施工进度计划

钻孔桩的计划开工日期为2016年3月30日,完工日期为2016年7月30日,总体计划工期120天(日历天)。因右半幅全部完工后才开始施工左半幅,所以计划施工工期较长。

四、施工方案和技术措施

4.1钻孔工艺

4.1.1场地准备

开钻前场地需完成三通一平。地上、地下的电缆管线、设备基础等障碍物均已排除处理完毕。各项临时设施如照明、动力、安全设施准备就绪。操作前应对钻机、吊车等机械进行安全可靠的检查,确保施工机械处于良好工作状态。场地应先按设计图纸要求的标高进行平整,清除桩位处地上、地下一切障碍物(包括大块石、树根和垃圾等),场地低洼处须回填夯实。

4.1.2测量放线

在恢复定线的基础上,根据经监理工程师及业主审批过的导线点、水准点成果,用全站仪进行基桩桩位精确放样,并在基桩中心位置钉以木桩(木桩中心钉以小铁钉),作为标记。木桩标记要妥善保管,如发现破坏、移位或丢失,必须重新放样。4.1.3冲击钻灌注桩施工工艺

4.1.3.1护筒用6~8㎜钢板卷制焊接而成,护筒直径比桩径大240㎜,200㎜、180㎜上部开一个溢浆口;护筒埋设时先开挖比护筒直径大0.2~0.3m,深1.3m左右的基坑,再安装护筒;按桩位中心线找正后四周倒入粘土压实;进行复测,以确保护筒中心与桩位中心相一致。护筒中心与桩位中心偏差控制在<50㎜,护筒顶端应高于地面0.2m;护筒底部用铁钎探测有无障碍物,若遇障碍物必须及时处理,必要时加长护筒高度;护筒埋好后用钢丝绳做保险系在钢轨上。

4.1.3.2挖循环泥浆池,采用泥浆循环的方法掏渣。4.1.3.3冲桩机就位

护筒埋设结束后将冲孔机就位,冲孔机摆放平稳,钻机底座用钢管支垫,钻机摆放就位后对机具及机座稳固性等进行全面检查,用水平尺检查钻机摆放是否水平,吊线检查钻机摆放是否正确。

4.1.3.4冲击钻成孔

冲机钻就位前,应对钻孔前的各项准备工作进行检查,包括主要机具设备的检查和维修,全面检查钻机的各运转部位是否灵活可靠,润滑油是否够量,冲机钻安装是否平稳,钻机就位后,应水平平稳,不得产生位移和沉陷,冲头和桩位中心应在同一铅垂线上,开孔的孔位必须准确。

根据基桩的直径及工程地质情况,采用5~8T冲击锤。在钻机驱动钻锤冲击的同时,利用泥浆泵,向孔内输送泥浆(当钻进一个时期,检查孔内泥浆性能如果不符合要求时,必须根据不符情况采取不同的方法予以净化改善)。冲洗孔底携带钻渣的冲洗液沿钢丝绳与孔壁之间的外环空间上升,从孔口回流向泥浆池,形成排渣系统。

冲锥的钢丝绳同钢护筒中心位置偏差不大于2㎝,升降机锥头时要平稳,不得碰撞护壁和孔壁。

冲进过程中,每进5~8尺检查钻机直径和竖直度,注意地层变化,在地层变化处捞取渣样,判明后记入记录表中并与地质剖面图核对;根据实际地层变化采用相应的钻进方式,在冲进至中层易液化砂层时,冲进速度必须放慢,以确保成孔质量。

在护筒下1m范围内,宜慢速冲进。

冲孔作业必须连续,并作冲孔施工记录,经常对冲孔泥浆进行检测和试验,不符合要求的随时改正,注意补充新拌的好泥浆,在整个施工过程

中,泥浆的损失要小,孔内水位要保证,防止孔壁坍塌,埋冲锥头的现象发生,确保冲孔桩的成孔质量和成孔速度。

冲孔应用小径冲锥冲到深度后,用大径冲锥扩孔,冲管内的泥渣和泥浆经常倒出,在冲孔排渣,提冲锥头除土或因故停冲时,应保持孔内水头和要求的泥浆指标。

4.1.3.5成孔要点

钻孔桩在软土中钻进,应根据泥浆补给情况控制钻进速度;在硬层或岩层中的钻进速度以钻机不发生跳动为准。

冲孔桩每钻进4~5m验孔一次,在更换钻头前或容易缩孔处应验孔。桩进入全风化岩后,非桩端持力层每钻进30~50cm,桩端持力层每钻进10~30cm应清孔分段取样分析一次,确保入岩深度,并做记录。

成孔中如发生斜孔、塌孔和护筒周围冒浆、失稳等情况,应停止施工,采取相应措施后再进行施工。

4.1.3.6冲孔桩机操作要点及注意事项

开冲时,应稍提冲头,在护筒内旋转造浆,开动泥浆进行循环,待泥浆均匀后以抵挡慢速开始冲进,使护筒脚处有牢固的泥皮护壁。冲至护筒脚下1.0m后,方可按正常速度钻进。冲进过程中必须保证冲孔的垂直。

在冲进过程中,应注意地层变化。对不同的土层,采用不同的冲进方法;在粘土中冲进,中等转速,大泵量稀泥浆,进尺不得太快;在砂土或软土层中,冲进时要控制进尺,抵挡慢速大泵量,稠泥浆冲进,防止泥浆排量不足,冲渣来不及排除而造成埋冲头事故;在土夹砾(卵)石层中冲进时,宜采用抵挡、慢速、良好的泥浆,大泵量。

冲进过程中,要随时观察孔内水位及进尺变化情况,冲机的负荷情况,以便判断塌孔或漏浆。

冲进过程中,对于地层交界处软硬不匀,颗粒粒径大小悬殊,采用低速慢冲,上下反复扫孔,并随时注意冲孔垂直度检测;在松软土层中冲进,根据泥浆补给情况控制冲进速度。

施工期间护筒内的泥浆面应高出地下水位1m以上,在受水位涨落影响时,泥浆面控制在高出最高水位1.5m以上,冲速不要太快,在孔深4m以内不要超过2m/h,往后也不要超过3m/h。

冲进过程中,经常注意泥浆指标变化情况,并掌握好孔内泥浆面高度,发现变化后及时调整。

经常检查机具的运转是否正常,发现异常应立即向当班班长和技术人员报告;润滑部位每班检查一次。

小工具如扳手、榔头、撬棍、垫叉等应放在离孔口较远处,防止掉入孔内。

上下冲时发现阻力大的易缩径孔段,应采取上下来回反复划圆扫孔以保证孔径达到要求。

操作人员要执行操作规程,按规定表格详细记录冲进中每一环节的变化。

钻孔灌注桩施工泥浆循环系统由泥浆泵、护筒、连通管、泥浆池等组成。钻孔泥浆由泥浆泵从泥浆池1内泵送进浆,使悬浮在泥浆中的钻渣上升至孔口,用泥浆泵排入泥浆池2沉淀,经过沉淀后通过连通管进入泥浆池1,再通过泥浆泵泵送进入,如此反复循环。

根据泥浆池、基桩的钻孔灌注工程量及钻孔平台场地条件,钻孔施工过程,利用泥浆池对钻孔泥浆采用重力沉淀法进行净化。

当满足设计要求并达到设计孔深时,经值班质检员检查并经监理认可后允许终孔。

终孔后,首先进行清孔,根据泥浆质量及井内沉渣多少由质检员及实验员确定清孔时间及措施。清孔结束后,由质检员会同监理下探孔器,孔径孔深及沉渣厚度,作好记录,填写相应表格。

4.1.3.7清孔

每钻进1m,采用泵吸反循环清渣;在砼灌注前再次用泵吸反循环清渣进行二次清孔、控制沉淀。4.1.4钢筋笼制作

钢筋笼制作应符合设计要求,钢筋笼的主筋、箍筋和加劲箍筋应按品种、规格、长度编号堆放。钢筋笼的尺寸、电焊质量、搭接长度等,按设计要求和《技术规范》要求施工,钢筋笼要牢固定位,要保证在搬运及安放过程中不变形,安放钢筋笼要对中,并设有导向架,保证钢筋笼的垂直度,吊放钢筋笼时要把制备好的钢筋笼分段吊起进行焊接放入孔内。桩壁混凝土保护层及顶面高程要达到设计要求,同时在钢筋笼上安设检测管,要绑扎牢固,位置正确。放入钢筋笼后要尽快浇筑砼,如孔底彻底清理后4小时尚未开始浇筑混凝土,则孔底必须重新清理。采取有效方法固定好钢筋笼,以防在灌注砼过程中钢筋笼上浮。

钢筋骨架检测项目:

4.1.5桩芯砼灌注

砼浇注导管采用Φ300型快速接口管,按《公路桥涵施工技术规范》JTJ041-2000要求,在浇注前进行密封耐压试验,长度测量标码等工作。

钻孔桩砼浇注工序要求衔接紧凑、有条不紊,清孔完成后,应立即下放钢筋笼,接着下放导管。

在浇注砼前再次检查孔度沉渣厚度,如不满足,则立即利用导管进行二次清孔。

下导管口离孔底0.2~0.4m,第一批灌注砼数量应能满足导管初次埋置深度(≥1.0m)。

灌注开始后,应连续、快速地进行,做到一气呵成,在灌注过程中,要特别注意保持孔内的静压水头,不少于2.0m,同时要及时测量砼面的高度及上升速度。

根据导管长度,推算和控制埋管深度。导管最大埋深不大于6m,最小埋深不小于2m。

桩顶标高的确定:灌注桩顶要比设计桩顶标高多浇注0.8-1.0m,以确

保桩顶质量。

做好每根桩水下砼灌注记录和砼施工记录。

五、质量保证措施

5.1钢筋工程质量保证措施 5.1.1材料进场检验

本工程所用的钢筋,供应商提供具有出厂证书和检验报告的合格钢材,并按规定取样送项目部试验室进行试验,并经总监办中心实验室抽检,鉴定质量合格后方可使用。

5.1.2钢筋焊接

焊工持证上岗,并在规定的范围内进行焊接操作。钢筋焊接时,严格按照设计图纸、施工工艺标准要求进行。钢筋焊接前,根据施工条件进行试焊,实验合格后方可施焊。

5.2混凝土质量保证措施 5.2.1商品混凝土的拌合及运输

商品混凝土拌合过程我单位会派专人进行监督,对所使用的材料、外加剂用量及质量进行检查,同时与现场的施工人员保持联系,如有问题及时与混凝土公司沟通,确保混凝土的施工质量和供应速度。

对于进入现场的混凝土进行质量验收,并检查出厂合格证,经检查合格后方可浇。

制定切实可行的运输路线,同时在施工场地内派专人指挥混凝土运输车辆进、出现场,确保现场的连续浇筑。

5.2.2混凝土浇筑及养护

保证混凝土运输时道路畅通,保证浇筑的连续性。

六、安全措施

6.1安全目标

6.1.1生产活动中的死亡、重伤事故为0。6.1.2安全隐患整改率100%。

认真贯彻落实“安全第一,预防为主”的方针,严格按照安全技术规程和安全规则组织施工。

6.2保证安全生产组织措施

为实现上述目标,成立以项目经理为第一责任人的安全生产组织领导机构,下设安全质量检查室,工程队成立以队长为首的安全生产组织,下设安检室。安检室设专职安检工程师和安检员,工班设兼职安全员,自上而下形成安全生产监督,保证体系,对施工生产实施全过程安全监控。见安全管理组织机构、安全保证体系图。

6.3保证安全生产制度措施

完善各项安全生产管理制度,针对各部位,各工种的各自特点制定相应的安全管理制度,如“安全教育制度,安全检查制度,事故分析制度,安全奖惩制度”等,并由各级安全组织督促检查,加以落实,营造安全生产,人人有责的良好氛围。把“安全生产”充分的落实到每一个员工身上,充分的体现在每一个环节,甚至每一个细微的环节

上。

6.4保证安全生产技术措施

6.4.1针对本工程特点,编制详细的安全操作规程、细则及安全技术措施,并发至工班,组织逐条学习,落实。

6.4.2特殊工种的安全教育、考核、复验,严格按照《特种作业人员安全技术考核管理规则》,执行经过培训考试合格,获取操作合格证后方能持证上岗,对已取得上岗证者,要进行登记存档,按期复审,未经安全教育管理人员、施工人员,不准上岗,未进行三级安全教育的新工人不准上岗,变换工程或采用新工法,新工艺,新设备,新材料及技术难度较大的经过技术,未经培训合格者不准上岗。

6.4.3严格执行逐级安全技术交底制度,施工前由项目总工程师组织有关人员进行详细的安全技术交底,并履行签字手续待查,各施工队安全员组织对施工班组及具体操作人员进行安全技术交底,各级专职安全员对安全措施的执行情况进行督察,并作好记录。

6.4.4所有起重设备、电器设备、运输设备等要加强保养,使其保持良好的工作状态并具有完备的安全装置,所有机具设备的操作人员均经过严格训练,持证上岗,并严格遵守操作规程,严禁违章作业。

6.4.5施工用电按《施工现场临时用电安全技术规范》要求进行设计、检测。施工照明线路电压在窄小施工区域不大于36V,其它区域可用220V,动力设备为380V,所有电力设备设专人检查维护,并设警示标志,操作电气设备,要符合如下规定:

非专职电气操作人员,不操作电气设备。

操作高压电气设备,戴绝缘手套,穿电工绝缘靴并站在绝缘板上。手持式电气设备的操作手柄和工作中接触的部位,有良好绝缘,使用前进行绝缘检查。

低压电气设备加装漏电保护。

电气设备有良好的接地保护,每班均由专人检查。施工现场自备发电机,以防止突然停电造成安全事故。

所有施工用电线路均按施组要求分别定位悬挂,由值班电工负责检查管理。

6.4.6施工现场做到布局合理,场地平整,道路畅通,机械设备安置稳固、材料堆放整齐,用电设施安装触电保护器,为安全生产创造良好的环境。施工现场设醒目的安全标语和安全警示标志,提示工人注意安全。

6.4.7进入施工现场人员,佩戴安全帽,特殊工种按规定要佩戴好防护用品。

6.4.8现场生产、生活区按《消防法》规定,布设足够的消防水源和消防设施网点,消防器材有专人管理,组成业余消防队,定期训练,保证所有施工人员熟悉并掌握消防设备性能和使用方法。

6.4.9严禁酒后驾驶车辆和操作机械,车辆严禁“三超”,禁止使用带“病”的车辆、机械和超负荷运转,并坚持“三查”制。

6.4.10机械设备在施工现场集中停放,严禁对运转中的机械设备进行检修、保养,机械作业的指挥人员,指挥信号准确,操作人员听从指挥,严禁违章作业。

使用钢丝绳的机械,在运行中禁止工作人员跨越钢丝绳,用钢丝绳起

吊、拖拉重物时,现场人员远离作业半径,并对钢丝绳进行定期保养,检查更换

6.4.11钢筋工程安全技术措施

6.4.11.1工程所用钢筋全部在现场加工场加工,钢筋加工前由负责钢筋加工的工长对加工机械(切断机、弯曲机、对焊机等)的安全操规程及注意事基进行交底,并由机械技师对所有机械性能进行检查,合格后方可使用。

6.4.11.2多人合运钢筋,起落、转停动作要一致,人工传送不在同一垂直线上,钢筋堆放要分散、稳当、防止倾倒和塌落

6.4.11.3钢筋起吊捆牢固,吊勾下方不站人,吊运绑扎钢筋工作架子系好钢丝绳,在无任何牵连的情况下进行吊运,到位后,待工作架放稳,搭好支撑主能放下钢丝绳。

6.4.12吊装工程安全防护措施

6.4.12.1吊车司机由我公司机械公司负责管理和安全交底,机械公司派专业工程师住现场,负责解决吊车的维修检查和管理,确保现场吊车的安全使用,保证吊装方案的顺利实行。

6.4.12.2吊车钢丝绳、绳具由项目经理部负责和安全使用。6.4.12.3吊车信号指挥工经培训考试合格持证上岗,严格执行以下“十不吊”的规定:

①被吊物超过机械性能允许范围 ②信号不明 ③吊物下方有人 ④吊物上站人 ·⑤埋在地下物 ⑥斜拉、斜牵、斜吊

⑦散物捆扎不牢 ⑧零散、小物件无容器 ⑨吊物重量不明,吊索具不符合规定 ⑩六级以上强风 6.4.12.4吊车起吊前,安全部门验收合格后方准使用。

6.4.13影响道路交通的工程施工时,首先与管理部门取得联系,制定确保施工安全的工程施工方案、施工计划及保证安全的具体措施,报管理部门审批,按批准的方案在规定时间内完成施工作业。

七、环境保护

认真贯彻执行河南省环境保护的有关政策、法规,对参加施工的全体人员进行环境保护知识、法规宣传教育,把做好环境保护工作和坚持文明施工,变为每个职工的自觉行动。

7.1按政府环保部门和建设单位的要求,配备人员开展工作,做到环保工作有人负责、定期检查。

7.2严格按建设单位要求和设计文件规定组织施工,每一个工程项目、每道工序,均按环保要求采取相应的保护措施。

7.2.1按批准的施工组织设计布置各种临时设施,加强管理,保持施工区和生活区的文明整洁。

7.2.2不干扰正常交通,并防止对周围的污染和堵塞。

7.3按照政府的有关规定,结合本合同段工程实际,参加施工的队伍都要制定好文明施工的内部管理措施,确保施工现场周围道路畅通,排水系统经常处于良好状态,保持场容场貌整洁。

7.4减少噪声污染

7.4.1各种临时设施和场地,如堆料场、加工场等距居民区不小于300m,而且设于居民区主要风向的下风处。

7.4.2机械设备尽量减少噪声、废气等的污染;建筑施工场地的噪声符合《建筑施工场地界噪声限值》(GB12523-1990)的规定,并遵守当地有关部门对夜间施工的规定。

7.5泥浆处理:

钻孔泥浆外运采用自卸车,车斗密闭,外罩蓬布,保证运输过程中不漏浆,并在场内设置一套清洗设备,装载泥浆的设备在场内清洗干净后驶出场外。钻渣按指定地点集中存放。

本工程全部完成撤离施工现场前,按照建设单位要求,清理现场,做好一切善后工作。

下载钻孔灌注桩施工专项安全方案(大全5篇)word格式文档
下载钻孔灌注桩施工专项安全方案(大全5篇).doc
将本文档下载到自己电脑,方便修改和收藏,请勿使用迅雷等下载。
点此处下载文档

文档为doc格式


声明:本文内容由互联网用户自发贡献自行上传,本网站不拥有所有权,未作人工编辑处理,也不承担相关法律责任。如果您发现有涉嫌版权的内容,欢迎发送邮件至:645879355@qq.com 进行举报,并提供相关证据,工作人员会在5个工作日内联系你,一经查实,本站将立刻删除涉嫌侵权内容。

相关范文推荐

    钻孔灌注桩基础施工方案

    钻孔灌注桩基础施工方案 一、一般规定 1、施工前必须将桩周围地坪整好。场地平整及范围应根据地形、施工水位、桩顶标高、施工需要等因素考虑。 2、在平整好的场地上,依据已......

    钻孔灌注桩施工安全操作规程

    钻孔灌注桩施工安全操作规程1、钻机应放置平衡、坚实。钻机机械就位后,应对钻机及配套设备进行全面检查。钻机安设必须平稳、牢固;钻架应加设斜撑或缆风绳。2、冲击钻孔,选用的......

    钻孔灌注桩施工常见问题

    钻孔灌注桩施工常见问题 原因分析及防治措施 许陴拣 (北京城建五建设工程有限公司) 摘要:钻孔灌注桩具有抗震性好、施工噪声低、承载力大、对周围环境影 响小等优点,在各......

    钻孔灌注桩施工作业指导书

    钻孔灌注桩施工作业指导书1.准备作业劳动力组织:桥梁工,架工,电焊工,钢筋工。1.1机具设备:钻机,抽水机,搅拌机,吊装设备。1.2施工安全及劳动保护1.3施工安全1.3.1.1工作台搭设平稳,并......

    钻孔灌注桩施工合同

    设计试桩施工合同发包方:(以下简称甲方) 承包方:(以下简称乙方) 依照《中华人民共和国合同法》、《中华人民共和国建筑法》及其他有关法律、行政法规,遵循平等、自愿、公平和诚实守......

    钻孔灌注桩冬季施工方案(精选五篇)

    冬季施工方案 一、编制依据 《建筑工程冬期施工规程》(JGJ-104-97) 《混凝土结构工程施工质量验收规范》(GB50204-2002) 《房屋建筑工程技术资料管理规程》(DB15/427—2005) 《岩......

    钻孔桩安全专项施工方案

    牙克石至海拉尔高速公路土建工程 第七合同段钻 孔 桩 安 全 专 项 施 工 方 案吉林省亨通公路建设集团有限责任公司 第七合同段项目经理部 二0一一年五月二十日钻孔桩安全专......

    钻孔灌注桩施工安全技术保证措施

    钻孔灌注桩施工安全技术保障措施 第一章 钻孔桩施工安全技术措施 为确保桩基的安全生产,实现我项目部的安全目标,对钻孔灌注桩工程制定以下安全技术措施: 一、孔口护筒制作、埋......